Item No. 3 - DEV2021-00180 Lincoln Sunkist Townhomes 200 S. Anaheim Blvd. Suite #162 Anaheim, CA 92805 Tel: (714) 765-5139 Fax: (714) 765-5280 www.anaheim.net ITEM NO. 3 PLANNING COMMISSION REPORT City of Anaheim PLANNING AND BUILDING DEPARTMENT DATE: DECEMBER 5, 2022 SUBJECT: DEVELOPMENT APPLICATION NO. 2021-00180 CONDITIONAL USE PERMIT TENTATIVE TRACT MAP NO. 19237 LOCATION: This property is located at the southwest corner of Lincoln Avenue and Sunkist Street (2420-2450 East Lincoln Avenue). APPLICANT/PROPERTY OWNER: The applicant is KB Home, represented by John Abboud. The property owner is Albert & Sons Real Estate I, LLC., represented by Tracy Muller. The agent is Sagecrest Planning+Environmental represented by Laurel Reimer. REQUEST: The applicant requests approval of the following entitlements: 1) A Conditional Use Permit (CUP) to allow the construction of an 83-unit, attached single-family residential project with modified development standards (Attachment 1); 2) A Tentative Tract Map (TTM No. 19237) to permit a 1-lot 83-unit subdivision for condominium purposes (Attachment 2). RECOMMENDATION: Staff recommends that the Planning Commission approve the attached resolutions, determining that streamlined review pursuant to Section 15183.3 of the California Environmental Quality Act (CEQA) Guidelines is the appropriate environmental documentation for the proposed project, and approving the Conditional Use Permit and Tentative Tract Map No. 19237. BACKGROUND: This 4-acre property is located in the “C-G” General Commercial and Residential Opportunity (RO) Overlay Zones and is developed with two multi- tenant office buildings. The site is designated for Medium Density land uses by the General Plan. Single-family residential land uses are adjacent to the property to the south and across Lincoln Avenue to the north, commercial uses including a service station and car wash are located to the east across Sunkist Street, and multi-family residential uses are adjacent to the west. Development Application No. 2021-00180 December 5, 2022 Page 2 of 7 PROPOSAL: The applicant requests approval of a conditional use permit and a tentative tract map to construct 83 single-family attached townhomes (Residential Planned Unit Development) with modifications of development standards. The units would be divided throughout 10 buildings on the site with three of the buildings fronting Lincoln Avenue, one building facing Sunkist Street, and the remaining six spread out throughout the property. The project includes five floor plans consisting of two, three, and four-bedrooms. Depending on the placement, design, and orientation of the townhome, the front door would either face a common courtyard, pedestrian walkway, or public street. The street-facing units are designed with a stooped entrance that would lead to the front door or a private patio area. The project site would provide two vehicular access points from private drives that connect to Lincoln Avenue and Sunkist Street. The Lincoln Avenue driveway is located adjacent to the west property line. The second driveway is located near the southeast corner of the property. All units would include an attached two-car garage, and surface parking spaces would be provided along the south and east property lines. The units would contain between 1,415 and 1,834 square feet of living area. A total of 238 parking spaces would be provided for the project. Site Plan The common courts or alleyways have been designed to provide enhanced landscaping throughout the development. The main entrance to each of the units would also provide small planters that help soften the hardscape and create a formal entryway. A wide pathway is provided from each unit to the project’s pathways and sidewalks for safe and attractive pedestrian access. Four of the five common courts feature multi-colored pavement in a wave design to provide an extension of common open space areas. While this area is not counted towards the recreation-leisure area, the enhanced common courts provide over 10,000 square feet of additional area for residents to use. Development Application No. 2021-00180 December 5, 2022 Page 3 of 7 Plan Type Number of Units Square Footage Bedrooms/Bathrooms Plan 1 34 1,415 2/2.5 Plan 2 14 1,460 3/2.5 Plan 3 10 1,800 3/3.5 Plan 4 8 1,761 4/3.5 Plan 5 17 1,834 4/3.5 Plan Type Matrix The project would feature attractive and enhanced architectural elements including façade articulation, height variation, contrasting colors and materials, and dense landscaping in the setback and pedestrian access areas. The color palette would include a mix of whites, greys, and beiges, with red and brown accents. The first story would include stucco with stone veneer accents. Townhomes with second-story decks would have contrasting metal railings. Typical Elevation Lincoln Avenue Elevation Recreational-Leisure Area: The project exceeds the required amount of recreation-leisure space with 24,852 square feet including 15,627 square feet of common recreation-leisure area. Based on the unit count and a minimum of 275 square feet per unit, a total of 22,285 square feet is required. The common area amenities would include a tot lot, community barbeques, seating areas, a dog park, and a community garden. Private areas would include decks and ground floor patios at some of the units. FINDINGS AND ANALYSIS: Following is staff’s analysis and recommendation for each requested entitlement action: Development Application No. 2021-00180 December 5, 2022 Page 4 of 7 General Plan Housing Element: The Land Use Element of the City’s General Plan is the guide for the City’s future development. It designates the distribution and location of specific land uses and establishes the permitted densities for each land use designation. The General Plan designation of the project site Medium Density, and the zoning designation is C-G with a Residential Opportunity (RO) Overlay Zone. The purpose of the Residential Opportunity (RO) Overlay Zone is to provide “by-right” housing development opportunities consistent with a property’s residential General Plan land use designation. This Overlay Zone is intended to be applied to properties that are currently zoned and/or developed with non-residential uses, but designated for multiple-family residential uses by the City’s General Plan. The Overlay Zone is further intended to serve as an implementation tool of the City’s Housing Element of the General Plan by facilitating residential development on identified “housing opportunity sites.” This property is currently developed with commercial office uses, is designated in the General Plan for Medium Density Residential land uses, and qualifies for residential development under the RO Overlay Zone. Conditional Use Permit: The development of residential uses through implementation of the RO Overlay Zone must be in accordance with the uses and requirements set forth in the Zoning Code for Multiple-Family Residential Zones. Specifically, the project would be subject to the “RM-3.5” Multiple-Family Residential Zone requirements. Residential Planned Unit Developments of single-family attached units require a conditional use permit in the RM-3.5 Zone. Before the Planning Commission may recommend approval of the conditional use permit for the Residential Planned Unit Development, it must make a finding of fact that the evidence presented shows that all of the following conditions exist: 1) The uses within the project are compatible; 2) New buildings or structures related to the project are compatible with the scale, mass, bulk, and orientation of existing buildings in the surrounding area, provided the existing buildings conform with the provisions of this title; 3) Vehicular and pedestrian access are adequate; 4) The project is consistent with applicable design guidelines adopted by the City; 5) The size and shape of the site proposed for the use are adequate to allow the full development of the proposed use in a manner not detrimental to the particular area; 6) The traffic generated by the proposed use will not impose an undue burden upon the streets and highways designed and improved to carry the traffic in the area; 7) The project complies with the General Plan and any applicable zoning or specific plan; and 8) The granting of the conditional use permit under the conditions imposed, if any, will not be detrimental to the peace, health, safety, and general welfare of the citizens of the City of Anaheim. Modification of Development Standards: Setbacks for projects in the RM-3.5 Zone may be modified in conjunction with a conditional use permit when it is determined that the modifications achieve a good project design, privacy, livability, and compatibility with surrounding uses. The applicant requests to modify the minimum required setbacks between buildings to permit a 15-foot distance where the Zoning Code requires a 40-foot separation between three-story buildings with parallel walls that are designated as “primary” walls. Primary walls are building walls that contain an entrance and/or windows opening into living areas. The proposed project would provide Development Application No. 2021-00180 December 5, 2022 Page 5 of 7 reduced building-to-building setbacks of 15 feet at the narrowest point. The three-story primary building elevations would be separated by enhanced landscaped paseos and area landscape and would have adequate separation to ensure a quality living environment. The elevations would provide off-setting window locations for the upper floors while the first floor would have a solid wall where the garage and entry areas are located. The proposed modification would help achieve a functional, pedestrian-friendly design and provide for a high-quality living environment. This building-to-building setback request applies to the separation between Building E and Building F on the Lincoln Avenue Street frontage. Elevation Building E Window Placement The applicant is also requesting a 10-foot setback from ground floor patios where 20 feet would be required. The 10-foot encroachment into the required setback would allow for semi-private access to the front door of the units, thereby separating the units from the public sidewalk along Sunkist Street, while still maintaining adequate street connectivity, which would add to the livability and privacy of the proposed residences. Furthermore, staff believes this design would allow for a higher level of design around the grade difference that currently exists along the Sunkist frontage to the interior lot area. Staff believes that the findings can be met to approve the Residential Planned Unit Development. The use of the project site includes only single-family attached residences designed in a manner that the buildings are compatible with each other. The project is compatible with the scale, mass, bulk, and orientation of existing buildings in the surrounding area as the project has been designed so that the buildings are setback from the adjacent residential uses and buffered with landscaping, parking spaces, and drive aisles. The project includes adequate vehicle and pedestrian access, is consistent with the design guidelines, and the property is of a size that is adequate to allow the full development of the proposed use in a manner not detrimental to the particular area. Traffic generated by the proposed use will not impose an undue burden upon the streets and the project complies with the General Plan and the RO Overlay Zone. Staff believes that the granting of the conditional use permit under the conditions imposed, will not be detrimental to the peace, health, safety and general welfare of the citizens of the City of Anaheim and recommends that the Planning Commission approve this request. Development Application No. 2021-00180 December 5, 2022 Page 6 of 7 Parking Requirements: The Municipal Code requires 237 parking spaces for the proposed project. The project has been designed to exceed the required number of parking spaces with 166 spaces located in garages and 72 surface spaces for a total of 238 parking spaces. Tentative Tract Map: Before the Planning Commission may recommend approval of the tentative tract map, it must make a finding of fact that the evidence presented shows that all of the following conditions exist: 1) That the proposed subdivision of the Property, including its design and improvements, is consistent with the General Plan of the City of Anaheim, and more particularly with the "Medium Density Residential" land use designation. 2) That the proposed subdivision of the Property, as shown on proposed Tentative Tract Map No. 19237, including their design and improvements, is consistent with the zoning and development standards of the "RM-3.5" Multiple-Family Residential Zone, with the exception of the reduced building-to-building setback and street setback being proposed in conjunction with the Conditional Use Permit. 3) That the site is physically suitable for the type and density of the Proposed Project. 4) That the design of the subdivision, as shown on the proposed Tentative Tract Map No. 19237, is not likely to cause substantial environmental damage or substantially and avoidably injure fish or wildlife or their habitat, as no sensitive environmental habitat has been identified. 5) That the design of the subdivision, as shown on the proposed Tentative Tract Map No. 19237, or the type of improvements is not likely to cause serious public health problems. 6) That the design of the subdivision, as shown on proposed Tentative Tract Map No. 19237, or the type of improvements will not conflict with easements acquired by the public, at large, for access through or use of property within the proposed subdivision. A tentative tract map is proposed to create a 1-lot condominium subdivision for the 83 “airspace” condominium units. All common areas, including driveways, recreational areas, paseos, and sidewalks would be owned and maintained by the homeowner’s association. The proposed density of 20.75 dwelling units per acre is permitted under the Medium Density Residential land use designation, which allows up to 36 dwelling units per acre. In addition, the project does not conflict with easements acquired by the public and complies with all subdivision requirements. Therefore, staff recommends approval of the tentative tract map request. Community Outreach: The applicant hosted a community outreach meeting on October 18, 2022, from 6:00 p.m. to 8:00 p.m. at the Abraham Lincoln Elementary School. Additionally, the applicant also attended the District 5 Community Meeting on October 19, 2022, at the Anaheim United Methodist Church. The applicant provided a summary of each meeting, included as Attachment 6. Environmental Impact Analysis: A streamlined environmental review checklist was prepared pursuant to Section 15183.3 of the California Environmental Quality Act Guidelines to determine Development Application No. 2021-00180 December 5, 2022 Page 7 of 7 whether the proposed project would have any significant effects that the City, as Lead Agency, did not previously disclose in Environmental Impact Report Nos. 330 and 346 pursuant to Public Resources Code Section 21094.5. No new mitigation measures are being recommended to the Planning Commission as a result of this project. Several existing mitigation measures do apply to this project and are reflected in Mitigation Monitoring Plan No. 385, included with the checklist and reflected in the recommended conditions of approval. With implementation of these measures, and uniformly applicable development policies or standards, the project will not cause any new or more significant effects than previously disclosed by Environmental Impact Report Nos. 330 and 346 and no additional environmental review is required. CONCLUSION: Staff has carefully considered the proposed project and believes that it is compatible with the surrounding land uses and is designed in a manner that will provide a quality living environment for its future residents and the surrounding community. In addition, the proposed project meets the goals of the General Plan to continue to provide a variety of quality housing opportunities to address the City’s diverse housing needs, would provide housing in furtherance of the City’s Housing Element through the implementation of the Residential Opportunity (RO) Overlay Zone which is consistent with the City Council’s policy that identifies additional sites throughout the property for housing development opportunities. Prepared by, Submitted by, Ivan Orozco Scott Koehm, AICP Associate Planner Principal Planner Attachments: 1. Draft Conditional Use Permit Resolution 2. Draft Tentative Tract Map Resolution 3. Infill Streamlining Checklist 4. Project Description 5. Project Plans 6. Applicant Community Outreach Summary 7. Aerial and Vicinity Maps [DRAFT] ATTACHMENT NO. 1 - 1 - PC2022-*** RESOLUTION NO. PC2022-*** A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF ANAHEIM APPROVING A CONDITIONAL USE PERMIT AND MAKING CERTAIN FINDINGS IN CONNECTION THEREWITH (DEV2021-00180) (2420-2450 EAST LINCOLN AVENUE) WHEREAS, the Planning Commission of the City of Anaheim (the "Planning Commission") did receive a verified petition for a Conditional Use Permit to allow the construction of an 83-unit attached, single-family residential project with modified development standards, i.e., a reduction in the street landscape setback and building-to-building setback requirements of the "RM-3.5" Multiple-Family Residential Zone, for that certain real property generally located at the southwest corner of Lincoln Avenue and Sunkist Street and commonly referred to as 2420-2450 East Lincoln Avenue in the City of Anaheim, County of Orange, State of California, as generally depicted on the map attached hereto as Exhibit A and incorporated herein by this reference (the "Property"); and WHEREAS, a Conditional Use Permit is proposed in conjunction with a tentative tract map to permit a 1-lot, 83 unit attached single-family residential subdivision of the Property for condominium purposes, which is designated as "Tentative Tract Map No. 19237", and Development Permit No. 2021-00180. A Conditional Use Permit, Tentative Tract Map No. 19237, and Development Permit No. 2021-00180 shall be referred to herein collectively as the "Proposed Project"; and WHEREAS, the Property is approximately 4.0 acres in size and is currently developed with two commercial office buildings. The Land Use Element of the Anaheim General Plan designates the Property for Medium Density residential land uses. The Property is located in the “C-G” General Commercial zone. The development standards and regulations of Chapters 18.34 (Residential Opportunity (RO) Overlay Zone) and 18.06 (Multiple-Family Residential Zones) of the Anaheim Municipal Code (the "Code") shall apply to the Proposed Project consistent with the General Plan designation for the Property; and WHEREAS, single-family, attached dwelling developments within the RM-3.5 (Multiple- Family Residential) zone are subject to the approval of a conditional use permit by the Planning Commission pursuant to Table 6-A of Section 18.06.030 (Uses). Pursuant to subsection .030 of Section 18.06.160 (Residential Planned Unit Development), the minimum setbacks set forth in Section .090 of Chapter 18.06 (Multiple-Family Residential Zones) may be modified in order to achieve a good project design, privacy, livability, and compatibility with surrounding uses. If approved, the Conditional Use Permit will permit the reduction in building-to-building setbacks and street landscape setback; and WHEREAS, pursuant to and in accordance with the provisions of the California Environmental Quality Act (Public Resources Code Section 21000 et seq.; herein referred to as “CEQA”), the State of California Guidelines for Implementation of the California Environmental Quality Act (herein referred to as the "CEQA Guidelines"), and the City's CEQA Procedures, the - 2 - PC2022-*** City is the "lead agency" for the preparation and consideration of environmental documents for the Proposed Project; and WHEREAS, in May 2004, the City Council certified the General Plan and Zoning Code Update Program EIR No. 330 (EIR 330), which evaluated impacts associated with implementation of the Anaheim General Plan and Zoning Code Update and created a Mitigation Monitoring Program No. 122 to mitigate those impacts. The Property was designated for Low-Medium Density Residential land use as a part of the update; and WHEREAS, in September 2013, the City Council certified Supplemental Environmental Impact Report No. 346 (SEIR 346) for the Anaheim Housing Opportunities Site Rezoning. The City approved Mitigation Monitoring Program No. 122A as part of SEIR 346. SEIR 346 supplemented EIR 330 in the areas of air quality, greenhouse gas emissions, noise, and transportation and traffic. The Rezoning implemented a key strategy of the City’s 2006-2014 General Plan Housing Element by rezoning the properties identified as Housing Opportunities Sites in the Housing Element. The proposed rezoning of these approximately 166 sites allowed “by-right” housing development at these locations by applying one of two overlay zones to these properties: the Residential Opportunity (RO) Overlay Zone or the Mixed Use (MU) Overlay Zone. The Property was reclassified to the “RO” Overlay Zone as a part of the Rezoning Project; and WHEREAS, a streamlined review checklist was prepared pursuant to Section 15183.3 of the California Environmental Quality Act Guidelines to determine whether the project would have any significant effects that the City, as Lead Agency, did not previously disclose in Environmental Impact Report Nos. 330 and 346 pursuant to Public Resources Code Section 21094.5; and WHEREAS, in conformance with CEQA and the CEQA Guidelines, mitigation measures from Mitigation Monitoring Program No. 122A that are specific to the Proposed Project mitigation measures are reflected in Mitigation Monitoring Plan No. 385 (herein referred to as "MMP 385"). A complete copy of the Infill Streamlining Checklist including Appendices and MMP 385 is on file and can be viewed in the Planning and Building Department of the City; and WHEREAS, the Planning Commission did hold a public hearing at the Civic Center in the City of Anaheim on December 5, 2022, at 5:00 p.m., notice of said public hearing having been duly given as required by law and in accordance with the provisions of Chapter 18.60 of the Code, to hear and consider evidence and testimony for and against the Proposed Project and to investigate and make findings and recommendations in connection therewith; and WHEREAS, after examining the Infill Streamlining Checklist, and pursuant to the provisions of CEQA, the CEQA Guidelines, and the City's CEQA Procedures, this Planning Commission finds and determines and that with implementation of MMP 385 and uniformly applicable development policies and standards, the Proposed Project will not cause any new specific effects or more significant effects and no additional environmental review is required; and WHEREAS, pursuant to Subsection .050 (Findings) of Section 18.06.160 (Residential Planned Unit Development), this Planning Commission, after due consideration, inspection, investigation and study made by itself and in its behalf, and after due consideration of all evidence and reports offered at said hearing, including the plans submitted by the applicant, does hereby find and determine the following facts with respect to the conditional use permit: - 3 - PC2022-*** 1. The uses within the project are compatible with the surrounding land uses. 2. New buildings or structures related to the project are compatible with the scale, mass, bulk, and orientation of existing buildings in the surrounding area. The surrounding buildings include single-family and multi-family residential. The proposed three-story buildings will have a maximum height of 39’-6” and be setback 55’ from the adjacent single-family zone and 37’ from the adjacent multiple-family zone. The placement of 83 new dwelling units will be compatible with the surrounding residential structures and with neighborhood-scale businesses. 