86R-118
RESOLUTION NO. 86R--118
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ANAHEIM
AMENDING RATES, RULES AND REGULATIONS FOR THE SALE AND
DISTRIBUTION OF WATER AS ADOPTED BY RESOLUTION NO. 72R-600
AND AMENDED BY RESOLUTION NOS. 73R-255, 73R-38 7, 73R-532,
74R-433, 75R-3l5, 75R-469, 75R-479, 76R-378, 78R-4l8,
78R-4l9, 78R-459, 79R-643, 80R-304, 8lR-124, 8lR-402,
82R-355, 83R-33l AND 84R-246.
WHEREAS, the City of Anaheim maintains a water distribution system
for the furnishing of water to residents and inhabitants of the City of
Anaheim and has adopted Water Rates, Rules and Regulations for the sale and
distribution of water; and
WHEREAS, it is the policy of the City Council that Anaheim's Water
Utility shall be self-supporting from charges made by the City for water fur-
nished to consumers and for services rendered in connection therewith; and
WHEREAS, the Water System Facilities in the Anaheim Stadium Business
Center (ASBC) are not adequate to provide service to office and commercial
deve lopment and the Water Utility does not have funds available to finance
upgraded Facilities; and
WHEREAS, a reasonable estimate of the cost to upgrade water
facilities in the ASBC Area is approximately $7,000,000; and
WHEREAS, developer advances are reasonable where necessary to
prevent burden on rate payers; and
WHEREAS, a fee of $.80 per square foot of Gross Floor Building Area
is a reasonable estimate for developer contribution and it is appropriate for
the City Council to adjust Gross Floor Building Area fees from time to time.
NOW, THEREFORE BE IT RESOLVED by the City Counci 1 of the City of
Anaheim that the Water Rates, Rules and Regulations adopted by City Council
Resolution No. 72R-600 and amended by City Council Resolution Nos. 73R-255,
73R-387, 73R-532, 74R-433, 75R-3l5, 75R-469, 75R-479, 76R-378, 78R-4l8,
78R-4l9, 78R-459, 79R-643, 80R-304, 8lR-124, 8lR-402, 82R-355, 83R-33l, and
84R-246 be amended as follows, to wit:
1202b031386
3. 10. ')
BE IT FURTHER RESOLVED by the City Council of the City of Anaheim
that the amended Water Rates, Rules and Regulations be made effective for
service rendered on and after March 25, 1986.
THE FOREGOING RESOLUTION is approved and adopted by the City Council
of the City of Anaheim this 25th day of March 1986.
4~
ATTEST:
MAYOR OF THE CITY OF ANA
~~.-"---.---.'\
/ I
~~4 /{~
CITY CLERK OF THE CITY OF ANAHEIM
1202h0313Rfi
1 In "
CLERK
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SSe
CITY OF ANAHEIM )
I, LEONORA N. SOHL, City Clerk of the City of Anaheim, do hereby certify that
the foregoing Resolution No. 86R-118 was introduced and adopted at a regular
meeting provided by law, of the City Council of the City of Anaheim held on
the 25th day of March, 1986, by the following vote of the members thereof:
AYES:
COUNCIL MEMBERS: Kaywood, Overholt, Bay, Pickler and Roth
NOES:
COUNCIL MEMBERS: None
ABSENT:
COUNCIL MEMBERS: None
AND I FURTHER certify that the Mayor of the City of Anaheim signed said
Resolution No. 86R-118 on the 25th day of March, 1986.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of the
City of Anaheim this 25th day of March, 1986.
~aA~
CITY LERK OF THE CITY OF ANAHEIM
(SEAL)
I, LEONORA N. SOHL, City Clerk of the City of Anaheim, do hereby certify that
the foregoing is the original of Resolution No. 86R-118 duly passed and
adopted by the Anaheim City Council on March 25, 1986.
\~C{ 1C ~~
CITY CLERK --
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd..
Anaheim, California 92805
WATER RATES, RULES
AND REGULATIONS
Page No. i i
RATES, RULES AND REGULATIONS
TABLE OF CONTENTS
TITLE
Title Page
Table of Contents
" " "
" " "
" " "
" " "
EFFECTIVE
DATE
12-19-72
PAGE NO.
