RES-2012-018 Resolution 2012- 018
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ANAHEIM CERTIFYING THAT ANAHEIM HAS THE
RESOURCES TO FUND THE PROJECTS SUBMITTED FOR
INCLUSION IN THE FY 2012/13- 2017/18 TRANSPORTATION
IMPROVEMENT PROGRAM AND AFFIRMING ITS
COMMITMENT TO IMPLEMENT ALL OF THE PROJECTS
SUBMITTED IN THE PROGRAM
WHEREAS, City of Anaheim (ANAHEIM) desires to include the submitted
projects, set forth in Exhibit "A," attached hereto and incorporated herein by reference, in the
Orange County Transportation Authority's ( "OCTA ") Federal Transportation Improvement
Program; and
WHEREAS, ANAHEIM warrants that full funding is committed and available for
Projects submitted for programming in the first four years (FY 2012/13 through FY 2017/18) of
the Regional Transportation Improvement Program; and that ANAHEIM accepts responsibility
for full funding of said Projects and warrants that no additional funding allocations are required
of OCTA for ANAHEIM to fully implement said Projects therefore committing that the first
three years of the RTIP are financially constrained; and
WHEREAS, Projects programmed in years 2012/13 — 2017 /18 are Projects
expected to receive future funding through anticipated revenues, therefore, all Projects submitted
for inclusion in the 2013 FTIP are financially constrained; and
WHEREAS, OCTA as the agency responsible for short-range capital and service
planning and programming for the Orange County area, requires an approved Resolution from
the governing body of the Lead Agency for all Projects included in the Transportation
Improvement Program; and
WHEREAS, OCTA also requires that the Lead Agency include a financial plan
that demonstrates how the Projects submitted for inclusion in the Transportation Improvement
Program can be implemented; and
WHEREAS, the City of Anaheim, as the Lead Agency, possesses the legal
authority to submit the Projects for inclusion in the Transportation Improvement Program and to
finance, acquire, and construct the Projects.
NOW, THEREFORE, BE IT RESOLVED that the City Council of ANAHEIM
does hereby:
Affirm its continuing commitment to the Projects submitted for inclusion in the
2013 Federal Transportation Improvement Program; and
Commit that the City of Anaheim, as Lead Agency for the Projects, will carry out
the Projects consistent with the project implementation schedule; and
Certify that the City of Anaheim will enter into a contract with OCTA committing
that it will carry out the Projects identified as transportation control measures (TCM) in the
South Coast Air Basin consistent with the project implementation schedule; and
Certify that the City of Anaheim will allocate the necessary local match funds
contained within the project to carry out any federally approved project; and
Certify that the City of Anaheim, as the Lead Agency, will comply with
applicable provisions of the California Environmental Quality Act, the National Environmental
Policy Act, the Americans with Disabilities Act, the Secretary of the Interior's Standards and
Guidelines for Archaeology and Historic Preservation, and any other Federal, State, and /or local
laws, rules and regulations.
THE FOREGOING RESOLUTION is approved and adopted by the City Council
of the City of Anaheim this 28th day of February, 2012, by the following roll -call vote:
AYES: Mayor Tait, Council Members Galloway, Sidhu, Eastman and Murray
NOES: None
ABSTAIN: None
ABSENT: None
('/Z
MA OR OF THE CITY OF ANAHEIM
ATTES
r "4.0
CITY CLERK OF THE CITY 1J ANAHEIM
88203.1/bmorley
EXHIBIT A
PROJECT
PROJECT TITLE 0 STATUS COMPLETION
DATE
GENE AUTRY WAY WEST @ 1 -5 (1 -5 HOV TRANSITWAY TO HASTER) ADD
OVERCROSSING ON 1 -5 (S) /MANCHESTER AND EXTEND GENE AUTRY WAY PROGRAMMED Nov. 2012
WEST FROM 1 -5 TO HASTER (3 LANES IN EA DIR.)
SR -91 /GYPSUM CANYON ROAD INTERCHANGE. WIDEN GYPSUM CANYON
ROAD FROM 2 TO 4 LANES. ADD CLASS II ON -ROAD BIKE LANES, ADD PROGRAMMED Dec. 2019
MULTI USE TRAIL AND SIDEWALK ON WE
ANAHEIM FIXED GUIDEWAY PROGRAMMED March 2013
(Design)
DEVELOP AND IMPLEMENT AN ITS MASTER PLAN IN ANAHEIM PROGRAMMED Sept. 2012
ANAHEIM REGIONAL TRANS INTERMODAL CENTER (ARTIC) - INCLUDE
EXPAND OF EXIST AMTRAK /METROLINK STATION AT ANA STAD TO PROGRAMMED June 2018
PROVIDE ACCESS W/ TRANS SVC
BROOKHURST STREET WIDENING FROM S/0 BALL ROAD TO N/O KATELLA PROGRAMMED Jan. 2014
AVENUE
KATELLA AVE SMART ST (HUMOR TO JEAN) COMPLETED Nov. 2010