3. Vehicular and pedestrian access are adequate because the project entry has been designed in accordance with City standards. Additionally, a 24-foot-wide drive aisle will encircle the project and provide garage access for 42 units. Five 20-foot wide alleyways will provide garage access for 41 units. An accessible path of travel will provide connectivity to all community amenities and both public streets. The project is designed to adjust the existing sidewalks away from the street, provide a new landscaped parkway, and provide stooped entries to contribute to the pedestrian orientation of the area, encourage walkability, and promote community interaction. 4. The Project is consistent with any adopted design guidelines applicable to the Property because the project will consist of 10 buildings and five product types with two architectural styles. The project incorporates a variety of rooflines, wall articulation, porches, balconies, window treatments, and varied colors and building materials on all elevations. The buildings will have a maximum height of 39’-6” and be set back 55’ from the adjacent single-family residential zone and 47’ from the adjacent multiple-family residential zone. Common open space amenities will include a tot lot, community barbeques, seating area, dog park, and community garden. Private open space amenities will include balconies and patios. 5. The size and shape of the site proposed for the Project is adequate to allow the full development of the proposed use in a manner not detrimental to the particular area because the project property has a gross lot size of 4.0-acres, which would allow for up to 144 dwelling units under the Residential Opportunity (RO) Overlay. The proposed project provides 83 larger family dwelling units and meets the parking requirements. With the exception of building setbacks, the development will comply with all other development standards of the RM-3.5 zone. 6. The traffic generated by the project will not impose an undue burden upon the streets and highways designed and improved to carry the traffic in the area because, in addition to the studies done under EIR No. 330 and SEIR No. 346, a trip generation memo was prepared for the project, reviewed, and approved by the City’s Public Works Department. The trip generation memo demonstrated that the proposed project will not exceed the thresholds to require a Traffic Impact Study. Projects that are below the threshold are not considered to create generate vehicle traffic that would impact the local roadways. Additionally, the site is zoned General Commercial but will be developed with a residential use, which has a lower traffic generation rate than commercial uses. 7. The Project will comply with the General Plan and zoning for the property because the site is zoned for General Commercial land uses but has a General Plan Land Use designation of Medium Density Residential with the Residential Opportunity (RO) Overlay Zone. Both the RO Overlay Zone and State law relieves applicants from rezoning property when the General Plan allows the density proposed. Housing can be built “by-right” provided the project meets the site - 4 - PC2022-*** development standards of the RM-3.5 Zone. Alternatively, Section 18.06.160 Residential Planned Unit Development of the Code allows developers to apply for a conditional use permit to modify development standards from the applicable zone. 8. The granting of the conditional use permit under the conditions imposed will not be detrimental to the health and safety of the citizens of the City of Anaheim because the project will provide 83 new townhomes towards much-needed family housing, the majority of which will have three or four bedrooms that can accommodate larger families. The high-quality development will provide an attractive attached single-family community for Anaheim residents with well-designed common and private open space amenities. The project is compatible with the existing surrounding uses and careful consideration was given to the landscaping and pedestrian activities. The project will not generate hazardous materials, noise or pollution. Approval of the conditional use permit will not harm the public interest, health, safety, convenience or welfare of the City; and WHEREAS, the Planning Commission determines that the evidence in the record constitutes substantial evidence to support the actions taken and the findings made in this Resolution, that the facts stated in this Resolution are supported by substantial evidence in the record, including testimony received at the public hearing, the staff presentations, the staff report and all materials in the project files. There is no substantial evidence, nor are there other facts, that negate the findings made in this Resolution. The Planning Commission expressly declares that it considered all evidence presented and reached these findings after due consideration of all evidence presented to it. NOW, THEREFORE, BE IT RESOLVED that, as the "lead agency" under CEQA, the Planning Commission of the City of Anaheim, based upon a thorough review of the Proposed Project, the Infill Streamlining Checklist, EIR 330, SEIR 346, and the evidence received to date, does determine as follows: 1. That the Infill Streamlining Checklist was prepared in compliance with the requirements of CEQA, the CEQA Guidelines, and the City's CEQA Procedures . 2. That, based upon the evidence submitted and as demonstrated by the analysis included in the Infill Streamlining Checklist, no additional environmental review is required as the Proposed Project will not cause any new specific effects or more significant effects, or uniformly applicable development policies and standards will substantially mitigate such effects; specifically: (a) There have not been any substantial changes in any of the entitlements that were analyzed in EIR 330 and SEIR 346 that require major revisions of EIR 330 or SEIR 346 because of new significant environmental effects or a substantial increase in the severity of previously identified significant effects; (b) There have not been any substantial changes with respect to the circumstances under which the Proposed Project is undertaken that require major revisions of EIR 330 and SEIR 346 due to the involvement of new significant environmental effects or a substantial increase in the severity of previously identified significant effects; and - 5 - PC2022-*** (c) There is no new information of substantial importance, which was not known and could not have been known with the exercise of reasonable diligence at the time EIR 330 and SEIR 346 were certified as complete and adopted, that shows any of the following: (i) The Proposed Project will have one or more significant effects not discussed in EIR 330 and SEIR 346; (ii) Significant effects previously examined will be substantially more severe than shown in EIR 330 and SEIR 346; (iii) Mitigation measures or alternatives previously found not to be feasible would in fact be feasible and would substantially reduce one or more significant effects of the Proposed Project, but the proponents of the Proposed Project decline to adopt the mitigation measures or alternatives; or (iv) Mitigation measures or alternatives which are considerably different from those analyzed in EIR 330 and SEIR 346 would substantially reduce one or more significant effects on the environment, but the proponents of the Proposed Project decline to adopt the mitigation measures or alternatives. BE IT FURTHER RESOLVED that, pursuant to the above findings, the Planning Commission determines that EIR 330 and SEIR 346, together with the Infill Streamlining Checklist, are adequate to serve as the required environmental documentation for the Proposed Project. BE IT FURTHER RESOLVED that the Planning Commission has reviewed and considered MMP 385, which was prepared for the Proposed Project and reflects mitigation measures from EIR 330 and SEIR 346 that are specific to the Proposed Project, and, in accordance with the requirements of CEQA, finds and determines that, with the imposition of identified mitigation measures and uniformly applicable development policies and standards, the Proposed Project will not cause any new specific effects or more significant effects . BE IT FURTHER RESOLVED that, pursuant to the above findings and Section 18.06.160.010 of the Code, this Planning Commission does hereby approve this conditional use permit, contingent upon and subject to: (1) the adoption of a resolution approving Tentative Tract Map No. 19237, which entitlements are now pending; and (2) the mitigation measures set forth in MMP 385, and the conditions of approval set forth in Exhibits B and C attached hereto and incorporated herein by this reference, which are hereby found to be a necessary prerequisite to the proposed use of the Property in order to preserve the health, safety and general welfare of the citizens of the City of Anaheim. Extensions for further time to complete conditions of approval may be granted in accordance with Section 18.60.170 of the Code. Timing for compliance with conditions of approval may be amended by the Planning Director upon a showing of good cause provided (i) equivalent timing is established that satisfies the original intent and purpose of the condition(s), (ii) the modification complies with the Code, and (iii) the applicant has demonstrated significant progress toward establishment of the use or approved development. - 6 - PC2022-*** BE IT FURTHER RESOLVED, that any amendment, modification, or revocation of this permit may be processed in accordance with Chapters 18.60.190 (Amendment to Permit Approval) and 18.60.200 (City-Initiated Revocation or Modification of Permits) of the Code. BE IT FURTHER RESOLVED that the Planning Commission does hereby find and determine that adoption of this Resolution is expressly predicated upon applicant's compliance with each and all of the conditions hereinabove set forth. Should any such condition, or any part thereof, be declared invalid or unenforceable by the final judgment of any court of competent jurisdiction, then this Resolution, and any approvals herein contained, shall be deemed null and void. BE IT FURTHER RESOLVED that approval of this application constitutes approval of the proposed request only to the extent that it complies with the Code and any other applicable City, State and Federal regulations. Approval does not include any action or findings as to compliance or approval of the request regarding any other applicable ordinance, regulation, or requirement. THE FOREGOING RESOLUTION was adopted at the Planning Commission meeting of December 5, 2022. Said resolution is subject to the appeal provisions set forth in Chapter 18.60 (Procedures) of the Anaheim Municipal Code pertaining to appeal procedures and may be replaced by a City Council Resolution in the event of an appeal. CHAIRPERSON, PLANNING COMMISSION OF THE CITY OF ANAHEIM ATTEST: SECRETARY, PLANNING COMMISSION OF THE CITY OF ANAHEIM PC2022-*** PC2022-*** EXHIBIT “B” CONDITIONAL USE PERMIT (DEV2021-00180) NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT WITHIN 30 DAYS OF APPROVAL OF THE CONDITIONAL USE PERMIT 1 Owner/Developer shall install an approved backflow prevention assembly on the water service connection(s) serving the property, behind the property line and building setback in accordance with the Public Utilities Department Water Engineering Division requirements. Public Utilities, Water Engineering PRIOR TO ISSUANCE OF A GRADING PERMIT 2 Prior to approval of permits for improvement plans, the property owner/developer shall coordinate with Electrical Engineering to establish electrical service requirements and submit electric system plans, electrical panel drawings, site plans, elevation plans, and related technical drawings and specifications. Public Utilities, Electrical Engineering 3 Prior to the connection of electrical service, the legal owner shall provide to the City of Anaheim a Public Utilities Easement with dimensions as shown on the approved utility service plan. Public Utilities, Electrical Engineering 4 Prior to connection of electrical service, the legal owner shall submit payment to the City of Anaheim for service connection fees. Public Utilities, Electrical Engineering 5 The Owner/Developer shall submit a set of improvement plans for Public Utilities Water Engineering review and approval in determining the conditions necessary for providing water service to the project. Public Utilities, Water Engineering 6 Prepare and submit a final grading plan showing building footprints, pad elevations, finished grades, drainage routes, retaining walls, erosion control, slope easements and other pertinent information in accordance with Anaheim Municipal Code and the California Building Code, latest edition. Public Works, Development Services 7 Prepare and submit a final drainage/hydrology study, including supporting hydraulic and hydrological data to the City of Anaheim for review and approval. The study shall confirm or recommend changes to the City's adopted Master Drainage Plan by identifying off-site and on-site storm water runoff impacts resulting from build- out of permitted General Plan land uses. In addition, the study shall identify the project's contribution and shall provide locations and sizes of catchments and system connection points and all downstream drainage-mitigating measures including but not limited to offsite storm drains and interim detention facilities. Public Works, Development Services PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT 8 The developer shall execute a Save Harmless Agreement with the City of Anaheim for any storm drain connections to a City storm drain system. The agreement shall be recorded by the applicant on the property prior to the issuance of any permits. Public Works, Development Services 9 All required plans and studies shall be prepared by a Registered Professional Engineer in State of California. Public Works, Development Services 10 The OWNER shall obtain the required coverage under California’s General Permit for Stormwater Discharges associated with Construction Activity by providing a copy of the Notice of Intent (NOI) submitted to the State Water Resources Control Board and a copy of the subsequent notification of the issuance of a Waste Discharge Identification (WDID) number. Public Works, Development Services 11 Submit Water Quality Management Plan (WQMP) to the City for review and approval. The WQMP shall be consistent with the requirements of Section 7 and Exhibit 7.II of the Orange County Drainage Area Management Plan (DAMP) for New Development/ Significant Redevelopment projects. identify potential sources of pollutants during the long-term on-going maintenance and use of the proposed project that could affect the quality of the stormwater runoff from the project site; define Source Control, Site Design, and Treatment Control (if applicable) best management practices (BMPs) to control or eliminate the discharge of pollutants into the surface water runoff; and provide a monitoring program to address the long-term implementation of and compliance with the defined BMPs. Submit three (3) copies and a plan checking deposit to the Public Works/Development Services for consideration and approval. Public Works, Development Services 12 Submit a Geotechnical Report to the Public Works Development Services Division for review and approval. The report shall include any proposed infiltration features of the WQMP. Public Works, Development Services 13 At the time of grading plan submittal, a Fire Master Plan (Fire access plan) shall be submitted by the owner/developer to Anaheim Fire & Rescue for review. Anaheim Fire & Rescue 14 The owner/developer shall ensure the following: During construction, construction contractors shall comply with South Coast Air Quality Management District’s (South Coast AQMD’s) Rules 402 and 403 to minimize construction emissions of dust particulates. South Coast AQMD Rule 402 requires that air pollutant Planning and Building Department, Planning Services Division PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT emissions of dust and particulates. South Coast AQMD Rule 402 requires that air pollutant emissions not be a nuisance off site. Rule 402 prohibits the discharge from any source whatsoever such quantities of air contaminants or other material which cause injury, detriment, nuisance, or annoyance to any considerable number of persons or to the public, or which endanger the comfort, repose, health, or safety of any such persons or the public, or which cause, or have a natural tendency to cause, injury or damage to business or property. SCAQMD Rule 403 requires that fugitive dust be controlled with Best Available Control Measures so that the presence of such dust does not remain visible beyond the property line of the emission source. This rule is intended to reduce PM10 emissions from any transportation, handling, construction, or storage activity that has the potential to generate fugitive dust. This requirement shall be included as notes on the contractor specifications. Table 1 of Rule 403 lists the Best Available Control Measures that are applicable to all construction projects. The measures include, but are not limited to, the following: a. Portions of a construction site to remain inactive longer than a period of three months will be seeded and watered until grass cover is grown or otherwise stabilized. b. All on-site roads will be paved as soon as feasible or watered periodically or chemically stabilized. c. All material transported off site will be either sufficiently watered or securely covered to prevent excessive amounts of dust. d. The area disturbed by clearing, grading, earthmoving, or excavation operations will be minimized at all times. Where vehicles leave a construction site and enter adjacent public streets, the streets will be swept daily or washed down at the end of the workday to remove soil tracked onto the paved surface. PRIOR TO ISSUANCE OF A BUILDING PERMIT 15 A private water system with separate water service for fire protection and domestic water shall be provided and shown on plans submitted to the Water Engineering Division of the Anaheim Public Utilities Department. Public Utilities, Water Engineering 16 Per California Water Code, Division 1, Chapter 8, Article 5, Section 537-537.5) as amended by Senate Bill 7, water submetering shall be furnished and installed by the Owner/Developer and a water submeter shall be installed to each individual unit. Provisions for the ongoing maintenance and operation (including meter billing) of the Public Utilities, Water Engineering PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT submeters shall be the responsibility of the Owner and included and recorded in the Master CC&Rs for the project. 17 All backflow equipment shall be located above ground outside of the street setback area in a manner fully screened from all public streets and alleys. Any backflow assemblies currently installed in a vault will have to be brought up to current standards. Any other large water system equipment shall be installed to the satisfaction of the Water Engineering Division outside of the street setback area in a manner fully screened from all public streets and alleys. Said information shall be specifically shown on plans and approved by Water Engineering and Cross Connection Control Inspector. Public Utilities, Water Engineering 18 All requests for new water services, backflow equipment, or fire lines, as well as any modifications, relocations, or abandonments of existing water services, backflow equipment, and fire lines, shall be coordinated and permitted through Water Engineering Division of the Anaheim Public Utilities Department. Public Utilities, Water Engineering 19 All existing water services and fire services shall conform to current Water Services Standards Specifications. Any water service and/or fire line that does not meet current standards shall be upgraded if continued use is necessary or abandoned if the existing service is no longer needed. The Owner/Developer shall be responsible for the costs to upgrade or to abandon any water service or fire line. Public Utilities, Water Engineering 20 The Owner shall irrevocably offer to dedicate to the City of Anaheim (i) an easement for all large domestic above-ground water meters and fire hydrants, including a five (5)-foot wide easement around the fire hydrant and/or water meter pad. (ii) a twenty (20) foot wide easement for all water service mains and service laterals all to the satisfaction of the Water Engineering Division. The easements shall be granted on the Water Engineering Division of the Public Utilities Department’s standard water easement deed. The easement deeds shall include language that requires the Owner to be responsible for restoring any special surface improvements, other than asphalt paving, including but not limited to colored concrete, bricks, pavers, stamped concrete, decorative hardscape, walls or landscaping that becomes damaged during any excavation, repair or replacement of City owned water facilities. Provisions for the repair, replacement and maintenance of all surface improvements other than asphalt paving shall be the responsibility of the Owner and included and recorded in the Master CC&Rs for the project. Public Utilities, Water Engineering 21 The Owner/Developer shall submit to the Public Utilities Department Water Engineering Division an estimate of the maximum fire flow rate and maximum day and peak hour water demands for the project. This information will be used to determine the adequacy of the existing water system to provide the estimated Public Utilities, Water Engineering PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT water demands. Any off-site water system improvements required to serve the project shall be done in accordance with Rule No. 15A.1 of the Water Utility Rates, Rules, and Regulations. 