1
3-18-86
7-01-84
"
11
iii
iv
v
V1
1.0.1
3-18-86
"
Water Utility Policy
12-19-72
Rate Schedules
7-15-80
2. O. 1
Schedule W-CA; Commodity Adjustment Clause
"" " " "
7-15-80
"
2.1.1
2.1.2
2.1.3
2.1.3.1
2.1.4
2.1.4.1
2.1.4.2
2.1.4.3
2.1.4.4
2.1.4.5
2.1.4.6
2.1.4.7
2.1.4.8
2.1.5
2.1.5.1
2.1.5.2
2.1.5.3
2.1.5.4
2.1.5.5
2.1. 6
2.1.7
" " " " "
" " " " "
" " " " "
" " " " "
" " " " "
" " " "
" " " "
" "
" "
" "
" "
" "
" "
" " "
." " "
" " "
" " " " "
" " " " "
" " " " "
Schedule W-PS; High Elevation Pumping
Surcharge
" " " " "
" " " " "
" " " " "
" " " " "
"
"
"
"
"
7-01-82
"
5-11-83
"
7-17-85
"
7-15-80
"
"
7-01-82
3-01-83
7-17-85
7-15-80
10-23-84
7-15-80
"
"
2.1.8
2.1.9
2.1.9.1
2.1.9.2
2.1.10
3-01-83
7-17-85
Schedule W-R; Residential Service -
Single-Family Accommodation
Schedule W-R; Residential Service -
Multi-Family Accommodation
Schedule W-G; General Water Service
Schedule W-RO; Residential Service -
Outside City Limits
7-01-84
2.2.1
"
2.3.1
2.4.1
"
"
ISSUED BY
Gordon W. Hoyt
Gener.al Manaqer
l197b03D86
3 18 86 (Continued) 86R-
Effective - - b R I . N
Y eso utlon o. 84 46
Superseding Resolution No. K L
2.5.1
2.5.2
, 3-18-86
Dated6 26 84
Date~. 10. 5
"
"
"
"
"
7-15-80
WAT-30
CITY OF ANAHEIM WATER RATES, RULES
Management Services Division AND REGULATIONS
200 S. Anaheim Blvd.. Page No. v
Anaheim, California 92805
RATES, RULES AND REGULATIONS
TABLE OF CONTENTS
(Continued)
EFFECTIVE
TITLE DATE PAGE NO.
Rule No. 15; Main Extensions ~26-73 3.15.1
" " " " " 7-01-84 3.15.2
" " " " " 7-01-78 3.15.2.1
" " " " " 6-26-73 3.15.2.2
" " " " 7-01-78 3.15.3
" " " " 7-01-84 3.15.3.1
" " " " 1l-01-79 3.15.4
" " " " 3.15.4.1
" " " 3.15.4.2
" " " 3.15.5
" " " 3.15.6
" " " 3.15.7
" " " 3.15.8
" " " 3.15.9
" " " 3.15.10
" " " 3.15.11
" " " 3.15.12
" " " " " " 3.15.13
" " " " " " 3.15.14
" " " " " 8-16-83 3.15.15
" " " " " " 3.15.16
" " " " " " 3.15.17
" " " " " 3.15.18
" " " " " 3.15.19
" " " " " 3.15.20
" " " " " 3.15.21
" " " " 3-18-86 3.15.22
" " " " 3.15.23
" " " " 3.15.24
" " " " " 3.15.25
" " " " " 3.15.26
" " " " " 3.15.27
" " " " " 3.15.28
" " " " " " 3.15.29
Rule No. 16; Service Connections, Meters,
and Customer Facilities 7-01-84 3.16. 1
" " " " " " " 3.16.2
" " " " " " " 3.16.3
" " " " " " 12-19-72 3.16.4
" " " " " " " 3.16.5
Rule No., 17 ; Meter Tests and Adjustment of
Bills for Meter Errors 7-13-82 3.17.1
" " " " " " " " " 3.17.2
(Continued)
ISSUED BY
Gordon W. Hoyt
Gener.al Manager
WAT-30 1197b031386
Effectl've 3-18-86 b R I . N 86R-
y eso utlon o.
Superseding Resolution No. R4R-?4h
3-18-86
Dated
Dated6-?h-R4
3.10.5
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd.
