PC 2015/03/09-Presentation on Park FeesCOMMUNITY SERVICES DEPARTMENT
PARKS CAPITAL DEVELOPMENT
1
Planning Commission March 9. 2015
This presentation will provide an overview of how the Community Services Department plans for the recreational facility needs for the residents of Anaheim. Focusing on funding generated
in the four districts, I will review how fees are collected, recent park and trail improvements and highlight upcoming projects that staff will be recommending.
The Anaheim Outdoors Connectivity Plan was approved by Council in April of 2013. this plan serves as the guiding principals for capital development for parks, trails and bikeways and
includes helpful items such as a plant palette. This planning document was funded through two grants: the Urban Greening Planning Grant funded through state proposition 84 and a grant
through the Southern California Association of Governments.
Staff has used this plan as the basis to revise the Bikeway Master Plan and associated General Plan update. This update will come before this commission in the near future for approval.
1
Park development fee process –
quimby act
2
Colony Park
To fund the development of new parks and provide for the addition of new amenities in existing parks, the Community Services Department receives park development fees from new residential
development projects built in the City in accordance with a State law called the Quimby Act. The California Legislature first established the Quimby Act in 1975 and it was amended in
1982.
2
Quimby ACT EQUATION
3
(L+D) SP
------------
1,000
L = Land (average acquisition cost per acre)
D = Development cost per acre
S = Standard (2.0 acres per 1,000 population)
P = Persons per dwelling unit (1.50 persons/Platinum Triangle dwelling unit)
The City of Anaheim has adopted an ordinance, which is set forth in Anaheim’s Municipal Code, enacting its own version of the Quimby Act. This ordinance requires, as a condition of
approval of a subdivision, the dedication of land, the payment of a fee in lieu of dedication, or a combination of both for park or recreational purposes. Over the years, the City
has benefitted from the Quimby Act through all three of these methods.
This slide illustrates the formula used to determine the amount of funding to be received from developers when a specific housing development is approved for construction.
Our ordinance specifies the cost of land and land development and the park standard. The density varies for type of development.
The Quimby Act also serves as a vital resource for the City to provide our residents with upgrades to existing parks like new restrooms, upgraded playgrounds, and other amenities. The
Community Services Department also aggressively pursues grant funding to fund new park amenities.
Extra notes
In June 2011 the council approved $635,000 for development and $2,940,300 for land cost
Actual Cost of development is $1.5 million
3
Platinum Triangle Park Fees – Fund 471
Residential unit $8,114.01
West, Central, and East City Park Fees – Fund 216
Single Family detached unit $6,936.46
Single Family attached unit $5,388.14
Apartments: 2-4 units $6,998.39
Apartments: 5 or more units $5,408.78
Mobile home unit $4,149.49
PARK DEVELOPMENT FEES
4
In Anaheim, park development fees fall into two general categories; fees received from housing development within the Platinum Triangle (Fund 471) and fees received from development
outside of the Platinum Triangle (Fund 216). These fees have not changed since 2005.
4
PARK ACREAGE STANDARDS
5
NATIONAL STANDARD: 6.25 TO 10.5 ACRES PER 1,000 RESIDENTS
QUIMBY ACT STANDARD: 3.5 ACRES PER 1,000 RESIDENTS
ANAHEIM’S STANDARD BY ORDINANCE: 2.0 ACRES PER 1,000 RESIDENTS
ANAHEIM’S CURRENT RATIO: 1.9 ACRES PER 1,000 RESIDENTS
As the City’s population has grown, so has the need for additional parkland. The national standard for park acreage is 6.25 to 10.5 acres of developed park land per 1,000 people, and
the Quimby Act specifies 3.5 acres per 1,000 people. Anaheim’ standard is 2 acres per 1,000 residents and is currently at approximately 1.9 acres per 1,000 people.
These acres only include City owned and operated parks. It does not include County or State Parks or trails or school properties even with joint use agreements. This does include open
space areas such as Deer Canyon, Pelanconi Park or Oak Canyon.