22 Individual water service and/or fire line connections will be required for each parcel or residential, commercial, industrial unit per Rule 18 of the City of Anaheim’s Water Rates, Rules and Regulations. Public Utilities, Water Engineering 23 The existing 8-inch backflow prevention device on the fire service serving the property is substandard and must be replaced per Public Utilities Department Water Engineering Division requirements. Public Utilities, Water Engineering 24 That prior to the issuance of a building permit, street improvement plans shall be submitted showing R6-1(R) (ONE-WAY) sign on the median directly in front of project driveway for review and approval. Sign shall be installed prior to the first building and zoning inspection. Public Works, Traffic Engineering 25 That the project driveway on Lincoln Avenue shall be a right-turn in/out only driveway. That prior to the issuance of a building permit, plans shall be submitted showing R3-5(R) (RIGHT-TURN-ONLY) sign and right-turn arrow pavement legend at the project driveway. Subject property shall thereupon be developed and maintained in conformance with said plans. Public Works, Traffic Engineering 26 Prior to the issuance of a building permit, the applicant shall submit draft Covenants, Conditions and Restrictions (CC&Rs) that are prepared by an authorized professional for review and approval by the City Engineer, Planning Director, and City Attorney, which will generally provide for the following: • A requirement that residents shall use designated parking area, including garages, only for the parking of vehicles. • A provision that parking garages are subject to inspection by the Association or City of Anaheim staff. • A provision requiring that proposed amendments to the CC&Rs shall be submitted for review to the City Engineer, Planning Director or designee, and shall be approved by the City Attorney prior to the amendment being valid. • A provision that the City is a third-party beneficiary to the CC&Rs and has the right, but not the obligation, to enforce any of the provisions of the CC&Rs relative to common area and utility maintenance, Water Quality Management Plan, and internal parking. Public Works, Traffic Engineering 27 The owner/developer shall record Tract Map No. 19237 pursuant to the Subdivision Map Act and in accordance with City Code. Provide a duplicate photo Mylar of the recorded map to the City Engineer's office. Public Works, Development Services PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT 28 Provide a certificate, from a Registered Civil Engineer, certifying that the building pad has been completed in accordance with the City of Anaheim Municipal Code. Submit a pad compaction report prepared by the project's Geotechnical-Soil Engineer of Record. Public Works, Development Services 29 Design per City Standards full improvements for all impacted public streets/facilities in accordance with City Code, Standards and Specifications. Such improvements shall include, but not be limited to the following: Curb widening, new curb and gutter, new curb return at the intersection of Lincoln Avenue and Sunkist Street, traffic signal relocation and modification, new commercial driveway approaches, new sidewalk, landscape parkway with irrigation and relocation of existing utility boxes and appurtenances. Public Works, Development Services 30 A Right of Way Construction Permit shall be obtained from the Development Services Division for all work performed in the public right-of-way. Public Works, Development Services 31 The owner/developer shall ensure that all California Building Code and California Fire Code requirements are followed for permit issuance. Any fire permits which include fire sprinklers, fire alarm, etc. shall be submitted directly to Anaheim Fire Department. Anaheim Fire & Rescue PRIOR TO FINAL BUILDING AND ZONING INSPECTIONS 32 Owner/Developer shall install an approved backflow prevention assembly on the water service connection(s) serving the property, behind property line and building setback in accordance with Public Utilities Department Water Engineering Division requirements. Public Utilities, Water Engineering 33 Prior to Final Building and Zoning Inspections, the owner/developer shall execute and record with the Orange County Recorder an unsubordinated declaration of Covenants Conditions and Restrictions (CC&Rs) to run with the land, satisfactory to the City Engineer, Planning Director, and City Attorney, which restricts the installation of vehicle gates across the project driveways or access roads as the site design does not allow any such gates to conform to City of Anaheim Engineering Standard Detail 475 pertaining to gate set back distance, turnaround area, guest phone, separate lane for guest access, and minimum width for ingress/egress as required by the Fire Department. Should gates be desired in the future, an amendment to the CC&Rs approved by the City Engineer, Planning Director and the City Attorney's office shall be recorded. Gates, if any, shall comply with the current version of City of Anaheim Engineering Standard Detail 475 and are subject to approval by the City Engineer. Public Works, Traffic Engineering PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT 34 Prior to final building and zoning inspection, fire lanes shall be posted by the owner/developer with “No Parking Any Time.” Said information shall be specifically shown on plans submitted for building permits. Public Works, Traffic Engineering 35 If fire hydrants for proposed project are private hydrants serving this site, the owner/developer shall submit CC&Rs to Anaheim Fire & rescue for review and approval covering the private fire hydrants (if applicable). Anaheim Fire & Rescue 36 All public improvements shall be constructed by the owner/developer, inspected and accepted by Construction Services prior to final building and zoning inspection. Public Works, Development Services 37 All remaining fees/deposits required by Public Works department must be paid in full by the owner/developer. Public Works, Development Services 38 The owner/developer shall set all Monuments in accordance with the final map and submit all centerline ties to Public Works Department. Any monuments damaged as a result of construction shall be reset to the satisfaction of the City Engineer. Public Works, Development Services 39 Record Drawings and As-Built Plans shall be submitted by the owner/developer for review and approval to the Department of Public Works, Development Services Division. Public Works, Development Services 40 The owner/developer shall ensure that each individual residence or unit is clearly marked with its appropriate number and address. These shall be positioned so they are easily viewed from vehicular and pedestrian pathways throughout the complex. Main building numbers shall be a minimum height of 12” and illuminated during the hours of darkness. Address numbers shall be positioned to be readily readable from the street. Numbers shall be illuminated during hours of darkness. Police Department 41 The owner/developer shall ensure: • All exterior doors to have adequate security hardware, e.g., deadbolt locks. • The locks shall be so constructed that both the deadbolt and deadlocking latch can be retracted by a single action of the inside doorknob/lever/turn piece. • Wide-angle peepholes or other viewing device shall be designed into all dwelling-unit front doors and all solid doors where exterior visibility is compromised. Police Department 42 The owner/developer shall ensure: • Monument signs and addresses shall be well lighted during hours of darkness. • Adequate lighting of parking lots and associated carports, circulation areas, aisles, passageways, recesses, and grounds Police Department PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT contiguous to residences shall be provided with lighting of sufficient wattage to provide adequate illumination to make clearly visible the presence of any person on or about the premises during the hours of darkness and provide a safe, secure environment for all persons, property, and vehicles on-site. GENERAL 43 The design of the on-site private sewer system shall be submitted to the Anaheim Building Division for review, approval, permit issuance and inspection in accordance with the Building Code and Plumbing Code requirements. Public Works, Development Services 44 The Owner shall be responsible for restoring any special surface improvements, other than asphalt paving, within any right-of- way, public utility easement or City easement area including but not limited to colored concrete, bricks, pavers, stamped concrete, walls, decorative hardscape or landscaping that becomes damaged during any excavation, repair or replacement of City owned water facilities. Provisions for maintenance of all said special surface improvements shall be included in the recorded Master CC&Rs for the project and the City easement deeds. Public Utilities, Water Engineering 45 A minimum of two connections to public water mains and water looping inside the project are required. Public Utilities, Water Engineering 46 The following minimum horizontal clearances shall be maintained between proposed water main and other facilities: • 10-feet minimum separation (outside wall-to-outside wall) from sanitary sewer mains and laterals • 5-feet minimum separation from all other utilities, including storm drains, gas, and electric • 6-feet minimum separation from curb face • 10-feet minimum separation from structures, footings, and trees. The following minimum clearances shall be provided around all new and existing public water facilities (e.g., water mains, fire hydrants, service laterals, meters, meter boxes, backflow devices, etc.): • 10 feet from structures, footings, walls, stormwater BMPs, power poles, street lights, and trees. • 5 feet from driveways, BCR/ECR of curb returns, and all other utilities (e.g., storm drain, gas, electric, etc.) or above ground facilities. Public Utilities, Water Engineering PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT 47 No public water main or public water facilities shall be installed in private alleys or paseo areas. Public Utilities, Water Engineering 48 No public water mains or laterals allowed under parking stalls or parking lots. Public Utilities, Water Engineering 49 All fire services 2-inch and smaller shall be metered with a UL listed meter, Hersey Residential Fire Meter with Translator Register, no equals. Public Utilities, Water Engineering 50 Townhouses shall require NFPA 13D fire sprinkler systems. Any change in type of R occupancy shall require an additional analysis for fire protection system(s). Anaheim Fire & Rescue 51 All drivable surfaces - Permanent, temporary, and phased emergency access roads shall be designed and maintained to support an imposed load of 78,000 lbs. and surfaced to provide all- weather driving capabilities. Anaheim Fire & Rescue 52 An adequate water supply capable of providing minimum fire flow requirements for fire hydrants and a fire sprinkler system shall be available for the future, proposed condominiums. Anaheim Fire & Rescue 53 “No Trespassing 602(k) P.C.” signs shall be posted by the owner/developer at the entrances of parking areas and located in other appropriate places. Signs must be at least 2’ x 1’ in overall size, with white background and black 2” lettering. All entrances to parking areas shall be posted with appropriate signs per 22658(a) C.V.C. to assist in removal of vehicles at the property owner’s/manager’s request. Police Department 54 The owner/developer shall ensure: • Landscaping shall be of the type and situated in locations to maximize observation while providing the desired degree of aesthetics. Security planting materials are encouraged along fence and property lines and under vulnerable windows. • Trees shall not be planted close enough to the structure to allow easy access to the roof or should be kept trimmed to make climbing difficult. Police Department 55 Residential buildings/units shall be pre-wired by the owner/developer for the future installation of an alarm system. Police Department PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT 56 All open parking areas shall maintain a minimum recommended lighting level of 0.5 foot-candles, measured at the parking surface, with a maximum to minimum ratio no greater than 15:1. Police Department 57 Prior to the issuance of a building permit, the applicant shall submit draft Covenants, Conditions and Restrictions (CC&Rs) that are prepared by an authorized professional for review and approval by the City Engineer, Planning Director, and City Attorney, which will generally provide for the following: 1. A requirement that residents shall use designated parking area, including garages, only for the parking of vehicles. 2. A provision that parking garages are subject to inspection by the Association or City of Anaheim staff. 3. A provision requiring that proposed amendments to the CC&Rs shall be submitted for review to the City Engineer, Planning Director or designee, and shall be approved by the City Attorney prior to the amendment being valid. 4. A provision that the City is a third-party beneficiary to the CC&Rs and has the right, but not the obligation, to enforce any of the provisions of the CC&Rs relative to common area and utility maintenance, Water Quality Management Plan, and internal parking. Planning and Building Department, Planning Services Division 58 The premises shall be developed substantially in accordance with plans and specifications submitted to the City of Anaheim by the applicant, which plans are on file with the Planning Department, and as conditioned herein. Planning and Building Department, Planning Services Division 59 All new landscaping shall be installed in conformance with Chapter 18.46 “Landscape and Screening” of the Anaheim Municipal Code and shall be maintained in perpetuity. Landscaping shall be replaced in a timely manner in the event that it is removed, damaged, diseased, and/or dead. Planning and Building Department, Planning Services Division 60 The owner/applicant is responsible for paying all charges related to the processing of this discretionary case application within 30 days of the issuance of the final invoice or prior to the issuance of building permits for this project, whichever occurs first. Failure to pay all charges shall result in delays in the issuance of required permits or may result in the revocation of the approval of this application. Planning and Building Department, Planning Services Division PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT 61 The Applicant shall defend, indemnify, and hold harmless the City and its officials, officers, employees and agents (collectively referred to individually and collectively as “Indemnitees”) from any and all claims, actions or proceedings brought against Indemnitees to attack, review, set aside, void, or annul the decision of the Indemnitees concerning this permit or any of the proceedings, acts or determinations taken, done, or made prior to the decision, or to determine the reasonableness, legality or validity of any condition attached thereto. The Applicant’s indemnification is intended to include, but not be limited to, damages, fees and/or costs awarded against or incurred by Indemnitees and costs of suit, claim or litigation, including without limitation attorneys’ fees and other costs, liabilities and expenses incurred by Indemnitees in connection with such proceeding. Planning and Building Department, Planning Services Division 62 The property owner/developer shall be responsible for compliance with and any direct costs associated with the monitoring and reporting of all mitigation measures set forth in Mitigation Monitoring Plan (MMP) No. 385, established by the City of Anaheim as required by Section 21081.6 of the Public Resources Code to ensure implementation of those identified mitigation measures within the timeframes identified in the measure. Planning and Building Department, Planning Services Division PC2022-*** EXHIBIT “C” KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Terms and Definitions: 1. Property Owner/Developer – Owner or developer of KB Homes Lincoln & Sunkist Townhomes project. 2. Environmental Equivalent/Timing – Any mitigation measure and timing thereof, subject to the approval of the City, which will have the same or superior result and will have the same or superior effect on the environment. The Planning Division, in conjunction with any appropriate agencies or City departments, shall determine the adequacy of any proposed "environmental equivalent/timing" and, if determined necessary, may refer said determination to the Planning Commission or City Council. Any costs associated with information required in order to make a determination of environmental equivalency/timing shall be done by the property owner/developer. Staff time for reviews will be charged on a time and materials basis at the rate in the City’s adopted Fee Schedule. 3. Implementation Timing – This is the point where a mitigation measure must be monitored for compliance. In the case where multiple action items are indicated, it is the first point where compliance associated with the mitigation measure must be monitored. Once the initial action item has been complied with, no additional monitoring pursuant to the Mitigation Monitoring Plan will occur, as routine City practices and procedures will ensure that the intent of the measure has been complied with. For example, if the timing is "to be shown on approved building plans" subsequent to issuance of the building permit consistent with the approved plans will be final building and zoning inspections pursuant to the building permit to ensure compliance. 4. Responsible Monitoring Party – Shall mean that compliance with the subject mitigation measure(s) shall be reviewed and determined adequate by all departments listed for each mitigation measure. Outside public agency review is limited to those public agencies specified in the Mitigation Monitoring Plan which have permit authority in conjunction with the mitigation measure. 5. Ongoing Mitigation Measures – The mitigation measures that are designated to occur on an ongoing basis as part of this Mitigation Monitoring Plan will be monitored in the form of an annual letter from the property owner/developer in January of each year demonstrating how compliance with the subject measure(s) has been achieved. When compliance with a measure has been demonstrated for a period of one year, monitoring of the measure will be deemed to be satisfied and no further monitoring will occur. For measures that are to be monitored "Ongoing During Construction", the annual letter will review those measures only while construction is occurring; monitoring will be discontinued after construction is complete. A final annual letter will be provided at the close of construction. 