Anaheim, California 92805
WATER RATES, RULES
AND REGULATIONS
Page No.
vi
RATES, RULES AND REGULATIONS
TABLE OF CONTENTS
(Continued)
TITLE
Rule No. 18; Service to Separate Premises and
Multiple Units, and Resale of Water
EFFECTIVE
DATE
PAGE NO.
12-19-72
3.18.1
Rule No. 19;
Measurement of Service
12-19-72
3.19.1
Rule No. 20;
" " "
Fire Protection
" "
8-26-81
12-19-72
3.20.1
3.20.2
ISSUED BY
Gordon W. Hoyt
Gener.al Manager
WAT-30 1197b031386
Effective3-18-86 by Resolution No. 86R-
Superseding Resolution No. 84R-246
Dated3-18-86
Dated6-26-84
3.10.5
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd..
Anaheim, California 92805
WATER RATES, RULES
AND REGULATIONS
Page No. 3.15.22
RULE NO. 15
MAIN EXTENSIONS
(Continued)
D. Anaheim Stadium Business Center Water Facilities
The cost of upgrading all water facilities serving the Anaheim Stadium
Business Center (Stadium Area) as defined herein shall be paid for by the
owners or developers of property requiring such facilities. The procedure set
forth herein provides that the person who develops a parcel of property within
the Stadium Area, other than for permitted primary industrial uses as provided
in Section D.ll, shall pay his proportional share of the cost of facilities in
the form of Gross Floor Building Area (GFA) fees. Other fees, which are
covered in the City's Water Rates, Rules, and Regulations shall also be
applicable.
1. Definition of Terms
a. Advance - The payment required for financing the installation of
upgraded water facilities within the Stadium Area.
b. City - The City of Anaheim, California, a municipal corporation.
c. Commercial or Office Development - Any buildings or structures within
the Anaheim Stadium Business Center hereafter constructed, enlarged,
or modified in use wherein the proposed use is changed to a more
intensive use.
d. Competitive Bidding Procedure The process of obtaining sealed
construction bids by the developer for a portion of the upgraded
water facilities. The bids must be obtained in a bid form and bid
items approved by the General Manager prior to soliciting for bids.
The developer must obtain a minimum of three bids. The developer
will not be allowed to award the contract and to proceed with the
water construction work, until the bids are submitted to the City and
the lowest responsible bid approved by the General Manager. The bids
obtained by the developer shall be from construction contractors
licensed by the State of California and qualified to perform water
construction work. The General Manager will have the authority to
reject all bids and request the developer to obtain additional bids.
If all bids submitted to the General Manager for approval are not
satisfactory the City reserves the option to solicit bids for the
work under established City advertising and awarding procedures.
(Continued)
ISSUED BY
Gordon W. Hoyt
Gener.al Manager
WAT-30 l197b031386
Effective 3-18-86 by Resolution No.
Superseding Resolution No.
86R-
Dated 3-18-86
Dated
3.10.5
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd..
Anaheim, California 92805
WATER RATES, RULES
AND REGULATIONS
Page No. 3.15.23
D. Stadium Area Water Facilities (continued)
e. Developer/Applicant The person, association,
governmental agency applying for water service.
corporation or
f. General Manager
Manager.
The City of Anaheim Public Utilities General
g. Gross Floor Building Area Fees - Gross Floor Building Area (GFA) fees
shall be the rate to be charged per Gross Floor Building Area in
commercial and office developments within the Stadium Area.
h. Gross Floor Building Area of Applicant's Development The total
gross floor area as shown on the building plans submitted to the City
for approval including any amendments, additions or revisions as may
be requested by the Applicant or the City, measured to the nearest
square foot.
~. Pay, Paid, Payment "Make satisfactory financial arrangements,"
"satisfactorily arranged for financially," and "satisfactory
financial arrangements," respectively, in addition to the accepted
meaning of these terms.
J. Projected Total Development - The Projected Total Development shall
be the incremental projected building square foot growth within the
boundaries of the Stadium Area projected by the Public Utilities
General Manager, for commercial and office space development measured
to the nearest square foot.
k. Stadium Area/Anaheim Stadium Business Center - That portion of the
service area bounded on the east by the Santa Ana River, on the south
by the Anaheim city limits, on the west by the Santa Ana Freeway, and
on the north by the Southern California Edison easement, which
easement is generally located parallel to and north of Katella Avenue.
