71R-180
.......
RESOLUTION NO. 71R-180
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE COMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR,
SERVICES, MATERIALS AND EQUIPMENT AND ALL
UTILITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND WATER, AND THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEMENT, TO WIT:
FURNISHING AND INSTALLING TRAFFIC SIGNALS AND
SAFETY LIGHTING AT THE INTERSECTION OF LA PALMA
AVENUE AND OLIVE STREET, IN THE CITY OF ANAHEIM,
WORK ORDER NO. 599-A.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
printed, published and circulated in the City of Anaheim, to
wit: The Anaheim Bulletin, on the 3rd and the 10th d~ys of
SeDt:ember , 19 70 , a notice inviting sealed
proposals for furnishing the following:
All plant, labor, services, materials and equipment, and
all utilities and transportation, including power, fuel
and water, and perfo~ing all work necessary to construct
and complete in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings
therefor on file in the Office of the City Engineer or
City Clerk of the city of Anaheim, the following public
improvement, to wit:
Furnishing and installing traffic signals at the
intersection of La Palma Avenue and Olive Street,
in the City of Anaheim, including safety lightinq,
and appurtenant work as more particularly set
forth in the plans and specifications on file in
the Office of the City Clerk or City Engineer,
Work Order No. 599-A.
in accordance with the designs, plans, profiles and specifica-
tions prepared by the Department of Public Works
and the notice inviting sealed proposals, which said notice
specified that sealed proposals as specified in said notice would
be received up until 2: 00 0' clock P.M. of the 17th day of
September , 19 70 , and which said notice did state and
declare that, pursuant to the provisions of Section 1770 of the
Labor Code, the City Council of the City of Anaheim had ascer-
tained the prevailing rate of wages for each type of labor needed
to execute said contract, and did state that the prevailing hourly
wage scale so ascertained was on file in the Office of the City
Clerk: and
,
-1-
""-"n
......
WHEREAS, on September 17 , 19 70, at the hour of
2:00 o.clock PcM~, the City Clerk and the City Engineer of
the City of Anaheim did open said sealed proposals received up
to that time for the furnishing of all plant,. labor, services,
materials and equipment, and all utilities and transportation,
including power, fuel and water, and performing all work neces-
sary to construct and complete, in a good and workmanlike manner,
in strict accordance with the specifications, plans and drawings
therefor on file in the Office of the City Clerk of the City of
Anaheim, the public improvement hereinabove more particularly
described and set forth, in public, in the City Council Chamber
in the City Hall, Anaheim, California, and the City Engineer did
tabulate the result of said sealed proposals and did make a
report to the City Council at its next ---.------- regular
meeting; and
WHEREAS, the City Council of the City' of Anaheim did,
at its next ----------- regular meeting, held on the 22nd
day of September ,19 70, at the hour of o. clock
P.Mo, consider the sealed proposals submitted for furnishing the
materials and performing the work hereinabove more particularly
described and set forth, and did thereupon find and determine that
the sealed proposal submitted by LOOP ELECTRIC, l3.657 Magnolia
Corona, California
for the construction, installation and completion of said traffic
s. na sand safet 1. htin at the intersection of La Palma Ave. and
Olive St.. Citv of Anaheim, w.o. i599-A here1nabove ment10ne
and described, was the lowest responsible proposal submitted
therefor, and thereupon accepted said bid and did award a contract
to said LOOP ELECTRIC
~or furnishing all plant, labor,
services, materials and equipment and all utilities and transpor-
tation, including power, fuel and water, and performing all work
necessary to construct and complete, in a good and workmanlike
manner, in strict accordance with the specifications, plans and
drawings, the said public improvement as specified in said notice
inviting sealed proposals, and did authorize the Mayor and the
City Clerk of the City of Anaheim to execute a contract for and
on behalf of the City of Anaheim with LOOP. .ELECTRIC
which said
contract was duly made and entered into on the 25th day of
September , 19~; and
WHEREAS, the said LOOP ELECTRI.C
has furnished all plant, labor,
services, materials and equipment and all utilities and trans-
portation, and performed all work necessary for the construction
'and completion, in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings of said
public improvement as specified in the notice" inviting sealed
proposals and in the detailed designs, plans, drawings, and
specifications prepared by ~hp ~epartmen~o~ ~li~ Wo~ks
, and the con~ract ma e an entered into
with it by the City of Anaheim; and
WHEREAS, th~ Director of Public Works
has duly certified to the construction and completion of said
public improvement hereinabove mentioned and described, in accord-
ance with the plans and specifications and the contract documents
duly made and entered into with said LOOP ELECTRIC
; and
-2-
~.:.:.:.. ~.,-. ......:......:...IIII.;........~
~
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particu-
larly described in accordance with the provisions of the contract
and the contract documents, and that notice of completion should
be filed and payment of the balance due said contractor authorized
in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the
perfo~ance of all work necessary to construct, install and com-
plete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together
with the appurtenances thereto, said public improvement herein-
above more particularly described and set forth, in the City of
Anaheim, by said contractor, be, and the same are hereby accepted,
subject, nevertheless, to all the terms, conditions and provisions
of the contract documents, and that the balance due said con-
tractor for said work be paid to it thirty-five (35) days
from and after final acceptance of said work as evidenced by the
adoption of this resolution, but not sooner than thirty (30) days
after the date of the filing of notice of completion, excepting
only such sum or sums as may lawfully be withheld in accordance
with the provisions of said contract and contract documents.
That acceptance by the contractor of said payments made in accord-
ance with said final estimate shall operate and shall be a release
to the City of Anaheim, its officers, agents and employees fram
all claims and liabilities due the contractor for anything done
or furnished or withheld or for anything relating to the work or
any act or neglect of the City, its officers, agents and em-
ployees, excepting only claims against the City for amounts with-
held by the City at the time of such payment.
AND BE IT FURTHER RESOLVED that the Mayor and the City
Clerk of the City of Anaheim be, and they are hereby authorized
to execute and file a notice of completion of said work as
required by law.
THE FOREGOING RESOLUTION is approved and signed by me
this 4th day of __ Ma~ ___, 19 71_.
,..'- _._'~
ATTEST:
~L:?tt o~~ti~ OF ANAHEIM
~~
ANAHEIM \ -
-3-
. ---..-........
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss .
CITY OF ANAHEIM )
-..
I, DENE M. DAOUST, City Clerk of the City of Anaheim,
do hereby certify that the foregoing Resolution No. 71R-180 was
passed and adopted at a regular meeting of the City Council held
on the 4th day of May , 19 71, by the following
vote of the members thereof: ---
AYES:
COUNCILMEN: Roth, Thom and Stephenson
NOES:
COUNCILMEN: None
ABSENT: COUNCILMEN: Pebley and Dutton
Pro-Tem
AND I FURTHER CERTIFY that the Mayor/Of the City of
Anaheim approved and signed said resolution on the 4t~ day of
May , 19~.
IN WITNESS WHEREOF, I have hereunto set my hand and
affixed the seal of the City of Anaheim this 4th day of
May , 19 71 .
~
i ~.$~
CI Y CLERK OF THE CITY OF ANAHEIM
(SEAL)
I, DENE M. DAOUST, City Clerk of the City of Anaheim, do hereby
certify that the foregoing is the original of Resolution No. 7lR-l80 duly
passed and adopted by the Anaheim City Council on May 4, 1971.
LC-~
M. LV~
City Clerk
~lo""lI;'" . ~ ~~....... . 1!000-- ......... .................-..~..-..-..~ ....-1:,", ._...........