6. Building Permit – For purposes of this Mitigation Monitoring Plan, a building permit shall be defined as any permit issued for construction of a new building or structural expansion or modification of any existing building but shall not include any permits required for interior tenant improvements or minor additions to an existing structure or building. KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Mitigation Monitoring and Reporting Program Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Air Quality MM 5.2-1: Prior to the issuance of grading permits, the Property Owner/Developer shall include a note on all grading plans, which requires the construction contractor to implement following measures during grading. These measures shall also be discussed at the pre-grade conference. • Use low emission mobile construction equipment. • Maintain construction equipment engines by keeping them tuned. • Use low sulfur fuel for stationary construction equipment. • Utilize existing power sources (i.e., power poles) when feasible. • Configure construction parking to minimize traffic interference. • Minimize obstruction of through-traffic lanes. When feasible, construction should be planned so that lane closures on existing streets are kept to a minimum. • Schedule construction operations affecting traffic for off-peak hours. Prior to issuance of a grading permit Public Works Department/Engineering Division, Traffic and Transportation Division Planning Department/Building Division Grading Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method • Develop a traffic plan to minimize traffic flow interference from construction activities (the plan may include advance public notice of routing, use of public transportation and satellite parking areas with a shuttle service). Biological Resources MM 5.3-3: If construction activity is timed to occur during the nesting season (typically between March 1 and July 1), developers will be required to provide focused surveys for nesting birds pursuant to California Department of Fish and Game requirements. Such surveys shall identify avoidance measures taken to protect active nests. Prior to issuance of a grading permit Planning Department/Building Division, Advanced Planning Division; Zoning Division Grading Plan Check Biological Resources MM 5.3-4: Removal of non-native trees shall be permitted only outside the nesting season. Ongoing during construction activities Planning Department/Building Division, Advanced Planning Division; Zoning Division Construction Site Inspection Hydrology and Water Quality MM 5.7-3: Prior to issuance of the grading permit, the City shall require that new developments and/or significant redevelopments prepare a Final Water Quality Management Plan to be reviewed and approved by the City Engineer and conform to the City’s National Pollutant Discharge Elimination System (NPDES) related requirements to the satisfaction of the City Engineer. Prior to issuance of a grading permit Public Works Department/Engineering Division; Planning Department/Building Division Grading Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Public Services MM 5.11-1: Future projects will be reviewed by the City of Anaheim on an individual basis and will be required to comply with requirements in effect at the time building permits are issued (i.e., impact fees, etc.) or if an initial study is prepared and the City determines the impacts to be significant, then the project will be required to comply with appropriate mitigation measures (i.e., fire station sites, etc.). Prior to issuance of a building permit Planning Department/Building Division; Fire Department; Police Department Building Plan Check Transportation MM 5.15-5: Prior to issuance of each building permit, appropriate Transportation Impact and Improvement Fees shall be paid by the property owner/developer to the City of Anaheim in amounts determined by the City Council Resolution in effect at the time of issuance of the building permit with credit given for City- authorized improvements provided by the Property Owner/Developer; and participate in all applicable reimbursement or benefit districts which have been established. Prior to issuance of a building permit Public Works Department/Traffic and Transportation Division; Planning Department/Building Division Building Plan Check Transportation MM 5.15-6: Prior to approval of the first final subdivision map or issuance of the first building permit, whichever occurs first, and subject to nexus requirements, the property owner/developer shall irrevocably offer for dedication (with subordination of easements), including necessary construction easements, the ultimate right(s)-of-way as shown in the Circulation Element of the Anaheim General Plan adjacent to their property. Prior to approval of the first final subdivision map or issuance of the first building permit, whichever occurs first. Public Works Department/Engineering Division; Planning Department/Building Division Grading and/or Subdivision Map Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Transportation MM 5.15-8: The General Plan Circulation Element and associated Planned Roadway Network Map (Figure C-1 of the General Plan), identifies those roadways that are planned to accommodate current development and future growth established by the Land Use Element. Roadways will be constructed as development occurs and as funding becomes available. In addition to the roadways identified on the Planned Roadway Network Map, the improvements identified in Table 5.4-7 will be necessary to maintain acceptable levels of service within the anticipated theoretical buildout identified in the General Plan. Ongoing Public Works Department/Traffic and Transportation Division; Planning Department/Zoning Division, Advanced Planning Division Ongoing Project Management Tribal Cultural Resources MM 5.4-3 All archaeological resources shall be subject to the provisions of CEQA (Public Resources Code) Section 21083.2. Prior to issuance of a grading permit Planning Department/Building Division, Advanced Planning Division; Zoning Division Grading Plan Check Utilities and Service Systems MM 5.13-1: Prior to issuance of building permits, future projects shall demonstrate compliance with the following water conservation measures to the satisfaction of the Anaheim Public Utilities Department: • Install a separate irrigation meter when the total landscaped area exceeds 2,500 square feet. (City of Anaheim Water Conservation Measures) • Use of efficient irrigation systems such as drip irrigation systems and automatic Prior to issuance of a building permit Public Works Department/Engineering Division; Planning Department/Building Division Building Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method systems that include moisture sensors. (City of Anaheim Water Conservation Measures) • Use of low-flow sprinkler heads in the irrigation system. (City of Anaheim Water Conservation Measures) • Use of water-conservation landscape plant materials, wherever feasible. (City of Anaheim Water Conservation Measures) • Low-flow fittings, fixtures, and equipment including low flush toilets and urinals. (City of Anaheim Water Conservation Measures) • Use of cooling tower and waterway recirculation systems. (City of Anaheim Water Conservation Measures) • Use of water efficient ice machines, dishwashers, clothes washers, and other water using appliances. (City of Anaheim Water Conservation Measures). Existing Policies and Procedures Biological Resources PPP Bio-1: The Property Owner/Developer shall comply with all provisions of Anaheim Municipal Code Section 13.12 related to tree preservation. Ongoing Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Biological Resources PPP Bio-2: The Property Owner/Developer shall comply with the provisions of the Migratory Bird Treaty Act, Federal Endangered Species Act, the California Endangered Species Act, and the Central/Coastal Subregion (NCCP/HCP) for protection of Federal or State listed species. Ongoing Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Biological Resources PPP Bio-3: The Property Owner/Developer shall comply with Section 1601-1603 of the Fish and Game Code and Section 404 of the Clean Water Act. Ongoing Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Geology and Soils PPP Geo-1: All grading operations will be conducted in conformance with the Anaheim Municipal Code, Title 17 – Land Development and Resources. During construction Public Works Department/Engineering Division; Planning Department/Building Division Public Works Site Inspection Geology and Soils PPP Geo-2: The Property Owner/Developer shall submit for approval to the State Water Resources Control Board, a Notice of Intent to be covered under the Storm Water Permit, in compliance with the National Pollutant Discharge Elimination System (NPDES) program. In addition, future projects shall be required to develop and implement a Storm Water Pollution Prevention Plan (SWPPP), which incorporates Best Management Practices (BMPs). During project permitting Public Works Department/Engineering Division; Planning Department/Building Division Grading and Building Plan Check Hazards and Hazardous Materials PPP Haz-1: The Proposed Project shall comply with all relevant local, State, and federal regulations related to hazardous materials. Ongoing Public Works Department/Engineering Division; Planning Department/Building Division Public Works and Building Site Inspection and Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Hazards and Hazardous Materials PPP Haz-2: Prior to structural demolition/renovation activities, a Certified Environmental Professional shall confirm the presence or absence of asbestos containing materials (ACMs). Should ACMs be present, demolition materials containing ACMs shall be removed and disposed of at an appropriate permitted facility. Asbestos removal shall be performed by a State certified asbestos containment contractor in accordance with the South Coast Air Quality Management District (SCAQMD) Rule 1403. Prior to site demolition activities Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Hydrology and Water Quality PPP HYD-1: The Property Owner/Developer shall comply with all applicable local, State, and federal regulations relating hydrology and water quality. During permitting and construction Public Works Department/Engineering Division; Planning Department/Building Division Public Works and Building Plan Check Noise PPP NOI-1: The following Best Management Practices, included as Conditions of Approval, would reduce any noise level increases produced by the construction equipment to the nearby noise-sensitive residential land uses: • Prior to approval of grading plans and/or issuance of building permits, the Property Owner/Developer shall include a note on the plans indicating that noise-generating Project construction activities shall only occur between the hours of 7:00 a.m. to 7:00 p.m. on any day (City of Anaheim Municipal Code, Section 6.050.010). The Project construction supervisor shall Prior to grading permit issuance and during construction Planning Department/Building Division, Advanced Planning Division; Zoning Division Grading and Building Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method ensure compliance with the permitted construction hours. • The Property Owner/Developer shall post a construction site notice near the construction site access point or in an area that is clearly visible to the public. The notice shall include the following: job site address; permit number, name, and phone number of the contractor and owner; dates and duration of construction activities; construction hours allowed; and the City of Anaheim and construction contractor phone numbers where noise complaints can be reported and logged. • Ongoing during construction, the Construction Contractors shall do all of the following: o All construction equipment whether fixed or mobile, will be equipped with properly operating and maintained mufflers, consistent with manufacturer standards. o All stationary construction equipment will be placed so that emitted noise is directed away from the noise sensitive receptors nearest the project site. o As applicable, shut off all KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method equipment when not in use. o To the degree possible, equipment staging will be located in areas that create the greatest distance between construction- related noise and vibration sources, and sensitive receptors surrounding the project site. o Jackhammers, pneumatic equipment, and all other portable stationary noise sources will be directed away and shielded from existing residences in the vicinity of the project site. Either one- inch plywood or sound blankets can be utilized for this purpose. They should reach up from the ground and block the line of sight between equipment and existing residences. The shielding should be without holes and cracks. o No amplified music and/or voice will be allowed on the project site. o Haul truck deliveries will not occur outside of the hours presented as exempt for construction per City’s Municipal Code Section 6.70.010. KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Noise PPP NOI-2: A best management practice limiting the use of a vibratory roller within 20 feet or a large bulldozer within 12 feet of the existing residential structures to the south and west of the project site will be implemented to avoid significant impacts. During construction Public Works Department/Engineering Division; Planning Department/Building Division Public Works Site Inspection Public Services PPP PS-1: The Property Owner/Developer would pay school impact fees pursuant to Senate Bill 50 (Government Code Section 65995). During project permitting Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Recreation PPP REC-1: Prior to issuance of building permits, the Property Owners/Developers shall comply with Anaheim Municipal Code, Section 17.08.250, which requires the provision of parkland and/or the payment of fees, consistent with the Quimby Act. Prior to issuance of a building permit Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Project Design Features Noise PDF NOI-1: Windows and sliding glass doors on building elevations that will be exposed to exterior noise levels that exceed 65 dBA CNEL, will be upgraded to ensure that vehicle noise does not result in interior noise levels that exceed 45 dBA CNEL inside the residence. Prior to issuance of a building permit Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check PC2022-*** STATE OF CALIFORNIA ) COUNTY OF ORANGE ) ss. CITY OF ANAHEIM ) I, Susana Barrios, Secretary of the Planning Commission of the City of Anaheim, do hereby certify that the foregoing resolution was passed and adopted at a meeting of the Planning Commission of the City of Anaheim held on December 5, 2022, by the following vote of the members thereof: AYES: NOES: ABSTAIN: ABSENT: IN WITNESS WHEREOF, I have hereunto set my hand this 5th day of December 2022. SECRETARY, PLANNING COMMISSION OF THE CITY OF ANAHEIM [DRAFT] ATTACHMENT NO. 2 - 1 - PC2022-*** RESOLUTION NO. PC2022-*** A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF ANAHEIM APPROVING TENTATIVE TRACT MAP NO. 19237 AND MAKING CERTAIN FINDINGS IN CONNECTION THEREWITH (DEV2021-00180) (2420-2450 EAST LINCOLN AVENUE) WHEREAS, the Planning Commission of the City of Anaheim (the “Planning Commission”) did receive a verified petition for the approval of Tentative Tract Map No. 19237 to establish a one-lot subdivision and 83“airspace” condominium lots for that certain real property generally located on the southwest corner of Lincoln Avenue and Sunkist Street and commonly referred to as 2420-2450 East Lincoln Avenue in the City of Anaheim, County of Orange, State of California, as generally depicted on the map attached hereto as Exhibit A and incorporated herein by this reference (the "Property"); and WHEREAS, Tentative Tract Map No. 19237 is proposed in conjunction with a request for a conditional use permit to permit the construction of an 83-unit single-family attached residential project with modified development standards, i.e., a reduction in the street landscape setback and building-to-building setback requirements of the "RM-3.5" Multiple-Family Residential Zone. Conditional Use Permit and Tentative Tract Map No. 19237, shall be referred to herein collectively as the "Proposed Project"; and WHEREAS, the Property is approximately 4.0 acres in size and is currently developed with two commercial office buildings. The Land Use Element of the Anaheim General Plan designates the Property for Medium Density residential land uses. The Property is located in the “C-G” General Commercial zone. The development standards and regulations of Chapters 18.34 (Residential Opportunity (RO) Overlay Zone) and 18.06 (Multiple-Family Residential Zones) of the Anaheim Municipal Code (the "Code") shall apply to the Proposed Project consistent with the General Plan designation for the Property, and pursuant to the provisions of the State of California’s Housing Accountability Act codified in Section 65589.5 of the California Government Code; and WHEREAS, pursuant to and in accordance with the provisions of the California Environmental Quality Act (Public Resources Code Section 21000 et seq.; herein referred to as “CEQA”), the State of California Guidelines for Implementation of the California Environmental Quality Act (California Code of Regulations, Title 14, Chapter 3, Sections 15000-15387) (herein referred to as the "CEQA Guidelines"), and the City's CEQA Procedures, the City is the "lead agency" for the preparation and consideration of environmental documents for the Proposed Project; and WHEREAS, in May 2004, the City Council certified the General Plan and Zoning Code Update Program EIR No. 330 (EIR 330), which evaluated impacts associated with implementation of the Anaheim General Plan and Zoning Code Update and created a Mitigation Monitoring Program No. 122 to mitigate those impacts. The Property was designated for Medium Density Residential land use as a part of the update; and - 2 - PC2022-*** WHEREAS, in September 2013, the City Council certified Supplemental Environmental Impact Report No. 346 (SEIR 346) for the Anaheim Housing Opportunities Site Rezoning. The City approved Mitigation Monitoring Program No. 122A as part of SEIR 346. SEIR 346 supplemented EIR 330 in the areas of air quality, greenhouse gas emissions, noise, and transportation and traffic. The Rezoning implemented a key strategy of the City’s 2006-2014 General Plan Housing Element by rezoning the properties identified as Housing Opportunities Sites in the Housing Element. The proposed rezoning of these approximately 166 sites allowed “by-right” housing development at these locations by applying one of two overlay zones to these properties: the Residential Opportunity (RO) Overlay Zone or the Mixed Use (MU) Overlay Zone. The Property was reclassified to the “RO” Overlay Zone as a part of the Rezoning Project; and WHEREAS, a streamlined review checklist was prepared pursuant to Section 15183.3 of the California Environmental Quality Act Guidelines to determine whether the project would have any significant effects that the City, as Lead Agency, did not previously disclose in Environmental Impact Report Nos. 330 and 346 pursuant to Public Resources Code Section 21094.5; and WHEREAS, in conformance with CEQA and the CEQA Guidelines, mitigation measures from Mitigation Monitoring Program No. 122A that are specific to the Proposed Project mitigation measures are reflected in Mitigation Monitoring Plan No. 385 (herein referred to as "MMP 385"). A complete copy of the Infill Streamlining Checklist including Appendices and MMP 385 is on file and can be viewed in the Planning and Building Department of the City; and WHEREAS, the Planning Commission did hold a public hearing at the Civic Center in the City of Anaheim on December 5, 2022, at 5:00 p.m., notice of said public hearing having been duly given as required by law and in accordance with the provisions of Chapter 18.60 of the Code, to hear and consider evidence and testimony for and against the Proposed Project and to investigate and make findings and recommendations in connection therewith; and WHEREAS, after examining the Infill Streamlining Checklist, and pursuant to the provisions of CEQA, the State CEQA Guidelines, and the City's Local CEQA Procedure Manual, this Planning Commission finds and determines and that with implementation of MMP 385 and uniformly applicable development policies and standards, the Proposed Project will not cause any new specific effects or more significant effects and no additional environmental review is required; and that; and WHEREAS, the Planning Commission, after due consideration, inspection, investigation and study made by itself and in its behalf, and after due consideration of all evidence and reports offered at said hearing pertaining to the request to approve Tentative Tract Map No. 19237, does find and determine and recommends that the City Council so find and determine the following facts: 1. That the proposed subdivision of the Property, as shown on proposed Tentative Tract Map No. 19237, including its design and improvements, is consistent with the General Plan of the City of Anaheim, and more particularly with the Medium Density land use designation, because the Proposed Project will consist of a maximum density of 20.75 dwelling units per acre (townhomes) which is permitted under the Medium Density land use designation, which allows up to 36 dwelling units per acre. - 3 - PC2022-*** 2. That the proposed subdivision of the Property, as shown on proposed Tentative Tract Map No. 19237, including its design and improvements, is consistent with the zoning and development standards of the "RM-3.5" Zone contained in Chapter 18.06 of the Code, because the project will comply with applicable development standards including the modified development standards as permitted in Chapter 18.06.160 of the code, for a reduced building-to-building setback and reduced street setback, now pending. 3. That the site is physically suitable for the type and density of the Proposed Project. 4. That the design of the subdivision, as shown on proposed Tentative Tract Map No. 19237, is not likely to cause substantial environmental damage or substantially and avoidably injure fish or wildlife or their habitat, as no sensitive environmental habitat has been identified, because the previously approved EIR No. 330 and FEIR No. 346 are the appropriate environmental documentation for the project and that there will be no significant impacts to the environment as a result of the Proposed Project, furthermore analyzed through a project-specific initial study checklist. 5. That the design of the subdivision, as shown on proposed Tentative Tract Map No. 19237, or the type of improvements is not likely to cause serious public health problems. 