84R-319
,.....
.-
RESOLUTION NO.
84R-319
A RESOLUTIO OF THE CITY COUNCIL OF THE CITY OF
ANAHEIM FIN . LY ACCEPTING THE COMPLETION AND
THE FURNISH ~G OF ALL PLANT, LABOR, SERVICES,
MATERIALS D EQUIPMENT AND ALL UTILITIES AND
TRANSPORTAT ON INCLUDING POWER, FUEL AND WATER,
AND THE PER ORMANCE OF ALL WORK NECESSARY TO
CONSTRUCT COMPLETE THE FOLLOWING PUBLIC
IMPROVEMENT TO WIT:
.~
'\
OLIVE HILLS RESERVOIR STORM DRAIN CHANNEL
REPAIR, IN aE CITY OF ANAHEIM, ACCOUNT NO.
51-479-6329 l7280-708l0.
WHEREAS, th
cause to be publishe
published and circul
Anaheim Bulletin, on
sealed proposals for
All plant, labor
all utilities an
and water, and p
and complete in
accordance with
therefor on file
City Clerk of th
improvement, to
City Council of the City of Anaheim did
in a newspaper of general circulation,
ted in the City of Anaheim, to wit: The
the 1st and 8th days of March, 1984, inviting
furnishing the following:
services, materials and equipment, and
transportation, including power, fuel
rforming all work necessary to construct
good and workmanlike manner, in strict
he specifications, plans and drawings
in the Office of the City Engineer or
City of Anaheim, the following public
it:
Olive Hills Rese voir storm drain channel repair, in the
City of Anaheim, consisting of the construction of 54"
R.C.P., 48" spec'al wall R.C.P., P.C.C. transitions and
head walls, impor borrow and compacted fill, debris
cleaning and all other appurtenant work as shown on the
plans and de line ted in the specifications on file in the
Office of the Ci y Engineer, Account No.
51-479-6329-1728 -70810,
in accordance with t e designs, plans, profiles and specifications
prepared by the Publ'c Works Department, and the notice inviting
sealed proposals, wh'ch said notice specified that sealed
proposals as specifi in said notice would be received up until
2:00 o'clock P.M. on the 22nd day of March, 1984, and which said
notice did state and declare that, pursuant to the provisions of
Section 1770 of the abor Code, the City Council of the City of
Anaheim had ascertai ed the prevailing rate of wages for each type
of labor needed to e ecute said contract, and did state that the
prevailing hourly wae scale so ascertained was on file in the
Office of the City erk~ and
..-,.
,,.....
..-,
WHEREAS, on
2:00 o'clock P.M., t
City of Anaheim did
time for the furnish
and equipment, and a
power, fuel and wate
construct and comple
strict accordance wi
therefor on file in
Anaheim, the public
described and set fo
the City Hall, Anahe
tabulate the result
to the City Council
days after the bids
WHEREAS, th
a subsequent regular
10th day of April, 1
consider the sealed
materials and perfor
described and set fo
the sealed proposal
Box 549, Norco, Cali
tion and completion
channel repair, in t
17280-70810 hereinab
responsible proposal
said bid and did awa
ing all plant, labor
utilities and trans
performing all work
and workmanlike mann
tions, plans and dra
fied in said notice
the Mayor and the Ci
contract for and on
tractor, which said
18th day of May, 198
~
WHEREAS, th
labor, services, mat
transportation, and
tion and completion,
accordance with the
public improvement a
proposals and in the
fications prepared b
contract made and en
Anaheim~ and
.-.
the 22nd day of March, 1984, at the hour of
e City Clerk and the City Engineer of the
pen said sealed proposals received up to that
ng of all plant, labor, services, materials
1 utilities and transportation, including
, and performing all work necessary to
e, in a good and workmanlike manner, in
h the specifications, plans and drawings
he Office of the City Clerk of the City of
mprovement hereinabove more particularly
th, in public, in the City Council Chamber in
m, California, and the City Engineer did
f said sealed proposals and did make a report
t a meeting held no later than thirty (30)
ere opened~ and
City Council of the City of Anaheim did, at
or adjourned regular meeting, held on the
84, at the hour of 10:00 o'clock A.M.,
roposals submitted for furnishing the
ing the work hereinabove more particularly
th, and did thereupon find and determine that
ubmitted by STEVE PANDZA CONSTRUCTORS, P. O.