1. Stadium Area Documents - Shall consist of Drawing Nos. W-2523 and
W-2524 delineating the boundary of the Stadium Area, location and
estimated or actual cost of upgraded water facilities and the GFA in
square feet. These documents shall be revised periodically to
reflect adjusted GFA, actual cost of facilities in place, current
cost estimates, and such other costs which may be incurred annually
in direct benefit of the Stadium Area.
m. Stadium Area Facility Fund - A fund into which the GFA Fees and
Advances are deposited and expenditures are made from in connection
with upgrading all water facilities in the Stadium Area. All
interest earned by monies in this fund shall remain in this fund.
Appropriate administrative and overhead costs shall be charged
against this fund by the Utility.
(Continued)
ISSUED BY
Gordon W. Hoyt
Gener.al Manager
Effective 3-18-86 by Resolution No.
Superseding Resolution No.
86R-
Dated
Dated
3-18-86
WAT-30
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd..
Anaheim, California 92805
D. Stadium Area Water Facilities (continued)
WATER RATES, RULES
AND REGULATIONS
Page No. 3.15.24
n. Upgraded Water Facilities Those facilities which have been
determined to be necessary to provide domestic and fire flows to the
Stadium Area, as shown on Drawing No. W-2523 on file at the City of
Anaheim, Public Utilities Department, Water Engineering Division.
o. Utility - The City of Anaheim, Public Utilities Department.
2. Computation of Fee
a. GFA Fees - Gross Floor Building Area fees shall be computed on the
basis of the estimated or actual costs of construction of the
upgraded Water Facilities divided by the Projected Total Development.
b. The following table shall be an official record of Gross Floor
Building Area fees as computed per section D.2.a.:
Date
Cost of
Upgraded Facilities
Square Feet
Fee
3-18-86
$6,999,000
8,755,000
$ .80
3. Application of Fee
a.
Each Developer shall pay an amount
calculated by multiplying the GFA fee
Area of the Applicant's Development.
for upgraded water facilities
times the Gross Floor Building
4. Advances
a.
When in the opinion of the General Manager,
provide proper service to an Applicant's
shall be required to advance funds as
construction of said facilities.
a facility is required to
property, the Applicant
herein provided for the
b. Advances for the upgraded water Facilities shall include only those
facilities shown on Drawings Nos. W-2523 and W-2524. Upgraded Water
Facilities costs shall be based on the General Manager's estimate,
the consulting design engineer's cost estimate, and the construction
bid or the final construction cost, depending on what state of
development the facilities are in. This cost shall include, but
shall not necessarily be limited to, the cost of engineering, land or
offsite right-of-way (including acquisition costs thereof), grading,
paving, telemetry, retaining walls, curbs and drainage facilities,
and the cost of all other improvements and overheads necessary in the
opinion of the General Manager, to make these facilities a permanent
operating water installation.
(Continued)
ISSUED BY
Gordon W. Hoyt
Gener.al MqnaQef
WAT-30 ll97bUJn~6
3-18-86
Effective by Resolution No.
Superseding Resolution No.
86R-
3-18-86
Dated
Datet 10.5
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd.
Anaheim, California 92805
D. Stadium Area Water Facilities (continued)
WATER RATES, RULES
AND R EGU LATIONS
Page No. 3.15.25
c. Primary main fees in the Stadium Area shall be treated ~n the manner
set forth ~n Rule IS-A.
d. Revision of Advances Due The General Manager shall revise the
Stadium Area GFA Documents periodically to reflect actual cost .of
facilities in place, current cost estimates and such other cost
adjustments which may be directly related to the Stadium Area.
e.