6. That the design of the subdivision, as shown on proposed Tentative Tract Map No. 19237, or the type of improvements will not conflict with easements acquired by the public, at large, for access through or use of property within the proposed subdivision; and WHEREAS, the Planning Commission determines that the evidence in the record constitutes substantial evidence to support the actions taken and the findings made in this Resolution, that the facts stated in this Resolution are supported by substantial evidence in the record, including testimony received at the public hearing, the staff presentations, the staff report and all materials in the project files. There is no substantial evidence, nor are there other facts, that detract from the findings made in this Resolution. The Planning Commission expressly declares that it considered all evidence presented and reached these findings after due consideration of all evidence presented to it. NOW, THEREFORE, BE IT RESOLVED that, as the "lead agency" under the California Environmental Quality Act (Public Resources Code Section 21000 et seq.; herein referred to as “CEQA”), the Planning Commission of the City of Anaheim, based upon a thorough review of the Proposed Project, the Infill Streamlining Checklist, EIR 330, SEIR 346, and the evidence received to date, does determine as follows: 1. That the Infill Streamlining Checklist was prepared in compliance with the requirements of CEQA, the State CEQA Guidelines, and the City's Local CEQA Procedure Manual; 2. That, based upon the evidence submitted and as demonstrated by the analysis included in the Infill Streamlining Checklist, no additional environmental review is required as the Proposed Project will not cause any new specific effects or more significant effects, or uniformly applicable development policies and standards will substantially mitigate such effects; specifically: - 4 - PC2022-*** (a) There have not been any substantial changes in any of the entitlements that were analyzed in EIR 330 and SEIR 346 that require major revisions of EIR 330 or SEIR 346 because of new significant environmental effects or a substantial increase in the severity of previously identified significant effects; (b) There have not been any substantial changes with respect to the circumstances under which the Proposed Project is undertaken that require major revisions of EIR 330 and SEIR 346 due to the involvement of new significant environmental effects or a substantial increase in the severity of previously identified significant effects; and (c) There is no new information of substantial importance, which was not known and could not have been known with the exercise of reasonable diligence at the time EIR 330 and SEIR 346 were certified as complete and adopted, that shows any of the following: (i) The Proposed Project will have one or more significant effects not discussed in EIR 330 and SEIR 346; (ii) Significant effects previously examined will be substantially more severe than shown in EIR 330 and SEIR 346; (iii) Mitigation measures or alternatives previously found not to be feasible would in fact be feasible and would substantially reduce one or more significant effects of the Proposed Project, but the proponents of the Proposed Project decline to adopt the mitigation measures or alternatives; or (iv) Mitigation measures or alternatives which are considerably different from those analyzed in EIR 330 and SEIR 346 would substantially reduce one or more significant effects on the environment, but the proponents of the Proposed Project decline to adopt the mitigation measures or alternatives. BE IT FURTHER RESOLVED that, pursuant to the above findings, the Planning Commission determines that EIR 330 and SEIR 346, together with the Infill Streamlining Checklist, are adequate to serve as the required environmental documentation for the Proposed Project. BE IT FURTHER RESOLVED that the Planning Commission has reviewed and considered Mitigation Monitoring and Reporting Program No. 385 ("MMP 385"), which was prepared for the Proposed Project and reflects mitigation measures from EIR 330 and SEIR 346 that are specific to the Proposed Project, and, in accordance with the requirements of CEQA, finds and determines that, with the imposition of identified mitigation measures and uniformly applicable development policies and standards, the Proposed Project will not cause any new specific effects or more significant effects. WHEREAS, the Planning Commission, after due inspection, investigation and study made by itself and in its behalf, and after due consideration of all evidence and reports offered at said hearing with respect to the request to establish a subdivision for conveyance purposes, does find and determine the following facts: - 5 - PC2022-*** 1. The proposed subdivision, including its design and improvements, and with the conditions imposed herein is consistent with the Medium Density Residential land use designation in the Anaheim General Plan and the development standards contained in the “RM-3.5” Multiple- Family Residential Zones in that the proposed tract map will create “airspace” lots which do not grant any future development potential. The proposed lots are consistent with the proposed zoning and the existing General Plan land use designation. 2. The site is physically suitable for the type and size of the proposed subdivision in that the conveyance map would not grant any future development potential. 3. The design of the subdivision, with the conditions imposed, is not likely to cause substantial environmental damage or substantially and avoidably injure fish or wildlife or their habitat because no sensitive environmental habitat has been identified on the site in that no environmental impacts are anticipated. 4. The design of the subdivision or the type of improvements is not likely to cause serious public health problems, since any new structures and associated site improvements will be constructed on the property in compliance with the conditions imposed and other related Code requirements in that the future demolition, removal of structures, and future development will be subject to all City code requirements for demolition and construction. 5. The design of the subdivision or the type of improvements will not conflict with easements, acquired by the public at large, for access through or use of property within the proposed subdivision in that the tract map is conditioned to be submitted for review and approval to the City of Anaheim and the Orange County Surveyor and then shall be recorded in the Office of the Orange County Recorder prior to issuance of building permits. WHEREAS, the Planning Commission determines that the evidence in the record constitutes substantial evidence to support the actions taken and the findings made in this Resolution, that the facts stated in this Resolution are supported by substantial evidence in the record, including testimony received at the public hearing, the staff presentations, the staff report and all materials in the project files. There is no substantial evidence, nor are there other facts, that detract from the findings made in this Resolution. The Planning Commission expressly declares that it considered all evidence presented and reached these findings after due consideration of all evidence presented to it. NOW, THEREFORE, BE IT RESOLVED that, based upon the aforesaid findings and determinations, the Planning Commission does approve Tentative Tract Map No. 19237, contingent upon and subject to: (1) the adoption of a resolution approving a conditional use permit, which entitlements are now pending; and (2) the mitigation measures set forth in MMP 385, and the conditions of approval set forth in Exhibits B and C attached hereto and incorporated herein by this reference, which are hereby found to be a necessary prerequisite to the proposed use of the Property in order to preserve the health, safety and general welfare of the citizens of the City of Anaheim. Extensions for further time to complete said conditions of approval may be granted in accordance with Section 18.60.170 of the Code. Timing for compliance with conditions of approval may be amended by the Planning Director upon a showing of good cause provided (i) equivalent timing is established that satisfies the original intent and purpose of the condition (s), (ii) the modification complies with the Code, and (iii) the applicant has demonstrated significant progress toward establishment of the use or approved development. - 6 - PC2022-*** BE IT FURTHER RESOLVED that the Planning Commission does hereby find and determine that adoption of this Resolution is expressly predicated upon applicant's compliance with each and all of the conditions hereinabove set forth. Should any such condition, or any part thereof, be declared invalid or unenforceable by the final judgment of any court of competent jurisdiction, then this Resolution, and any approvals herein contained, shall be deemed null and void. BE IT FURTHER RESOLVED that approval of this application constitutes approval of the proposed request only to the extent that it complies with the Code and any other applicable City, State and Federal regulations. Approval does not include any action or findings as to compliance or approval of the request regarding any other applicable ordinance, regulation, or requirement. THE FOREGOING RESOLUTION was adopted at the Planning Commission meeting of December 5, 2022. Said Resolution is subject to the appeal provisions set forth in Section 17.08.104 of the Code pertaining to appeal procedures and may be replaced by a City Council Resolution in the event of an appeal. CHAIRPERSON, PLANNING COMMISSION OF THE CITY OF ANAHEIM ATTEST: SECRETARY, PLANNING COMMISSION OF THE CITY OF ANAHEIM PC2022-*** PC2022-*** EXHIBIT “B” TENTATIVE TRACT MAP NO. 19237 (DEV2021-00180) NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT PRIOR TO APPROVAL OF THE FINAL MAP 1 The legal property owner/developer shall irrevocably offer to dedicate to the City of Anaheim, for road, public utilities and other public purposes, the right-of-way easements along as shown on TTM No.19237 and in locations listed below: • Variable width dedication along Lincoln Avenue frontage (4’ to 11’) to achieve the ultimate half street width of 64 feet from street centerline at the right turn lane and transitioning into 53 feet from street centerline west of the proposed right turn lane, as shown on TTM19237. • A corner cutoff dedication at the southwest corner of Lincoln Avenue and Sunkist Street. Public Works, Development Services 2 The legal property owner/developer shall irrevocably offer to dedicate to the City of Anaheim public access easements for emergency services and solid waste/trash collection along the interior private drives/aisles, as shown on the TTM19237. Public Works, Development Services 3 All existing structures in conflict with the future property lines shall be demolished. The developer shall obtain a demolition permit from the Building Division prior to any demolition work. Public Works, Development Services 4 The vehicular access rights to public streets shall be released and relinquished to the City of Anaheim, except at approved driveway openings, as shown on the Tentative Tract Map. Public Works, Development Services 5 The owner/developer shall pay all applicable development impact fees required under the Anaheim Municipal Code. Move to prior to building issuance. Public Works, Development Services 6 The Owner/developer shall submit improvement plans and cost estimate for the construction of required public improvements along the project frontages Lincoln Avenue and Sunkist Street to the Public Works Development Services Division for review, approval, and to determine the bond amounts. Such improvements shall include, but not be limited to the following: street widening, new curb and gutter, new curb return at the intersection of Lincoln Avenue and Sunkist Street, traffic signal relocation and modification, new commercial driveway approaches, new sidewalk, new landscape parkway with irrigation, and relocation of existing utility boxes and appetences. Public Works, Development Services PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT 7 The final map shall be submitted to the City of Anaheim, Public Works Development Services Division and to the Orange County Surveyor for technical correctness review and approval. Public Works, Development Services 8 The Developer/Owner shall execute a maintenance covenant with the City of Anaheim in a form that is approved by the City Engineer and the City attorney for all private improvements including, but not be limited to the following: landscape lot, private utilities, drainage devices, parkway landscaping and irrigation, private drives, common courts, private lights, common ingress/egress, common facilities, parking areas, etc. In addition to maintenance requirements established in the Water Quality Management Plan (WQMP) as applicable to the project. The covenant shall be recorded concurrently with the Final Map. Public Works, Development Services 9 The Developer/Owner shall execute a Subdivision Agreement and submit security in an amount acceptable to the City Engineer to guarantee construction of the public improvements required herein. Security deposit shall be in accordance with City of Anaheim Municipal Code. The agreement shall be recorded concurrently with the Final Map. Public Works, Development Services 10 Provide a Monumentation bond in an amount specified in writing by a Licensed Land Surveyor of Record. Public Works, Development Services 11 Comply with all applicable requirements of the Anaheim Municipal Code. Public Works, Development Services 12 The developer shall design all public improvements in accordance with City standards and specifications. Public street improvements shall meet all City standards and requirements. Public Works, Development Services 13 The premises shall be developed substantially in accordance with plans and specifications submitted to the City of Anaheim by the applicant, which plans are on file with the Planning Department, and as conditioned herein. Planning and Building Department, Planning Services Division 14 The owner/applicant is responsible for paying all charges related to the processing of this discretionary case application within 30 days of the issuance of the final invoice or prior to the issuance of building permits for this project, whichever occurs first. Failure to pay all charges shall result in delays in the issuance of required permits or may result in the revocation of the approval of this application. Planning and Building Department, Planning Services Division 15 The Applicant shall defend, indemnify, and hold harmless the City and its officials, officers, employees and agents (collectively referred to individually and collectively as “Indemnitees”) from any and all claims, actions or proceedings brought against Indemnitees to attack, review, set aside, void, or annul the decision of the Indemnitees concerning this permit or any of the proceedings, acts or determinations taken, done, or made prior to the decision, or to determine the reasonableness, legality or validity of any condition attached thereto. The Applicant’s indemnification is intended to include, but not be limited to, damages, fees and/or costs awarded against Planning and Building Department, Planning Services Division PC2022-*** NO. CONDITIONS OF APPROVAL RESPONSIBLE DEPARTMENT or incurred by Indemnitees and costs of suit, claim or litigation, including without limitation attorneys’ fees and other costs, liabilities and expenses incurred by Indemnitees in connection with such proceeding. 16 The property owner/developer shall be responsible for compliance with and any direct costs associated with the monitoring and reporting of all mitigation measures set forth in Mitigation Monitoring Plan (MMP) No. 385, established by the City of Anaheim as required by Section 21081.6 of the Public Resources Code to ensure implementation of those identified mitigation measures within the timeframes identified in the measure. Planning and Building Department, Planning Services Division PC2022-*** EXHIBIT “C” KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Terms and Definitions: 1. Property Owner/Developer – Owner or developer of KB Homes Lincoln & Sunkist Townhomes project. 2. Environmental Equivalent/Timing – Any mitigation measure and timing thereof, subject to the approval of the City, which will have the same or superior result and will have the same or superior effect on the environment. The Planning Division, in conjunction with any appropriate agencies or City departments, shall determine the adequacy of any proposed "environmental equivalent/timing" and, if determined necessary, may refer said determination to the Planning Commission or City Council. Any costs associated with information required in order to make a determination of environmental equivalency/timing shall be done by the property owner/developer. Staff time for reviews will be charged on a time and materials basis at the rate in the City’s adopted Fee Schedule. 3. Implementation Timing – This is the point where a mitigation measure must be monitored for compliance. In the case where multiple action items are indicated, it is the first point where compliance associated with the mitigation measure must be monitored. Once the initial action item has been complied with, no additional monitoring pursuant to the Mitigation Monitoring Plan will occur, as routine City practices and procedures will ensure that the intent of the measure has been complied with. For example, if the timing is "to be shown on approved building plans" subsequent to issuance of the building permit consistent with the approved plans will be final building and zoning inspections pursuant to the building permit to ensure compliance. 4. Responsible Monitoring Party – Shall mean that compliance with the subject mitigation measure(s) shall be reviewed and determined adequate by all departments listed for each mitigation measure. Outside public agency review is limited to those public agencies specified in the Mitigation Monitoring Plan which have permit authority in conjunction with the mitigation measure. 5. Ongoing Mitigation Measures – The mitigation measures that are designated to occur on an ongoing basis as part of this Mitigation Monitoring Plan will be monitored in the form of an annual letter from the property owner/developer in January of each year demonstrating how compliance with the subject measure(s) has been achieved. When compliance with a measure has been demonstrated for a period of one year, monitoring of the measure will be deemed to be satisfied and no further monitoring will occur. For measures that are to be monitored "Ongoing During Construction", the annual letter will review those measures only while construction is occurring; monitoring will be discontinued after construction is complete. A final annual letter will be provided at the close of construction. 6. Building Permit – For purposes of this Mitigation Monitoring Plan, a building permit shall be defined as any permit issued for construction of a new building or structural expansion or modification of any existing building but shall not include any permits required for interior tenant improvements or minor additions to an existing structure or building. KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Mitigation Monitoring and Reporting Program Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Air Quality MM 5.2-1: Prior to the issuance of grading permits, the Property Owner/Developer shall include a note on all grading plans, which requires the construction contractor to implement following measures during grading. These measures shall also be discussed at the pre-grade conference. • Use low emission mobile construction equipment. • Maintain construction equipment engines by keeping them tuned. • Use low sulfur fuel for stationary construction equipment. • Utilize existing power sources (i.e., power poles) when feasible. • Configure construction parking to minimize traffic interference. • Minimize obstruction of through-traffic lanes. When feasible, construction should be planned so that lane closures on existing streets are kept to a minimum. • Schedule construction operations affecting traffic for off-peak hours. Prior to issuance of a grading permit Public Works Department/Engineering Division, Traffic and Transportation Division Planning Department/Building Division Grading Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method • Develop a traffic plan to minimize traffic flow interference from construction activities (the plan may include advance public notice of routing, use of public transportation and satellite parking areas with a shuttle service). Biological Resources MM 5.3-3: If construction activity is timed to occur during the nesting season (typically between March 1 and July 1), developers will be required to provide focused surveys for nesting birds pursuant to California Department of Fish and Game requirements. Such surveys shall identify avoidance measures taken to protect active nests. Prior to issuance of a grading permit Planning Department/Building Division, Advanced Planning Division; Zoning Division Grading Plan Check Biological Resources MM 5.3-4: Removal of non-native trees shall be permitted only outside the nesting season. Ongoing during construction activities Planning Department/Building Division, Advanced Planning Division; Zoning Division Construction Site Inspection Hydrology and Water Quality MM 5.7-3: Prior to issuance of the grading permit, the City shall require that new developments and/or significant redevelopments prepare a Final Water Quality Management Plan to be reviewed and approved by the City Engineer and conform to the City’s National Pollutant Discharge Elimination System (NPDES) related requirements to the satisfaction of the City Engineer. Prior to issuance of a grading permit Public Works Department/Engineering Division; Planning Department/Building Division Grading Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Public Services MM 5.11-1: Future projects will be reviewed by the City of Anaheim on an individual basis and will be required to comply with requirements in effect at the time building permits are issued (i.e., impact fees, etc.) or if an initial study is prepared and the City determines the impacts to be significant, then the project will be required to comply with appropriate mitigation measures (i.e., fire station sites, etc.). Prior to issuance of a building permit Planning Department/Building Division; Fire Department; Police Department Building Plan Check Transportation MM 5.15-5: Prior to issuance of each building permit, appropriate Transportation Impact and Improvement Fees shall be paid by the property owner/developer to the City of Anaheim in amounts determined by the City Council Resolution in effect at the time of issuance of the building permit with credit given for City- authorized improvements provided by the Property Owner/Developer; and participate in all applicable reimbursement or benefit districts which have been established. Prior to issuance of a building permit Public Works Department/Traffic and Transportation Division; Planning Department/Building Division Building Plan Check Transportation MM 5.15-6: Prior to approval of the first final subdivision map or issuance of the first building permit, whichever occurs first, and subject to nexus requirements, the