87-037RESOLUTION NO. 87-37
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ANAHEIM FINALLY ACCEPTING THE COMPLETION OF A
CERTAIN PUBLIC WORK. (INSTALLATION OF ELEVATOR
IN THE SENIOR CITIZENS CENTER BUILDING)
WHEREAS, the City Council of the City of Anaheim did
cause to be published in the Anaheim Bulletin on the Publication
Dates set forth in Exhibit A, a notice which: invited sealed
proposals for the public work (Project) as described in Exhibit A
in accordance with the designs, plans, profiles and specifications
prepared by the Public Works Department; declared that said
proposals would be received up until 2:00 o'clock P.M. on the Bid
Opening Date set forth in Exhibit A; stated that, pursuant to the
provisions of Section 1770 of the Labor Code, the City Council of
the City of Anaheim had ascertained the prevailing rate of wages
for each type of labor needed to execute said Project; and stated
that the prevailing hourly wage scale so ascertained was on file
in the Office of the City Clerk; and
WHEREAS, on the Bid Opening Date at the hour of 2:00
o'clock P.M., the City Clerk and the City Engineer of the City of
Anaheim did open said sealed proposals received up to that time
for the furnishing of all plant, labor, services, materials and
equipment, and ail utilities and transportation, including power,
fuel and water, and performing ali work necessary to construct and
complete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, the Project
hereinabove more particularly described and set forth, in public,
in the City Council Chamber in the City Hall, Anaheim, California,
and the City Engineer did tabulate the result of said sealed
proposals and did make a report to the City Council at a meeting
held no later than thirty (30) days after the bids were opened; and
WHEREAS, the City Council of the City of Anaheim did
consider the sealed proposals submitted for furnishing the
materials and performing the work hereinabove more particularly
described and set forth, and did thereupon find and determine that
the sealed proposal submitted by the Lowest and Best Responsible
Bidder set forth in Exhibit A for the construction, installation
and completion of said Project hereinabove mentioned and
described, was the lowest and best responsible proposal submitted
therefor, and thereupon accepted said bid and did award a contract
to said contractor for furnishing all plant, labor, services,
materials and equipment and all utilities and transportation,
including power, fuel and water, and performing all work necessary
to construct and complete, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings, the
said Project as specified in said notice inviting sealed
proposals, and did authorize the Mayor and the City Clerk of the
City of Anaheim to execute a contract for and on behalf of the
City of Anaheim with said contractor; and
WHEREAS, the said contractor has furnished all plant,
labor, services, materials and equipment and all utilities and
transportation, and performed all work necessary for the
construction and completion, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings of
said Project as specified in the notice inviting sealed proposals
and in the detailed designs, plans, drawings and specifications
prepared by the Public Works Department, and the contract made and
entered into with said contractor by the City of Anaheim; and
WHEREAS, the City Engineer has duly certified to the
construction and completion of said Project hereinabove mentioned
and described, in accordance with the plans and specifications and
the contract documents duly made and entered into with said
contractor; and
WHEREAS, the City Council finds that said contractor has
completed said Project hereinabove more particularly described in
accordance with the provisions of the contract and the contract
documents, and that notice of completion should be filed and
payment of the balance due said contractor authorized in
accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Anaheim that all plant, labor, services, materials and
equipment and all utilities and transportation, and the
performance of ail work necessary to construct, install and
complete in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together with
the appurtenances thereto, said Project hereinabove more
particularly described and set forth, in the City of Anaheim, by
said contractor, be, and the same are hereby, accepted subject,
nevertheless, to ail the terms, conditions and provisions of the
contract documents, and that the balance due said contractor for
said work be paid to said contractor thirty-five (35) days from
and after final acceptance of said work as evidenced by the
adoption of this resolution, but not sooner than thirty (50) days
after the date of the filing of notice of completion, excepting
only such sum or sums as may lawfully be withheld in accordance
with the provisions of said contract and contract documents. That
acceptance by the contractor of said payments made in accordance
with said final estimate shall operate and shall be a release to
the City of Anaheim, its officers, agents and employees from all
claims and liabilities due the contractor for anything done or
furnished or withheld or for anything relating to the work or any
act or neglect of the City, its officers, agents and employees,
excepting only claims against the City for amounts withheld by the
City at the time of such payment.
BE IT FURTHER RESOLVED that the Mayor be, and he is
hereby, authorized to execute completion of said work as required
by law.
--2-
BE IT FURTHER RESOLVED that the City Clerk be, and she is
hereby, directed to cause said Notice of Completion to be recorded
in the Office of the County Recorder within ten (10) days o£ the
date of this Resolution.
THE FOREGOING RESOLUTION is
City Council
1987.
approved and adopted by the
of the City of Anaheim this lOth day of February,
MAyOR 0F~T~ CI~TY 0 ANAHEIM
ATTEST:
CITY CLERK OF THE CITY OF ANAHEIM
/fi
6027M
020387
-3-
CLERK
STATE OF CALIFORNIA )
COUNTY OF ORA/~GE ) ss.
CITY OF A/~AHEIM )
I, LEONORA N. SOHL, City Clerk of the City of Anaheim, do hereby certify that
the foregoing Resolution No. 87R-37 was introduced amd adopted at a regular
meeting provided by law, of the City Council of the City of Anaheim held on
the 10th day of February, 1987, by the following vote of the members thereof:
AYES:
COUNCIL MEMBERS: Pickler, Hunter, Kaywood and Bay
NOES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEb~ERS: None
VACANCY: COUNCIL MEMBERS: One
AND I FURTHER certify that the Mayor of the City of Anaheim signed said
Resolution No. 87R-37 on the 10th day of February, 1987.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of the
City of Anaheim this 10th day of February, 1987.
CITY CLERK OF THE CITY OF ANAHEIM
(SEAL)
I, LEONORA N. $OHL, City Clerk of the City of Anaheim, do hereby certify that
the foregoing is the original of Resolution No. 87R-37 duly passed and adopted
by the Anaheim City Council on February 10, 1987.
CITY CLERK OF THE CITY OF ANAHEIM~
~XHIBIT A
~ROJECT:
Hydraulic passenger elevator in the Anaheim Senior Citizens Center
building located at 280 East Lincoln Avenue, in the City of Anaheim
consisting of construction of elevator pit, installation of
structural framing and drywall systems, minor HVAC work, associated
electrical services, and other miscellaneous revisions/remodeling
work and all appurtenant work as shown on the plans and delineated
in the specifications on file in the office of the City Engineer,
Account No. 25-807-7105-07060.
LOWEST AND BEST RESPONSIBLE BIDDER:
THE GORHAM COMPANY, INC.
1404 A S. Ritchey
Santa Ana, California 92705
PUBLICATION DATES:
BID OPENII4G DATE:
February 6 and February 13, 1986
February 27, 1986
PREVAILING WAGE RATE RESOLUTION NO: 86R-47
AWARD DATE:
March 25, 1986
AWARD RESOLUTION NO:
86R-108
CONTRACT PRICE:
EIGHTY THOUSAND SEVEN HUNDRED
NINETY-EIGHT DOLLARS ($80,798.00)
CONTRACT COMPLETION DAYS:
One Hundred (100)
LIQUIDATED DAMAGES:
ONE HUNDRED DOLLARS ($100.00) per
day