A cost adjustment
constructed based
cost index. The
adjusted GFA fee.
shall also be made for those facilities yet to be
on Engineering News Record's (ENR) construction
adjusted cost shall be used to determine the
f. Advances shall be computed as the remainder of costs detailed in
Section D.4.b. less Applicant's Gross Floor Building Area Fees
detailed in Section D.3.a.
g. Developers who advance funds shall be required to execute contracts
with the City of Anaheim for refunding as required by Section D.4.a.,
D.4.f., and D.S.a. through D.S.h.
h. In lieu of providing the Advances in accordance with Section D.4.f.,
the Applicant for water service that requires Stadium Area
Facilities, shall be permitted, if qualified in the judgment of the
General Manager, to construct and install the facilities himself, or
arrange for their installation pursuant to Competitive Bidding
Procedures. The cost, including the cost of inspection and
supervision by the Utility, shall be paid directly by Applicant. The
Applicant shall provide the General Manager with a statement of
actual construction cost in detail satisfactory to the General
Manager. The amount to be treated as an Advance subject to refund
shall be the lesser of (1) the actual cost, or (2) the price quoted
in the General Manager's detailed cost estimate. The installation
shall be in accordance with the plans and specifications approved by
the General Manager.
(Continued)
ISSUED BY
Gordon W. Hoyt
Gener.al Manager
WAT-30 l197b03l386
3-18-86
Effective by Resolution No.
Superseding Resolution No.
86R-
3-18-86
Dated
Dated
3.10.5
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd..
Anaheim, California 92805
WATER RATES, RULES
AND REGULATIONS
Page No. 3.15.26
D. Stadium Area Water Facilities (continued)
5. Refund of Advances
a.
Each Advance in excess of
subsequent Applicant's GFA
agreement between the Utility
the GFA Fees shall
Fees, in accordance
and the Developer.
be refunded from
with a written
b. The total amount of any refund to an Applicant shall not exceed the
amount of his Advance.
c. Refunds shall be subject to any existing Revenue Bond Covenants, and
shall be junior to any present or future bond and note payments.
d. The Utility shall make refunds to the Applicant who made an Advance,
or his assignee, until the amount of the Advance has been paid,
without interest.
e. When it has been necessary for the Utility to advance funds to alter
or add to the Stadium Area Facilities, funds available for refunds
will first be applied to the Utility's Advance before Section D.5.f.
is applicable.
f. Where two or more Applicants in the Stadium Area have paid Advances
in the Stadium Area, they shall each receive as refunds a
proportional amount of the funds received from GFA Fees.
g. The proportional yearly amount of refund is determined by by
multiplying the gross amount available for refund times a weighted
factor for each Applicant. The numerator of this factor is the
product of the Applicant's original Advance multiplied by the number
of years since the date of record of the Applicant's Advance. The
denominator of this factor is the sum of the numerators for all
applicants eligible for refunds. The number of years shall be
calculated to the nearest month.
h. The Utility shall make yearly refund payments to the eligible
Applicants in September of each year.
~. The first payment by the Utility for a developer's Advance shall be
made in September of the year following completion and acceptance by
the Utility of the upgraded water facility for which the Advance was
made.
(Continued)
ISSUED BY
Gordon W. Hoyt
Gener:al Manager
Effective 3-18-86 by Resolution No.
Superseding Resolution No.
86R-
3-18-86
Dated
Dated
1.10. c;
WAT-30
l197b031386
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd..
Anaheim, California 92805
D. Stadium Area Water Facilities (continued)
WATER RATES, RULES
AND REGULATIONS
Page No. 3. 15.27
6. Miscellaneous
a. Revision - The Utility reserves the right at any time to revise and
update the Stadium Area documents provided that such revision shall
not affect contracts which have been executed pursuant to this rule..
7. Ownership, Design and Construction of Stadium Area Facilities
a. Any Stadium Area Facilities installed hereunder shall become the sole
property of the Utility after acceptance by the City.
b. The design of Stadium Area Facilities shall be done by the Utility or
a consulting engineering firm retained by the Utility. The actual
construction shall be done by the Utility, a contractor employed by
the Utility, or by a contractor employed by the Applicant, as
outlined in D.4.h.
c. The construction of water facilities must be accomplished in
compliance with the requirements of any public authority having
jurisdiction in the area of work. Any additional costs incurred in
order to comply with these requirements shall become part of the
total cost of the water facility.