ornia 91760 for the construction, installa-
f said Olive Hills Reservoir storm drain
e City of Anaheim, Account No. 51-479-6329-
ve mentioned and described, was the lowest
submitted therefor, and thereupon accepted
d a contract to said contractor for furnish-
services, materials and equipment and all
rtation, including power, fuel and water, and
ecessary to construct and complete, in a good
r, in strict accordance with the specifica-
ings, the said public improvement as speci-
nviting sealed proposals, and did authorize
y Clerk of the City of Anaheim to execute a
ehalf of the City of Anaheim with said con-
ontract was duly made and entered into on the
~ and
said contractor has furnished all plant,
rials and equipment and all utilities and
erformed all work necessary for the construc-
in a good and workmanlike manner, in strict
pecifications, plans and drawings of said
specified in the notice inviting sealed
detailed designs, plans, drawings and speci-
the Public Works Department, and the
ered into with said contractor by the City of
-2-
r-
WHEREAS, th
certified to the con
improvement hereinab
with the plans and s
made and entered int
f~
WHEREAS, th
completed said publi
described in accorda
the contract documen
filed and payment of
accordance with the
NOW, THEREF
City of Anaheim that
equipment and all ut
ance of all work nec
good and workmanlike
fications, plans and
the City Clerk of th
ances thereto, said
larly described and
contractor, be, and
nevertheless, to all
contract documents,
said work be paid to
and after final acce
adoption of this res
after the date of th
only such sum or sum
with the provisions
acceptance by the co
with said final esti
the City of Anaheim,
claims and liabiliti
furnished or withhel
act or neglect of th
excepting only claim
City at the time of
.-
Public Works Executive Director has duly
truction and completion of said public
ve mentioned and described, in accordance
cifications and the contract documents duly
with said contractor~ and
City Council finds that said contractor has
improvement hereinabove more particularly
ce with the provisions of the contract and
s, and that notice of completion should be
the balance due said contractor authorized in
ontract documents.
RE, BE IT RESOLVED by the City Council of the
all plant, labor, services, materials and
lities and transportation, and the perform-
ssary to construct, install and complete in a
manner, in strict accordance with the speci-
drawings therefor on file in the Office of
City of Anaheim, together with the appurten-
ublic improvement hereinabove more particu-
et forth, in the City of Anaheim, by said
he same are hereby, accepted subject,
the terms, conditions and provisions of the
nd that the balance due said contractor for
said contractor thirty-five (35) days from
tance of said work as evidenced by the
lution, but not sooner than thirty (30) days
filing of notice of completion, excepting
as may lawfully be withheld in accordance
f said contract and contract documents. That
tractor of said payments made in accordance
ate shall operate and shall be a release to
its officers, agents and employees from all
s due the contractor for anything done or
or for anything relating to the work or any
City, its officers, agents and employees,
against the City for amounts withheld by the
uch payment.
AND BE IT F RTHER RESOLVED that the Mayor be, and he is
hereby, authorized t execute and file a notice of completion of
said work as require by law.
/,..-.....,
I
I
I
i
i
~
-3-
r-
,-"
THE FOREGO I
City Council of the
G RESOLUTION is approved and adopted by the
ity of Anaheim this 21st day of August, 1984.
MAYO~ !~
~
C
OF ANAHEIM
/fm
29l0M
8/14/84
.~
-4-
,.....
-,
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SSe
CITY or ANAHEIM )
i
I
I, LEONORA N. SOHL, City Cle1k of the City of Anaheim, do hereby certify that
the foreaoing Resolution No. 84R-3l9 was introduced and adopted at a regular
meetina pro~ided by law, of Ie City Council of the City of Anaheim held on
the 21st day of August, 1984 by the following vote of the members thereof:
,
"
AYES: COUNCIL MEMBERS: i Kaywood, Bay, Overholt, Pickler and Roth
i
i
NOES: COUNCIL MEMBERS: I None
1
ABSENT: COUNCIL MEMBERS: I None
AND I rURTHER certify that tie Mayor of the City of Anaheim signed said
Resolution No. 84R-3l9 on thf 21st day of August, 1984.
IN WIl'IIESS WHEREOF, I bave h~reunto set my band and affbed the seal of the
City of ADahe1.m this 21st dat of August, 1984.
~~~~
CITY CLERK OF THE CITY OF ANAHEIM
(SEAL)
i
I
I
I, LEOIORA N. SOHL, City cletk of the City of Anaheim, do hereby certify
the foregoing is the origina of Resolution No. 84R-3l9 duly passed and
adopted by the ADaheim City ouncil on August 21, 1984.
that
~~?L~
CITY CLERK
,
i