property owner/developer shall irrevocably offer for dedication (with subordination of easements), including necessary construction easements, the ultimate right(s)-of-way as shown in the Circulation Element of the Anaheim General Plan adjacent to their property. Prior to approval of the first final subdivision map or issuance of the first building permit, whichever occurs first. Public Works Department/Engineering Division; Planning Department/Building Division Grading and/or Subdivision Map Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Transportation MM 5.15-8: The General Plan Circulation Element and associated Planned Roadway Network Map (Figure C-1 of the General Plan), identifies those roadways that are planned to accommodate current development and future growth established by the Land Use Element. Roadways will be constructed as development occurs and as funding becomes available. In addition to the roadways identified on the Planned Roadway Network Map, the improvements identified in Table 5.4-7 will be necessary to maintain acceptable levels of service within the anticipated theoretical buildout identified in the General Plan. Ongoing Public Works Department/Traffic and Transportation Division; Planning Department/Zoning Division, Advanced Planning Division Ongoing Project Management Tribal Cultural Resources MM 5.4-3 All archaeological resources shall be subject to the provisions of CEQA (Public Resources Code) Section 21083.2. Prior to issuance of a grading permit Planning Department/Building Division, Advanced Planning Division; Zoning Division Grading Plan Check Utilities and Service Systems MM 5.13-1: Prior to issuance of building permits, future projects shall demonstrate compliance with the following water conservation measures to the satisfaction of the Anaheim Public Utilities Department: • Install a separate irrigation meter when the total landscaped area exceeds 2,500 square feet. (City of Anaheim Water Conservation Measures) • Use of efficient irrigation systems such as drip irrigation systems and automatic Prior to issuance of a building permit Public Works Department/Engineering Division; Planning Department/Building Division Building Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method systems that include moisture sensors. (City of Anaheim Water Conservation Measures) • Use of low-flow sprinkler heads in the irrigation system. (City of Anaheim Water Conservation Measures) • Use of water-conservation landscape plant materials, wherever feasible. (City of Anaheim Water Conservation Measures) • Low-flow fittings, fixtures, and equipment including low flush toilets and urinals. (City of Anaheim Water Conservation Measures) • Use of cooling tower and waterway recirculation systems. (City of Anaheim Water Conservation Measures) • Use of water efficient ice machines, dishwashers, clothes washers, and other water using appliances. (City of Anaheim Water Conservation Measures). Existing Policies and Procedures Biological Resources PPP Bio-1: The Property Owner/Developer shall comply with all provisions of Anaheim Municipal Code Section 13.12 related to tree preservation. Ongoing Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Biological Resources PPP Bio-2: The Property Owner/Developer shall comply with the provisions of the Migratory Bird Treaty Act, Federal Endangered Species Act, the California Endangered Species Act, and the Central/Coastal Subregion (NCCP/HCP) for protection of Federal or State listed species. Ongoing Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Biological Resources PPP Bio-3: The Property Owner/Developer shall comply with Section 1601-1603 of the Fish and Game Code and Section 404 of the Clean Water Act. Ongoing Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Geology and Soils PPP Geo-1: All grading operations will be conducted in conformance with the Anaheim Municipal Code, Title 17 – Land Development and Resources. During construction Public Works Department/Engineering Division; Planning Department/Building Division Public Works Site Inspection Geology and Soils PPP Geo-2: The Property Owner/Developer shall submit for approval to the State Water Resources Control Board, a Notice of Intent to be covered under the Storm Water Permit, in compliance with the National Pollutant Discharge Elimination System (NPDES) program. In addition, future projects shall be required to develop and implement a Storm Water Pollution Prevention Plan (SWPPP), which incorporates Best Management Practices (BMPs). During project permitting Public Works Department/Engineering Division; Planning Department/Building Division Grading and Building Plan Check Hazards and Hazardous Materials PPP Haz-1: The Proposed Project shall comply with all relevant local, State, and federal regulations related to hazardous materials. Ongoing Public Works Department/Engineering Division; Planning Department/Building Division Public Works and Building Site Inspection and Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Hazards and Hazardous Materials PPP Haz-2: Prior to structural demolition/renovation activities, a Certified Environmental Professional shall confirm the presence or absence of asbestos containing materials (ACMs). Should ACMs be present, demolition materials containing ACMs shall be removed and disposed of at an appropriate permitted facility. Asbestos removal shall be performed by a State certified asbestos containment contractor in accordance with the South Coast Air Quality Management District (SCAQMD) Rule 1403. Prior to site demolition activities Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Hydrology and Water Quality PPP HYD-1: The Property Owner/Developer shall comply with all applicable local, State, and federal regulations relating hydrology and water quality. During permitting and construction Public Works Department/Engineering Division; Planning Department/Building Division Public Works and Building Plan Check Noise PPP NOI-1: The following Best Management Practices, included as Conditions of Approval, would reduce any noise level increases produced by the construction equipment to the nearby noise-sensitive residential land uses: • Prior to approval of grading plans and/or issuance of building permits, the Property Owner/Developer shall include a note on the plans indicating that noise-generating Project construction activities shall only occur between the hours of 7:00 a.m. to 7:00 p.m. on any day (City of Anaheim Municipal Code, Section 6.050.010). The Project construction supervisor shall Prior to grading permit issuance and during construction Planning Department/Building Division, Advanced Planning Division; Zoning Division Grading and Building Plan Check KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method ensure compliance with the permitted construction hours. • The Property Owner/Developer shall post a construction site notice near the construction site access point or in an area that is clearly visible to the public. The notice shall include the following: job site address; permit number, name, and phone number of the contractor and owner; dates and duration of construction activities; construction hours allowed; and the City of Anaheim and construction contractor phone numbers where noise complaints can be reported and logged. • Ongoing during construction, the Construction Contractors shall do all of the following: o All construction equipment whether fixed or mobile, will be equipped with properly operating and maintained mufflers, consistent with manufacturer standards. o All stationary construction equipment will be placed so that emitted noise is directed away from the noise sensitive receptors nearest the project site. o As applicable, shut off all KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method equipment when not in use. o To the degree possible, equipment staging will be located in areas that create the greatest distance between construction- related noise and vibration sources, and sensitive receptors surrounding the project site. o Jackhammers, pneumatic equipment, and all other portable stationary noise sources will be directed away and shielded from existing residences in the vicinity of the project site. Either one- inch plywood or sound blankets can be utilized for this purpose. They should reach up from the ground and block the line of sight between equipment and existing residences. The shielding should be without holes and cracks. o No amplified music and/or voice will be allowed on the project site. o Haul truck deliveries will not occur outside of the hours presented as exempt for construction per City’s Municipal Code Section 6.70.010. KB Homes Lincoln & Sunkist Townhomes Mitigation Monitoring Program No. 385 Impact Category Mitigation Measure Implementation Timing Responsible Monitoring Party Monitoring/Reporting Method Noise PPP NOI-2: A best management practice limiting the use of a vibratory roller within 20 feet or a large bulldozer within 12 feet of the existing residential structures to the south and west of the project site will be implemented to avoid significant impacts. During construction Public Works Department/Engineering Division; Planning Department/Building Division Public Works Site Inspection Public Services PPP PS-1: The Property Owner/Developer would pay school impact fees pursuant to Senate Bill 50 (Government Code Section 65995). During project permitting Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Recreation PPP REC-1: Prior to issuance of building permits, the Property Owners/Developers shall comply with Anaheim Municipal Code, Section 17.08.250, which requires the provision of parkland and/or the payment of fees, consistent with the Quimby Act. Prior to issuance of a building permit Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check Project Design Features Noise PDF NOI-1: Windows and sliding glass doors on building elevations that will be exposed to exterior noise levels that exceed 65 dBA CNEL, will be upgraded to ensure that vehicle noise does not result in interior noise levels that exceed 45 dBA CNEL inside the residence. Prior to issuance of a building permit Planning Department/Building Division, Advanced Planning Division; Zoning Division Building Plan Check PC2022-*** STATE OF CALIFORNIA ) COUNTY OF ORANGE ) ss. CITY OF ANAHEIM ) I, Susana Barrios, Secretary of the Planning Commission of the City of Anaheim, do hereby certify that the foregoing resolution was passed and adopted at a meeting of the Planning Commission of the City of Anaheim held on December 5, 2022, by the following vote of the members thereof: AYES: NOES: ABSTAIN: ABSENT: IN WITNESS WHEREOF, I have hereunto set my hand this 5th day of December 2022. SECRETARY, PLANNING COMMISSION OF THE CITY OF ANAHEIM KB Home Lincoln & Sunkist Townhomes Project APPENDIX N CHECKLIST Prepared for: The City of Anaheim 200 S. Anaheim Boulevard Anaheim, CA 92805 Contact: Heather Allen, Principal Planner Applicant: KB Home 9915 Mira Mesa Boulevard, Suite 100 San Diego, CA 92131 Contact: John Abboud Prepared By: 27128 Paseo Espada, Suite 1524 San Juan Capistrano, CA 92675 (714) 931-9655 Contact: Laurel Reimer, AICP November 2022 ATTACHMENT NO. 3 This page is intentionally left blank. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist i TABLE OF CONTENTS 1 INTRODUCTION ............................................................................................................. 1 1.1 Purpose of the Appendix N: Environmental Checklist ............................................................................ 1 1.2 Content and Format of an Appendix N: Environmental Checklist .......................................................... 2 2 PROJECT SETTING .......................................................................................................... 3 2.1 Project Location ...................................................................................................................................... 3 2.2 Existing Land Uses and Designation of the Project Site .......................................................................... 3 2.3 Surrounding Land Uses............................................................................................................................ 3 2.4 Environmental Background ..................................................................................................................... 3 3 PROJECT DESCRIPTION .................................................................................................. 7 3.1 Project Background ................................................................................................................................. 7 3.2 Proposed Project ..................................................................................................................................... 7 3.3 Construction and Schedule ..................................................................................................................... 8 4 DISCRETIONARY APPROVALS ........................................................................................ 9 5 ENVIRONMENTAL CHECKLIST FORM ........................................................................... 15 5.1 Satisfaction of Appendix M Performance Standards ............................................................................ 17 5.2 Environmental Factors Potentially Affected: ........................................................................................ 21 5.3 Determination: ...................................................................................................................................... 21 5.4 Evaluation of Environmental Impacts of Infill Project ........................................................................... 23 5.4.1 Aesthetics ..............................................................................................................26 5.4.2 Agriculture and Forestry Resources........................................................................29 5.4.3 Air Quality ..............................................................................................................31 5.4.4 Biological Resources ..............................................................................................39 5.4.5 Cultural Resources .................................................................................................44 5.4.6 Energy....................................................................................................................47 5.4.7 Geology and Soils ...................................................................................................51 5.4.8 Greenhouse Gas Emissions ....................................................................................56 5.4.9 Hazards and Hazardous Materials ..........................................................................59 5.4.10 Hydrology and Water Quality .................................................................................64 5.4.11 Land Use and Planning ...........................................................................................70 5.4.12 Mineral Resources .................................................................................................72 KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist ii 5.4.13 Noise .....................................................................................................................74 5.4.14 Population and Housing .........................................................................................80 5.4.15 Public Services .......................................................................................................82 5.4.16 Recreation .............................................................................................................86 5.4.17 Transportation .......................................................................................................89 5.4.18 Tribal Cultural Resources .......................................................................................95 5.4.19 Utilities and Service Systems ..................................................................................98 5.4.20 Wildfire ................................................................................................................ 104 5.4.21 Mandatory Findings of Significance ...................................................................... 106 6 LIST OF PREPARERS ................................................................................................... 109 7 REFERENCES .............................................................................................................. 109 LIST OF FIGURES Figure 1 – Regional Vicinity Map .................................................................................................5 Figure 2 – Local Vicinity Map .......................................................................................................6 Figure 3 – Conceptual Site Plan .................................................................................................10 Figure 4 – Typical Building Elevations ........................................................................................11 Figure 5 – Conceptual Landscape Plan .......................................................................................12 Figure 6 – Open Space Plan .......................................................................................................13 Figure 7 – Conceptual Lighting Plan ...........................................................................................14 Figure 8 – Proximity to High Quality Transit Corridor Map.........................................................19 LIST OF TABLES Table 1 - Proposed Development ................................................................................................7 Table 2 - Construction-Related Regional Pollutant Emissions ....................................................34 Table 3 - Regional Operational Pollutant Emissions ...................................................................35 Table 4 - Local Construction Emissions at the Nearest Receptors ..............................................36 Table 5 - Project-Related Greenhouse Gas Emissions ................................................................57 KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist iii APPENDICES Appendix A – KB Home Lincoln & Sunkist Air Quality, Global Climate Change, and Energy Impact Analysis, Ganddini Group, Inc., November 21, 2022. Appendix B – Results of a Cultural and Biological Resources Due Diligence Study for the 2420 East Lincoln Avenue Project, APNs 083-731-18 and -19, Orange County, California, Brian F. Smith and Associates, Inc., rev. November 18, 2022. Appendix C – Geotechnical Exploration and Due Diligence Study, Proposed Residential Development at 2420 and 2450 East Lincoln Avenue, City of Anaheim, California, NMG Geotechnical, Inc., September 3, 2021. Appendix D – Phase I Environmental Assessment, 2420-2450 East Lincoln Avenue, Anaheim, California 92806, Hillman Consulting, August 31, 2021. Appendix D-1 – Hazardous Materials Inspection, 2420-2450 East Lincoln Avenue, Anaheim, California 92806, Hillman Consulting, September 1, 2021. Appendix E – Santa Ana Region Priority Project Water Quality Management Plan (WQMP), 2420 East Lincoln Avenue, October 4, 2022. Appendix F – Drainage Study for 2420 East Lincoln Avenue Project, Rick Engineering Company, October 3, 2022. Appendix G – Sewer Study – 2420-2450 E. Lincoln Avenue, PSOMAS, July 20, 2022. Appendix H – KB Home Lincoln & Sunkist Noise Impact Analysis, Ganddini Group, Inc., November 21, 2022. Appendix I – KB Home Lincoln & Sunkist Project Trip Generation Analysis, Ganddini Group, Inc., August 23, 2022. Appendix J – KB Home Lincoln & Sunkist Project Vehicle Miles Traveled Screening Assessment, Ganddini Group, Inc., August 23, 2022. Appendices available for review at https://www.anaheim.net/876/Environmental-Documents and at the City of Anaheim Planning and Building Department. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist iv ACRONYMS & ABBREVIATIONS Acronyms/Abbreviation Definition ADT Average Daily Traffic Applicant KB Home APN Assessor’s Parcel Number AQMP Air Quality Management Plan ASTs Above ground storage tanks BMPs Best Management Practices CAAQS California Ambient Air Quality Standards Caltrans California Department of Transportation CARB California Air Resources Board CBC California Building Code CCR California Code of Regulations CEQA California Environmental Quality Act cfs Cubic feet per second CGS California Geologic Survey CHSC California Health and Safety Code City City of Anaheim CMP Congestion Management Program CNEL Community Noise Equivalent Value CO Carbon monoxide County Orange County CRPR California Rare Plant Rank CWA Clean Water Act dB Decibel dBA A-weighted decibels EDR Environmental Data Resources, Inc. EPA Environmental Protection Agency ESA Environmental Site Assessment FEMA Federal Emergency Management Agency FTIP Federal Transportation Improvement Program GHG Greenhouse gas gpd Gallons per day HCM Highway Capacity Manual KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist v Acronyms/Abbreviation Definition ICU Intersection Capacity Utilization IS Initial Study Leq Equivalent sound level LBP Lead-based paint LOS Level of service LSTs Localized Significant Thresholds MBTA Migratory Bird Treaty Act mgd Million gallons per day MLD Most likely descendent MND Mitigated Negative Declaration MS4 Municipal Separate Storm Sewer System MSL Mean sea level MTCO2e Million metric tons of carbon dioxide equivalent NAAQS National Ambient Air Quality Standards NAHC Native American Heritage Commission NCCP Natural Communities Conservation Plan NO2 Nitrogen dioxide NPDES National Pollution Discharge Elimination System OSHA Occupational Safety and Health Administration PM2.5 Fine particulate matter PM10 Respirable particulate matter ppm Parts per million PPV Peak particle velocity RWQCB Regional Water Quality Control Board SCAB South Coast Air Basin SCAG Southern California Association of Governments SCAQMD South Coast Air Quality Management District SCCIC South Central Coastal Information Center SLF Sacred Lands File SO2 Sulfur dioxide SR-91 State Route 91 SWCRB State Water Resources Control Board SWPPP Storm Water Pollution Prevention Plan TAC Toxic air contaminant TMDLs Total maximum daily loads USTs Underground storage tanks UWMP Urban Water Management Plan V/C Volume-to-capacity VOC Volatile organic compound KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 1 1 INTRODUCTION KB Home (Applicant) is seeking approval of a Conditional Use Permit and Tentative Tract Map from the City of Anaheim (City) for the demolition of two commercial office buildings and construction of an 83-unit residential townhouse project on Housing Opportunity Sites 154 and 155 at 2420 and 2450 E. Lincoln Avenue (Proposed Project). The City of Anaheim is the Lead Agency for the Proposed Project. The Lead Agency will utilize this document as evidence that the Proposed Project qualifies for the Infill Streamlining Provisions provided by Senate Bill 226 (Simitian 2011), which is further described below. This document utilizes analysis from Environmental Impact Report (EIR) No. 330 for the 2004 City of Anaheim General Plan and Zoning Code Update and Supplemental Environmental Impact Report (SEIR) No. 346 prepared for the 2014-2021 Housing Opportunity Site Rezoning Project certified by the Anaheim City Council on September 13, 2013. 