8. Estimates, Contract Documents, Plans and Specifications
a. Upon request by a potential Applicant for a Stadium Area Facility,
the Utility shall prepare, without charge a preliminary sketch and
rough estimates of the cost of installation to be advanced by said
Applicant.
b. Any Applicant for a Stadium Area Facility requesting the Utility to
prepare detailed plans, specifications and cost estimates shall be
required to deposit with the Utility an amount equal to the estimated
cost of preparation of such material. The Utility shall, upon
request, make available within a reasonable period after receipt of
the deposit referred to above, such plans, specifications and cost
estimates of the proposed Stadium Area Facility.
c. In the event a Stadium Area Facilities contract with the Utility is
executed within 180 days after the Utility furnishes the detailed
plans and specifications, the deposit shall become a part of the
Advance. If such contract is not so executed, the deposit to cover
the cost of preparing plans, specifications and cost estimates shall
be forfeited by the Applicant.
ISSUED BY
Gordon W. Hoyt
Gener:al Manager
WAT-30 ll97b03l386
(('''nt-~n"",rl)
Effective 3-18-86 by Resolution No.
Superseding Resolution No.
86R-
3-18-86
Dated
Dated
3.10.5
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd..
Anaheim, California 92805
D. Stadium Area Water Facilities (continued)
WATER RATES, RULES
AND REGULATIONS
Page No. 3.15.28
d. When detailed plans, specifications and cost estimates are requested,
the Applicant fora Stadium Area Facility shall furnish the Utility
accurate drawings showing site plan including Gross Floor Building
Area of the building (s) to be developed. If changes are made
subsequent to the presentation of these drawings by the Applicant,
and these changes require additional expense in revising contrac t
documents, plans, specifications and cos t estimates, this additiona 1
expense shall be borne by the Applicant, not subject to refunds.
9. Timing and Adjustment of Advances
a. Unless the Applicant for the Stadium Area Facilities elects to
arrange for the installation of the Stadium Area Facility, as
permitted by Section D.4.h., the full amount of the required Advance,
or an acceptable surety bond and/or letter of credit must be provided
to the Utility at the time of execution of a Stadium Area Facility
agreement prior to issuance of a building permit.
b.
An Applicant for Stadium Area Facilities may be
General Manager to deposit sufficient cash to cover
Stadium Area Facilities in advance of construction.
required by the
the cost of such
c. An Applicant for a Stadium Area Facility who advances funds shall be
provided by the Utility with a statement of actual costs. Said
statement shall be submitted within sixty days after the actual costs
of the installation have been determined by the General Manager.
d. Any differences between the actual costs and the amount advanced
shall be shown as a revision of the amount of Advance and shall be
payable by the developer or reimbursed by the City within thirty days
of date of submission of statement to the Applicant.
10. Special Conditions
a. Special Situations - Special conditions of service, facilities and
related matters applicable to these Rules and Regulations not
expressly covered, shall be resolved by the Utilities General Manager.
b. Exceptional Cases - In unusual circumstances, when the application of
these rules appears impractical or unjust, the Applicant may refer
the matter to the Utilities General Manager for special ruling, or
for the approval of special conditions, which are agreed upon, prior
to commencing construction. If the matter is not satisfactorily
resolved with the Utilities General Manager, the Applicant may
petition the City Council for final determination.
(Continued)
ISSUED BY
Gordon W. Hoyt
Gener.al Manager
WAT-30 l197b03l386
3-18-86
Effective by Resolution No.
Superseding Resolution No.
86R-
Dated
Dated
3.10.5
3-18-86
CITY OF ANAHEIM
Management Services Division
200 S. Anaheim Blvd..
Anaheim, California 92805
WATER RATES, RULES
AND REGULATIONS
Page No. 3.15.29
D. Stadium Area Water Facilities (continued)
11. Exemp t ions
a. Any structure or any portion thereof devoted to parking of
automobiles.
b. Conversion of a building or structure to a similar or less intensive
land use.
c. Reconstruction of any building or structure destroyed by fire or
other natural cause.
d. Any building or structure wherein the proposed use is a permitted use
under Section 18.61.020 of the ML (limited Industrial) Zone.
ISSUED BY
Gordon W. Hoyt
Gener.al Manager
WAT-30 l197b03l386
Effective 3-18-86 by Resolution No.
Superseding Resolution No.
86R-
3-18-86
Dated
Dated
3.10.5