84R-018 RESOLUTION NO. 84R -18
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ANAHEIM FINALLY ACCEPTING THE COMPLETION AND
THE FURNISHING OF ALL PLANT, LABOR, SERVICES,
MATERIALS AND EQUIPMENT AND ALL UTILITIES AND
TRANSPORTATION INCLUDING POWER, FUEL AND WATER,
AND THE PERFORMANCE OF ALL WORK NECESSARY TO
CONSTRUCT AND COMPLETE THE FOLLOWING PUBLIC
IMPROVEMENT, TO WIT:
CENTRAL CITY - ANAHEIM BOULEVARD /ZEYN STREET
ALLEY IMPROVEMENT, IN THE CITY OF ANAHEIM,
ACCOUNT NO. 25- 793 - 6325- E3720.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
published and circulated in the City of Anaheim, to wit: The
Anaheim Bulletin, on the 21st and 28th days of July, 1983, a
notice inviting sealed proposals for furnishing the following:
All plant, labor, services, materials and equipment, and
all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct
and complete in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings
therefor on file in the Office of the City Engineer or
City Clerk of the City of Anaheim, the following public
improvement, to wit:
Central City - Anaheim Boulevard /Zeyn Street alley
improvement, in the City of Anaheim consisting of
clearing and grubbing; excavation; construction of P.C.C.
curb and alley; construction of asphalt concrete;
replacement of manhole frames and covers and cleanout
frame and cover; construction of sewer manholes;
constructionl of wood fences; and all appurtenant work as
shown on the plans and delineated in the specifications
on file in the office of the City Engineer, Account No.
25- 793 - 6325- E3720,
in accordance with the designs, plans, profiles and specifications
prepared by the Public Works Department, and the notice inviting
sealed proposals, which said notice specified that sealed
proposals as specified in said notice would be received up until
2:00 o'clock P.M. on the 18th day of August, 1983, and which said
notice did state and declare that, pursuant to the provisions of
Section 1770 of the Labor Code, the City Council of the City of
Anaheim had ascertained the prevailing rate of wages for each type
of labor needed to execute said contract, and did state that the
prevailing hourly wage scale so ascertained was on file in the
Office of the City Clerk; and
WHEREAS, on the 18th day of August, 1983, at the hour of
2:00 o'clock P.M., the City Clerk and the City Engineer of the
City of Anaheim did open said sealed proposals received up to that
time for the furnishing of all plant, labor, services, materials
and equipment, and all utilities and transportation, including
power, fuel and water, and performing all work necessary to
construct and complete, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings
therefor on file in the Office of the City Clerk of the City of
Anaheim, the public improvement hereinabove more particularly
described and set forth, in public, in the City Council Chamber in
the City Hall, Anaheim, California, and the City Engineer did
tabulate the result of said sealed proposals and did make a report
to the City Council at a meeting held no later than thirty (30)
days after the bids were opened; and
WHEREAS, the City Council of the City of Anaheim did, at
a subsequent regular or adjourned regular meeting, held on the 6th
day of September, 1983, at the hour of 1:30 o'clock P.M., consider
the sealed proposals submitted for furnishing the materials and
performing the work hereinabove more particularly described and
set forth, and did thereupon find and determine that the sealed
proposal submitted by NOBEST INCORPORATED & NODLAND, R. L. (J.V.),
Post Office Box 874, Westminster, California 92683, for the
construction, installation and completion of said Central City -
Anaheim Boulevard /Zeyn Street, in the City of Anaheim, alley
improvement, Project Account No. 25- 793 - 6325 -E3720 hereinabove
mentioned and described, was the lowest responsible proposal
submitted therefor, and thereupon accepted said bid and did award
a contract to said contractor for furnishing all plant, labor,
services, materials and equipment and all utilities and
transportation, including power, fuel and water, and performing
all work necessary to construct and complete, in a good and
workmanlike manner, in strict accordance with the specifications,
plans and drawings, the said public improvement as specified in
said notice inviting sealed proposals, and did authorize the Mayor
and the City Clerk of the City of Anaheim to execute a contract
for and on behalf of the City of Anaheim with said contractor,
which said contract was duly made and entered into on the 6th day
of October, 1983; and
WHEREAS, the said contractor has furnished all plant,
labor, services, materials and equipment and all utilities and
transportation, and performed all work necessary for the
construction and completion, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings of
said public improvement as specified in the notice inviting sealed
proposals and in the detailed designs, plans, drawings and
specifications prepared by the Public Works Department, and the
contract made and entered into with said contractor by the City of
Anaheim; and
-2-
WHEREAS, the Public Works Executive Director has duly
certified to the construction and completion of said public
improvement hereinabove mentioned and described, in accordance
with the plans and specifications and the contract documents duly
made and entered into with said contractor; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinabove more particularly
described in accordance with the provisions of the contract and
the contract documents, and that notice of completion should be
filed and payment of the balance due said contractor authorized in
accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Anaheim that all plant, labor, services, materials and
equipment and all utilities and transportation, and the
performance of all work necessary to construct, install and
complete in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together with
the appurtenances thereto, said public improvement hereinabove
more particularly described and set forth, in the City of Anaheim,
by said contractor, be, and the same are hereby, accepted subject,
nevertheless, to all the terms, conditions and provisions of the
contract documents, and that the balance due said contractor for
said work be paid to said contractor thirty -five (35) days from
and after final acceptance of said work as evidenced by the
adoption of this resolution, but not sooner than thirty (30) days
after the date of the filing of notice of completion, excepting
only such sum or sums as may lawfully be withheld in accordance
with the provisions of said contract and contract documents. That
acceptance by the contractor of said payments made in accordance
with said final estimate shall operate and shall be a release to
the City of Anaheim, its officers, agents and employees from all
claims and liabilities due the contractor for anything done or
furnished or withheld or for anything relating to the work or any
act or neglect of the City, its officers, agents and employees,
excepting only claims against the City for amounts withheld by the
City at the time of such payment.
AND BE IT FURTHER RESOLVED that the Mayor be, and he is
hereby, authorized to execute and file a notice of completion of
said work as required by law.
THE FOREGOING RESOLUTION is approved and adopted by the
City Council of the City of Anaheim this 17th day o anuary, 1984.
// e
MA R OF THE CITY OF ANAHEIM
ATTEST: !�
I'• . , . �7 %� ,
CITY LERK OF THE' CITY OF ANAHEIM
/fm
1925M
1/10/84 -3-
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF ANAHEIM )
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify that
the foregoing Resolution No. 84R -18 was introduced and adopted at a regular
meeting provided by law, of the City Council of the City of Anaheim held on
the 17th day of January, 1984, by the following vote of the members thereof:
AYES: COUNCIL MEMBERS: Kaywood, Bay, Overholt, Pickier and Roth
NOES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEMBERS: None
AND I FURTHER certify that the Mayor of the City of Anaheim signed said
Resolution No. 84R -18 on the 17th day of January, 1984.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of the
City of Anaheim this 17th day of January, 1984.
CITY LERK OF THE CI Y OF ANAHEIM
(SEAL)
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify that
the foregoing is the original of Resolution No. 84R -18 duly passed and adopted
by the Anaheim City Council on January 17, 1984.
41111 . 44P AILICIMariLl■
CITY CLERK