1.1 Purpose of the Appendix N: Environmental Checklist This Appendix N: Infill Environmental Checklist (Appendix N Checklist) has been prepared in accordance with the following: • California Environmental Quality Act (CEQA) of 1970 (Public Resources Code Sections 21000 et seq.). • California Code of Regulations, Title 14, Division 6, Chapter 3 (State CEQA Guidelines, Sections 15000 et seq.), specifically Sections 15060 and 15183.3. The infill streamlining provisions of CEQA were adopted in compliance with Senate Bill 226 (Simitian 2011) (“SB 226”). SB 226 was developed by the California State Legislature to address uncertainty and delay by creating a new streamlining mechanism in CEQA for infill projects that promote a specific set of environmental policy objectives. The broad purposes of SB 226 are two- fold: 1. Provide flexibility in project design by basing eligibility on environmental performance rather than prescribing specific project characteristics; and 2. Allow infill projects to avoid repetitive environmental analysis of environmental effects that were previously analyzed in a prior Environmental Impact Report for a planning-level decision. In order to qualify for the infill streamlining provision, a project site must either be in a developed urban area or adjoin existing qualified urban uses on 75 percent of the site perimeter. Appendix M of the CEQA Guidelines includes a set of performance standards required by SB 226, which a qualifying project must satisfy in order to be eligible for infill streamlining. The Proposed Project meets these performance standards, as further detailed in Section 5.1, Satisfaction of Appendix M Performance Standards. Compliance with the Appendix M performance standards leads to the next step in the infill streamlining process, which is completion of the Appendix N Checklist in the CEQA Guidelines. The Appendix N Checklist provides a tool to evaluate a development project and document its eligibility to use the infill streamlining process. The Appendix N Checklist also assists the lead KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 2 agency in identifying and summarizing project-specific effects and how those effects are or are not addressed in a prior programmatic level document or by uniformly applicable development policies: Once the lead agency has determined that a particular physical impact may occur as a result of an infill project, then the checklist answers must indicate whether that impact has already been analyzed in a prior EIR. If the effect of the infill project is not more significant that what has already been analyzed that effect of the infill project is not subject to CEQA. The brief explanation accompanying this determination should include page and section references to the portions of the prior EIR containing the analysis of that effect. The brief explanation shall also indicate whether the prior EIR included any mitigation measures to substantially lessen that effect and whether those measures have been incorporated into the infill project. Background of the prior environmental analysis is provided in Section 2.4, Environmental Background. Project Design Features (PDFs) and Standard Conditions/Existing Plans, Programs, or Policies (PPPs) The Appendix N Checklist references 1) Applicant-initiated Project Design Features (PDFs), 2) existing Standard Conditions applied to all development on the basis of federal, State, or local law, and 3) Existing Plans, Programs, or Policies currently in place which effectively reduce environmental impacts. Standard Conditions and Existing Plans, Programs, or Policies are collectively identified in this document as PPPs. Where applicable, PDFs and PPPs are listed to show their effect in reducing potential environmental impacts. Where the application of these measures does not reduce an impact to below a level of significance, applicable General Plan and Zoning Code Update Program Environmental Impact Report No. 330 (EIR No. 330) and Supplemental EIR No. 346 (EIR No. 346) (collectively referred herein as the Certified EIRs), are identified. The City would include these PDFs and PPPs along with applicable Certified EIRs mitigation measures (MMs) as Conditions of Approval of the Proposed Project. 1.2 Content and Format of an Appendix N: Environmental Checklist This Appendix N Checklist includes the following sections: Section 1: Introduction: This section provides information about CEQA, its requirements for environmental review, and explains the Appendix N Checklist that evaluates the potential impacts of the Proposed Project to the physical environment. Section 2: Project Setting: This section provides information about the Proposed Project’s location, the Project Site, and background. Section 3: Project Description: This section provides a description of the Proposed Project’s physical features and construction and operational characteristics. Section 4: Discretionary Approvals: This section describes anticipated approvals and permits needed for implementation of the Proposed Project. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 3 Section 5: Environmental Checklist: This section includes the Appendix N Checklist and evaluates the Proposed Project’s potential to result in significant adverse effects to the physical environment. 2 PROJECT SETTING 2.1 Project Location The Proposed Project is located at 2420 and 2450 E. Lincoln Avenue, the southwest corner of E. Lincoln Avenue and S. Sunkist Street in the City of Anaheim. The Project Site consists of two parcels, identified as assessor’s parcel number (APN) 083-731-18 and 083-731-19, totaling 4.0 acres (Figure 1 – Regional Vicinity Map and Figure 2 – Local Vicinity). The parcel is trapezoidal in shape and is bounded by Lincoln Avenue to the north, Sunkist Street to the east, existing single- family residential to the south, and existing multi-family residential to the west. 2.2 Existing Land Uses and Designation of the Project Site The Project Site is occupied by 56,274 square feet of commercial office buildings with associated surface parking lot and landscaping. The existing General Plan land use designation on the Project Site is Residential-Medium, which allows a density of up to 36 dwelling units per acre (du/ac). Existing zoning for the entire site is General Commercial (C-G), which provides for a range of commercial and office land uses. However, a Residential Opportunity (RO) overlay zone is present across the Project Site, which allows “by-right” housing development opportunities consistent with residential General Plan designations on sites that are zoned or developed with non- residential uses. 2.3 Surrounding Land Uses The site is bound by the following land uses: NORTH: Lincoln Avenue, with single-family residential neighborhood beyond EAST: Sunkist Street, with multi-family residential development beyond SOUTH: Single-family residential neighborhood WEST: Multi-family residential development 2.4 Environmental Background In May 2004, the Anaheim City Council certified Environmental Impact Report (EIR) No. 330, prepared as a Program EIR for the General Plan and Zoning Code Update Program. EIR No. 330 evaluated impacts associated with implementation of the Anaheim General Plan and Zoning Code Update and created Mitigation Monitoring Program No. 122 (MMP No. 122) to mitigate those impacts. In September 2013, the Anaheim City Council certified Supplemental EIR No. 346 (SEIR No. 346), as a supplemental EIR to EIR No. 330, pursuant to CEQA Guidelines Section 15163. SEIR No. 346 was prepared to serve as environmental documentation for the Housing Opportunities Sites Rezoning Project. The City approved Mitigation Monitoring Program No. 122A (MMP No. 122A) as part of SEIR No. 346. SEIR No. 346 supplemented EIR No. 330 in the areas of air quality, greenhouse gas emissions, noise, and transportation and traffic. The Rezoning Project implemented a key strategy of the City’s 2006-2014 General Plan Housing Element by rezoning 166 Housing Opportunities Sites identified in the Housing Element. The KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 4 rezoning included the application of an overlay zone to each property: either the Residential Opportunity (RO) Overlay Zone or the Mixed Use (MU) Overlay Zone. Both overlay zones allow “by-right” housing development. The Housing Element identified the Project Site as Housing Opportunity Sites 154 and 155, which received the RO Overlay Zone as a part of the Rezoning Project. One of the City’s goals in the Rezoning Project was to provide updated community-level environmental review to facilitate redevelopment. The Rezoning and application of overlay zones provides the opportunity for applicants to utilize Public Resources Code Section 21159.24, which allows for an exemption from further CEQA review for urban infill residential development that meets certain criteria. Properties designated as Housing Opportunity Sites by the General Plan would quality for a Statutory Infill Housing Exemption, as defined by Public Resources Code Section 21159.20. The City also intended for future projects consistent with the Certified EIRs and Approved Project to be able to utilize CEQA’s streamlining provisions, including those identified in SB 266, and implemented through CEQA Guidelines Section 15183.3, Streamlining for Infill Projects. Mitigation Monitoring Program No. 122A (adopted in conjunction with the certification of S EIR No. 346) applies to projects approved under the Program EIR for the General Plan and Zoning Code Update Program. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Figure 1: Regional Location Source: Anaheim GIS Not to Scale KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Figure 2: Local Vicinity Source: Google Earth 2022 Not to Scale KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 7 3 PROJECT DESCRIPTION 3.1 Project Background The Project Site appears to have originally been vacant prior to 1902 and then developed with a single residential structure by 1935. Between 1938 and 1972, the property was developed with a residence and agricultural orchards. From 1975 to present, the property has been developed with commercial uses. A Ralph’s grocery store was constructed in 1975 at 2420 E. Lincoln Avenue and was subsequently replaced in 1989 by the existing office building and associated parking and landscaping. The existing office building at 2450 E. Lincoln Avenue was constructed in 1975. The Project Site was reclassified to the Residential Opportunity (RO) Overlay Zone as a part of the Rezoning Project and identified as Housing Opportunity Sites 154-155. The maximum buildout of Housing Opportunity Sites 154-155, as listed in Table 3-2 of SEIR No. 346, is 139 residential units. 3.2 Proposed Project The Proposed Project involves the demolition of two commercial office buildings and construction of an 83-unit residential townhouse project on Housing Opportunity Sites 154 and 155. The proposed mix of residential units is summarized in Table 1 - Proposed Development and shown in Figure 3 - Conceptual Site Plan, and Figure 4 - Typical Building Elevations. Table 1 - Proposed Development Model Number Number of Units Floor Plan Unit Size (SF) Plan 1 34 2 bed/2.5 bath 1,415 Plan 2 14 3 bed/2.5 bath 1,460 Plan 3 10 3 bed/3.5 bath 1,800 Plan 4 8 4 bed/3.5 bath 1,761 Plan 5 17 4 bed/3.5 bath 1,834 Total 83 131,816 Architecture The single-family attached homes would be located in ten three-story buildings along the northern and eastern edges and in the center of the Project Site, with between six and ten units per building. The architectural style of the proposed buildings is contemporary with Spanish Colonial design details, including tile roof, stucco siding, decorative gable medallions, and decorative metal balcony railings. Buildings would be 39’ and 39’-6” in height from grade to peak of the gable roofline. Floorplans would range from two to four bedrooms and contain between 1,415 and 1,834 square feet. Parking Each unit would have an attached private two-car garage. Additional resident and guest surface parking spaces are provided along the south and west property lines. A total of 238 parking spaces would be provided to serve the residents and guests on the site. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 8 Landscape and Open Space Landscaping would include the required 20-foot-wide landscape setback along E. Lincoln Avenue, a 10-foot-wide landscape setback along S. Sunkist Street and the south property line, and 5-foot- wide setback along the west property line, in addition to interior Project site landscaping provided along walkways and in common areas. The Proposed Project would include the installation of trees with low to medium irrigation needs, such as date palm, queen palm, yellowwood, and palo verde. All grasses, shrubs, and groundcover included in the landscaping plan would have low or medium irrigation needs. These landscape types would include ground covers such as star jasmine and shrubs such as bottle brush, hopseed bush, yucca, and Japanese privet. See Figure 5 – Landscape Plan, for details on specific landscape planting details. The Proposed Project would provide 9,225 square feet of private open space features consisting of individual patios and decks. In addition, common recreational areas totaling 15,627 square feet include a dog park, community garden, and tot lot. Refer to Figure 6 - Open Space Plan, for details on the open space and recreational facilities. Lighting Site lighting consists primarily of low-level lighting to prevent light intrusion into the residential units, including a mix of bollards and targeted landscape lights. Tall light standards are also utilized to light surface parking areas along the south property line. Refer to Figure 7 – Conceptual Lighting Plan, for details on the type and placement of major site lighting features. Site Circulation Vehicular access to the Project Site would be from a two-way driveway entry on E. Lincoln Avenue to the north and a two-way driveway entry from Sunkist Street to the east. Both entries are right turn in-out only to conform to the existing street development pattern. Neither of the entries would be signalized or gated. Pedestrian access is provided from Lincoln Avenue, along sidewalks on the private roads and pedestrian walkways, connecting across the Project Site to Sunkist Street. The project will require between 4 feet and 11 feet of dedication along Lincoln Avenue to achieve the ultimate right-of-way width. It will also require reconstruction of all sidewalks and the addition of a 5-foot-wide landscaped parkway. Utilities and Infrastructure The Proposed Project would connect to existing water utility infrastructure in Sunkist Street, including a 16-inch water line, an 8-inch sewer line, and a 48-inch storm drain. The Proposed Project includes curb, gutter and sidewalk improvements along Lincoln Avenue and E. Sunkist Street. Water and electrical service will be provided by Anaheim Public Utilities and sanitation services will be provided by Republic Services as contracted through the City of Anaheim. 3.3 Construction and Schedule The Proposed Project is anticipated to be fully operational in 2026. The Proposed Project is anticipated to be built in multiple phases with demolition of the existing office buildings and associated landscape and hardscape beginning in May 2023, grading beginning in June 2023, and KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 9 vertical construction beginning in October 2023. A net import of 10,000 cubic yards of soil is identified on the conceptual grading plan. It is anticipated that the first building would be completed in February 2024, with the last building being completed in February 2026. Construction activities include demolition, site preparation, grading, building construction, architectural coatings, and paving. 4 DISCRETIONARY APPROVALS The Applicant requests City of Anaheim Planning Commission approval of the following discretionary actions to implement the Proposed Project (DEV2021-00180): • Conditional Use Permit to allow a residential planned unit development and attached single-family units. • Tentative Tract Map to establish lot subdivision for condominium purposes and right-of- way dedication along Lincoln Avenue. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Figure 3: Conceptual Site Plan Source: Summa Architecture KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Figure 4: Typical Building Elevations Source: Summa Architecture KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Figure 5: Conceptual Landscape Plan Source: Summa Architecture KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Figure 6: Open Space Plan Source: Summa Architecture KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Figure 7: Conceptual Lighting Plan Source: Visual Concepts Lighting KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 15 5 ENVIRONMENTAL CHECKLIST FORM The Appendix N Checklist assists the Lead Agency in the evaluation of potential environmental impacts of the Proposed Project. Project Design Features (PDFs), Standard Conditions/Existing Plans, Programs, or Policies (PPPs), and mitigation measures from the Certified EIRs that are applicable to the Proposed Project are included in the discussion for each topic area. As discussed in Section 2.4, Environmental Background, the Project Site was analyzed in SEIR No. 346 as a housing opportunity site and is eligible for infill streamlining pursuant to Section 15183.3 of the CEQA Guidelines and Section 21094.5 of the Public Resources Code (PRC), adopted per SB 226. SB 226 eliminates repetitive analysis of effects of a project that were previously analyzed in a programmatic EIR for a planning-level decision or that are substantially mitigated by uniformly applied development policies. The Appendix N Checklist determined that the Proposed Project would not have effects that either have not been analyzed in the Certified EIRs or are more significant than described in the Certified EIRs. The Project Site allows a density of up to 36 dwelling units per acre (du/ac). Existing zoning for the entire site is General Commercial (C-G), which provides for a range of commercial and office land uses. However, a Residential Opportunity (RO) overlay zone is present across the Project Site, which allows “by-right” housing development opportunities consistent with residential General Plan designations on sites that are zoned or developed with non-residential uses. 1. Project Title: KB Home Lincoln & Sunkist Townhomes 2. Lead Agency name and address: City of Anaheim, 200 S. Anaheim Blvd, Anaheim, CA 92805 3. Contact person and phone number: Heather Allen, Principal Planner, 714-765-4958 4. Project Location: Southwest corner of E. Lincoln Avenue and S. Sunkist Street 5. Project sponsor’s name and address: KB Home, 9915 Mira Mesa Boulevard, Suite 100, San Diego, CA 92131 6. General Plan and designation: Medium Density Residential 7. Zoning: General Commercial (C-G), within the Residential Opportunity (RO) Overlay Zone 8. Prior Environmental Documents Analyzing the Effects of the Infill Project (including State Clearinghouse Number if Assigned): • Anaheim General Plan and Zoning Code Update Environmental Impact Report No. 330, SCH No. 2003041105 (May 2004) • City of Anaheim Housing Opportunities Sites Rezoning Project Supplemental Environmental Impact Report No. 346, SCH No. 2003041105 (September 2013) 9. Location of Priority Environmental Documents Analyzing the Effects of the Infill Project: 200 S. Anaheim Blvd, Anaheim, CA 92805 10. Description of project: The Applicant is seeking approval of a Conditional Use Permit and a Tentative Tract Map from the City for demolition of two commercial office buildings and KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 16 construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155, including associated on-site and off-site improvements. See Section 3, Project Description. 