5
PARK DEVELOPMENT FEES by boundaries
6
Park development fees are divided into four zones; Platinum Triangle, West, Central and East. This map illustrates the park development zones within the City. The Quimby Act specifies
that park fees received in a particular area are spent on improvements in the area in which the fees are received within 5 years. The amount and location of land to be dedicated or
the fees to be paid shall be in sufficient proximity to the subdivision to serve those future residents. The Quimby Act Funds cannot be used for operations or maintenance, to purchase
materials and supplies, or to replace maintenance equipment.
6
Completed park projects on the west side
7
West Anaheim Youth Center
Twila Reid Park renovated restroom and community room
Schweitzer Park lighting, restroom, and playgrounds
Carbon creek bike path connecting Schweitzer Park and school to West Anaheim Youth Center
Maxwell Park Expansion
John Marshall Park playground
Modjeska Park restroom
Modjeska Park playground
7
park projects in progress on the west side
8
Twila Reid Park playground and other improvements
Chaparral improvements at former wading pool
New Park at Circle Park
Improvements at Brookhurst Community Center
8
Potential park projects on the west side
9
Expansion of the SCE easement
Expansion of the Carbon Creek bike path
Therapeutic Center at Brookhurst
Fully accessible Playground at Brookhurst
9
Completed park projects in central
10
Willow Park restroom
Palm Lane Park playground
New Park at Energy Field
Stoddard Park playground
Founders’ Park
Colony Park
Paul Revere Park
Pioneer Park playground and accessible field
Edison Park restroom, playground and exercise equipment
La Palma Park - Dog Park
10
park projects in progress in central
11
Sage Park restroom, playground and picnic area
Stoddard Park restroom
Building renovation at Manzanita
Edison Park walking path and exercise equipment
Miraloma Park and Community Center
Exercise equipment at the Downtown Community Center
Pearson Park Cactus Garden
Shade Structure at Founders’ Park
11
Potential park projects in central
12
Pioneer restroom replacement
La Palma Park west side renovation
Lincoln Park improvements
12
Completed park projects on the east side
13
East Anaheim Gym, Community Center and Library
Roosevelt Park
13
park projects in progress on the east side
14
Olive Hills Park -Dog Park
Pelanconi Park Stream Restoration
14
Potential park projects on the east side
15
New park adjacent to Canyon Library
15
Completed park projects near platinum triangle
16
Boysen Park playground
Anaheim Coves
Magnolia Park
The original Environmental Impact Report for the development of the Platinum Triangle specifies that fees and limited dedication of park land received from residential construction would
be used for the development of park amenities in the Platinum Triangle. The EIR also addressed the impact on three parks located just outside of the Platinum Triangle’s boundaries
by stating that “the Proposed Project will significantly increase usage at existing City parks and recreational facilities, including Ponderosa Park, Juarez Park, and Boysen Park.”
Subsequent legal opinions received from the City Attorney’s Office have interpreted that park fees from housing developments inside of the Platinum Triangle can be used to upgrade the
facilities in the these three parks, as well as the development and purchase of new recreational sites in the Platinum Triangle’s “sphere of influence” just outside of the area’s boundaries.
16
projects in progress near platinum triangle
17
Anaheim Coves Extension
Ponderosa Park and Family Resource Center
Ponderosa Skate Park
New park at SCE easement
Tens of millions of funds could be generated from residential developments in the platinum triangle
17
Potential projects near platinum triangle
18
Purchase and Development of the Ball Road Basin
Boysen Park Tennis Center Renovation
Boysen Master Plan
Juarez Master Plan
New joint use school/park
New Community Center/Library
Developer Parks
Tens of millions of funds could be generated from residential developments in the platinum triangle
18
Comments & Questions
19
Founders’ Park
That concludes my presentation with thanks to my colleagues who coordinated it’s development and to all of you for your attention to this issue. I would welcome your questions and comments.
19