11. Surrounding land uses and setting: Briefly describe the project's surroundings, including any prior uses of the project site, or, if vacant, describe the urban uses that exist on at least 75% of the project’s perimeter: The Project Site is bound by Lincoln Avenue and single- family residential the north; Sunkist Street and multi-family residential to the east, single- family residential to the south, and multi-family residential to the west. The Project Site is currently developed with 56,274 square feet of commercial office building and associated site development. Access to the Project Site is available directly from E. Lincoln Avenue and S. Sunkist Street. Topography of the Project Site is predominantly a flat developed site with existing paved parking lot and associated landscape planters. The Project Site previous uses included agricultural orchards, residential, and commercial office. The existing General Plan designation on the Project Site is Residential-Medium, which allows a density of up to 36 dwelling units per acre (du/ac). Existing zoning for the entire site is General Commercial (C- G), which provides for a range of commercial and office land uses. However, a Residential Opportunity (RO) overlay zone is present across the Project Site, which allows “by-right” housing development opportunities consistent with residential General Plan designations on sites that are zoned or developed with non-residential uses. 12. Other public agencies whose approval is required (e.g., permits, financing approval, or participation agreement): None 13. Have California Native American tribes traditionally and culturally affiliated with the project area requested consultation pursuant to Public Resources Code section 21080.3.1? If so, is there a plan for consultation that includes, for example, the determination of significance of impacts to tribal cultural resources, procedures regarding confidentiality, etc.? Note: Conducting consultation early in the CEQA process allows tribal governments, lead agencies, and project proponents to discuss the level of environmental review, identify and address potential adverse impacts to tribal cultural resources, and reduce the potential for delay and conflict in the environmental review process. (See Public Resources Code section 21080.3.2.) Information may also be available from the California Native American Heritage Commission’s Sacred Lands File per Public Resources Code section 5097.94 and the California Historical Resources Information System administered by the California Office of Historic Preservation. Please also note that Public Resources Code section 21082.3(c) contains provisions specific to confidentiality. The Appendix N Checklist is not a type of CEQA document subject to the tribal consultation requirements under PRC Section 21080.3.1. As part of the Certified EIRs, the City of Anaheim, acting as Lead Agency, initiated consultation with California Native American tribes in accordance with Senate Bill 18 (SB 18). No tribal cultural resources were identified as a result of the consultation. No additional consultation is required in accordance with the requirements of Assembly Bill (AB) 52 and Senate Bill (SB) 18. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 17 5.1 Satisfaction of Appendix M Performance Standards Provide the information demonstrating that the infill project satisfies the performance standards in Appendix M. For mixed-use projects, the predominant use will determine which performance standards apply to the entire project. 1. Does the non-residential infill project include a renewable energy feature? If so, describe below. If not, explain below why it is not feasible to do so. The Proposed Project is a residential infill project and is therefore not required to include an on-site renewable energy feature. However, pursuant to Title 24 of the California Building Code, the Proposed Project would include Energy Star rated appliances for all residential units. 2. If the project site is included on any list compiled pursuant to Section 65962.5 of the Government Code, either provide documentation of remediation or describe the recommendations provided in a preliminary endangerment assessment or comparable document that will be implemented as part of the project. The Project Site is not identified as having Recognized Environmental Conditions (RECs), Historical Recognized Environmental Conditions (HRECs), or Controlled Recognized Environmental Conditions (CRECs). An analysis is included in Section 5.4.8, Hazards and Hazardous Materials. 3. If the infill project includes residential units located within 500 feet, or such distance that the local agency or local air district has determined is appropriate based on local conditions, a high-volume roadway or other significant source of air pollution, as defined in Appendix M, describe the measures that the project will implement to protect public health. Such measures may include policies and standards identified in the local general plan, specific plans, zoning code or community risk reduction plan, or measures recommended in a health risk assessment, to promote the protection of public health. Identify the policies or standards, or refer to the site-specific analysis, below. (Attach additional sheets if necessary.) The Proposed Project is not located within 500 feet of a rail line or a high-volume roadway (SR-57) and therefore a health risk assessment (HRA) is not required. 4. For residential projects, the project satisfies which of the following? ☐ Located within a low vehicle travel area, as defined in Appendix M. (Attach VMT map.) ☒ Located within ½ mile of an existing major transit stop or an existing stop along high- quality transit corridor. (Figure 8 – Proximity to High Quality Transit Corridor Map) ☐ Consists of 300 or fewer units that are each affordable to low-income households. (Attach evidence of legal commitment to ensure the continued availability and use of the housing units for lower income households, as defined in Section 50079.5 of the Health and Safety Code, for a period of at least 30 years, at monthly housing costs, as determined pursuant to Section 50053 of the Health and Safety Code.) KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 18 The Project Site is within 0.5 mile of an existing bus stop on Orange County Transportation Authority (OCTA) Route 57 on State College Boulevard (Exhibit 8), which has AM and PM peak-hour headways of 15 minutes or less, which allows the Project Site to qualify as a high-quality transit corridor. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Figure 8: Proximity to High Quality Transit Corridor Source: City of Anaheim, SCAG Not to Scale OCTA Route 57 Bus Stop Project Site High Quality Transit Stops Buffer (1/2 mile) KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 20 This page is intentionally left blank. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 21 5.2 Environmental Factors Potentially Affected: The environmental factors checked below would be potentially affected by the Proposed Project, involving at least one impact that is a "Potentially Significant Impact" as indicated by the checklist on the following pages. ☐ Aesthetics ☐ Agriculture & Forestry Resources ☐ Air Quality ☐ Biological Resources ☐ Cultural Resources ☐ Energy ☐ Geology/Soils ☐ Greenhouse Gas Emissions ☐ Hazards and Hazardous Materials ☐ Hydrology/Water Quality ☐ Land Use/Planning ☐ Mineral Resources ☐ Noise ☐ Population/Housing ☐ Public Services ☐ Recreation ☐ Transportation ☐ Tribal Cultural Resources ☐ Utilities/Service Systems ☐ Wildfire ☐ Mandatory Findings of Significance 5.3 Determination: Based on this initial evaluation: ☒ I find that the proposed infill project WOULD NOT have any significant effects on the environment that either have not already been analyzed in a prior EIR or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate. Pursuant to Public Resources Code Section 21094.5, CEQA does not apply to such effects. A Notice of Determination (Section 15094) will be filed. ☐ I find that although the proposed infill project will have effects that either have not been analyzed in a prior EIR, or are more significant than describe in the prior EIR, and that no uniformly applicable development policies would substantially mitigate such effects. With respect to those effects that are subject to CEQA, I find that such effects WOULD NOT be significant and a NEGATIVE DECLARATION, or if the project is a Transit Priority Project a Sustainable Communities Assessment, will be prepared. ☐ I find that the proposed infill project will have effects that either have not been analyzed in a prior EIR, or are more significant than describe in the prior EIR, and that no uniformly applicable development policies would substantially mitigate such effects. I find that although those effects could be significant, there will not be a significant effect in this case because revisions in the infill project have been made by or agreed to by the project proponent. A MITIGATED NEGATIVE DECLARATION, or if the project is a Transit Priority Project a SUSTAINABLE COMMUNITIES ENVIRONMENTAL ASSESSMENT, will be prepared. ☐ I find that the proposed infill project would have effects that either have not been analyzed in a prior EIR, or are more significant than described in the prior EIR, and that no uniformly applicable development policies would substantially mitigate such effects. I find that those effects WOULD be significant, and an infill ENVIRONMENTAL IMPACT REPORT is required to analyze those effects that are subject to CEQA. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 22 _____________________________________________ _______________________ Signature Date Heather Allen, Principal Planner _______________________ Printed Name/Title Phone KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 23 5.4 Evaluation of Environmental Impacts of Infill Project 1. A brief explanation is required for all answers except “No Impact” answers that are adequately supported by the information sources a lead agency cites in the parentheses following each question. A “No Impact” answer is adequately supported if the referenced information sources show that the impact simply does not apply to projects like the one involved (e.g. the project falls outside a fault rupture zone). A “No Impact” answer should be explained where it is based on project-specific factors as well as general standards (e.g. the project will not expose sensitive receptors to pollutants, based on a project-specific screening analysis). 2. All answers must take account of the whole action involved, including off-site as well as on- site, cumulative as well as project-level, indirect as well as direct, and construction as well as operational impacts. 3. For the purposes of this checklist, “prior EIR” means the environmental impact report verified for a planning level decision, as supplemented by any subsequent or supplemental environmental impact reports, negative declarations, or addenda to those documents. “planning-level decision” means the enactment or amendment of a general plan, community plan, specific plan, or zoning code. (Section 15183.3(e).) 4. Once the lead agency has determined that a particular physical impact may occur as a result of an infill project, then the checklist answers must indicate whether the impact has already been analyzed in a prior EIR. If the effect of the infill project is not more significant than what has already been analyzed, that effect of the infill project is not subject to CEQA. The brief explanation accompanying this determination should include page and section references to the portions of the prior EIR containing the analysis of that effect. The brief explanation shall also indicate whether the prior EIR included any mitigation measures to substantially lessen that effect and whether those measures has been incorporated into the infill project. 5. If the infill project would cause a significant adverse effect that either is specific to the project site and was not analyzed in a prior EIR or is more significant than what was analyzed in a prior EIR, the lead agency must determine whether uniformly applicable development policies or standards that have been adopted by the lead agency, or city or county, would substantially mitigate that effect. If so, the checklist shall explain how the infill project’s implementation of the uniformly applicable development policies will substantially mitigate that effect. That effect of the infill project is not subject to CEQA if the lead agency makes a finding, based upon substantial evidence, that the development policies or standards will substantially mitigate that effect. 6. If all effects of an infill project were either analyzed in a prior EIR or are substantially mitigated by uniformly applicable development policies or standards, CEQA does not apply to the project, and the lead agency shall file a Notice of Determination. 7. Effects of an infill project that either have not been analyzed in a prior EIR, or that uniformly applicable development policies or standards do not substantially mitigate, are subject to CEQA. With respect to those effects of the infill project that are subject to KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 24 CEQA, the checklist shall indicate whether those effects are significant, less than significant with mitigation, or less than significant. If there are one or more “Significant Impact” entries when the determination is made, an infill EIR is required. The infill EIR should be limited to analysis of those effects determined to be significant. (Sections 15128, 15183.3(d).) 8. “Less Than Significant with Mitigation Incorporated” applies where the incorporation of mitigation measures will reduce an effect of an infill project that is subject to CEQA from “Significant Impact” to a “Less Than Significant Impact.” The lead agency must describe the mitigation measures, and briefly explain how those measures reduce the effect to a less than significant level. If the effects of an infill project that are subject to CEQA are less than significant with mitigation incorporated, the lead agency may prepare a Mitigated Negative Declaration. If all of the effects of the infill project that are subject to CEQA are less than significant, the lead agency may prepare a Negative Declaration. 9. The analysis of each issue should identify: a. the significance criteria or threshold used to evaluate each question; and b. the mitigation measure identified, if any, to reduce the impact to less than significance. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 25 This page intentionally left blank. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 26 5.4.1 Aesthetics Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Have a substantial adverse effect on a scenic vista? Less than Significant ☐ ☒ b) Substantially damage scenic resources, including, but not limited to, trees, rock outcroppings, and historic buildings within a State scenic highway? Less than Significant ☐ ☒ c) In non-urbanized areas, substantially degrade the existing visual character or quality of public views of the site and its surroundings? (Public views are those that are experienced from a publicly accessible vantage point). If the project is in an urbanized area, would the project conflict with applicable zoning and other regulations governing scenic quality? Less than Significant ☐ ☒ d) Create a new source of substantial light or glare which would adversely affect day or nighttime views in the area? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the aesthetic impacts related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.1.4 concluded that buildout of the General Plan would result in less than significant impacts related to scenic resources, scenic vistas, visual character, and light and glare upon implementation of General Plan goals and policies, and existing codes and regulations. No mitigation measures were required in MMP No. 122. Supplemental EIR No. 346, Chapter 7, page 7-3 and Appendix A, page 27 concluded that buildout of the Housing Opportunity Sites would not result in new impacts or impacts greater than those identified in EIR No. 330. No new mitigation measures were required in MMP No. 122A. Aesthetic resources and scenic vistas within the City are protected through implementation of the Green Element and Community Design Element of the General Plan. The purpose of the KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 27 Green Element is to combine all of Anaheim’s open space, conservation, recreation, and landscaping resources into one comprehensive, integrated document. The Green Element considers not only existing parks and open space, but also potential recreational opportunities and enhancements to the appearance of existing areas through enhanced landscaping of Anaheim’s corridors, community edges, and City entryways. The Community Design Element provides policy guidance for the built environment to recognize the importance of community appearance and identity to its vitality, economic health, and overall quality of life. A 4.5-mile portion of SR-91 is an officially designated State Scenic Highway from SR-55 to Weir Canyon Road. The freeway runs along the banks of the Santa Ana River and views include mountain ridgelines, rolling hills, canyons, intermittent riparian and chaparral vegetation, and residential and commercial development. The Scenic Corridor Overlay Zone in the Anaheim Municipal Code enforces this designation, and any impacts are less than significant. The City of Anaheim is largely built out. Major open space features are in the eastern part of the City within the Hill and Canyon Areas. 7,788 acres of land are designated for Open Space/Recreation, including golf courses, parks, open space, and water uses. The preservation of landforms within the Hill and Canyon areas as part of The Irvine Ranch Land Reserve and the Cypress Canyon addition to the Chino Hills State Park will result in a substantial open space preservation area that includes the highest elevation and thus most visible portions of the City. As a result, potential impacts to scenic vistas are less than significant. Development that occurs based on the implementation of the General Plan and Zoning Code Update may introduce additional lighting to provide nighttime street and building illumination, as well as security lighting, nighttime traffic, and light associated with future development. The Community Design and Green Elements call for comprehensive corridor landscape programs and use of trees, hedges, and berms as screening measures along roadways, and design guidelines for specific areas of the City will reduce the impacts of light and glare to a level of less than significant. Impacts Associated with the Proposed Project: The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155, which would have a maximum height of 39 feet 6 inches at the highest point on the three-story buildings. The existing two-story commercial office buildings on the Project Site are of contemporary architectural style with simplified Spanish Colonial design elements, including a tile roof, stucco walls, and applied arched window and door moldings. The Proposed Project has a similar architectural vernacular, but with an expanded material palette and articulated massing. Replacing nondescript office buildings with residential buildings of varied architectural style and mass would improve the visual character and quality of the Project Site by providing more visual architectural interest along the Lincoln Avenue corridor, as well enhanced landscaping in the property setback areas. See Figure 4 - Typical Building Elevations and Figure 5 – Conceptual Landscape Plan. EIR No. 330 identifies SR-91 east of SR-55, located over three miles to the northeast of the Project Site, as a scenic highway. EIR No. 330 also identifies the open space features of Anaheim KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 28 Hills, over five miles to the east, as scenic vistas. Due to the distance and intervening urban development between the Project Site and the scenic highway and vistas in Anaheim Hills, the Proposed Project would not have a substantial adverse effect on these scenic resources. Residential uses on the Project Site would result in less than significant increases in nighttime light or glare as the Proposed Project is replacing an existing commercial office use in an urbanized neighborhood. The Proposed Project would use typical residential construction materials such a wood, stucco, and glass, and would not use reflective materials that would result in glare. Prior to the issuance of a building permit, the Proposed Project would be subject to building code requirements that include an assessment of exterior lighting plans to ensure lighting fixtures are shielded to prevent light spillage. With the residential nature of the Proposed Project and the approval of lighting plans, there would be no new or increase in significant impacts related to lighting and glare. Therefore, a less than significant impact will occur, and no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.1, Aesthetics, Pages 5-1 to 5-12. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-3 and Appendix A, Initial Study, Page 27. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 29 5.4.2 Agriculture and Forestry Resources Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance (Farmland), as shown on the maps prepared pursuant to the Farmland Mapping and Monitoring Program of the California Resources Agency, to non- agricultural use? No Impact ☐ ☒ b) Conflict with existing zoning for agricultural use, or a Williamson Act contract? No Impact ☐ ☒ c) Conflict with existing zoning for, or cause rezoning of, forest land (as defined in Public Resources Code section 12220(g)), timberland (as defined by Public Resources Code section 4526), or timberland zoned Timberland Production (as defined by Government Code section 51104(g))? No Impact ☐ ☒ d) Result in the loss of forest land or conversion of forest land to non-forest use? No Impact ☐ ☒ e) Involve other changes in the existing environment which, due to their location or nature, could result in conversion of Farmland, to non-agricultural use or conversion of forest land to non-forest use? No Impact ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. Program EIR No. 330 concluded that buildout of the General Plan would result in no potential impacts to agricultural and forest resources and no mitigation measures were required in MMP KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 30 No. 122. Supplemental EIR No. 346 concluded that buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No. 122A. Impacts Associated with the Proposed Project: No Impact (a – e). The majority of the City of Anaheim is built out and does not have any large areas which are currently in agricultural production. However, the General Plan continues to allow use of easements for limited agricultural production including nursery crops. There is no unique, prime or farmland of statewide importance located within the City. There are no Williamson Act contracts within the project area. No impacts would occur. The Proposed Project is currently developed with commercial office uses, is not located on a site designated as unique, prime or farmland of statewide importance, and does not have a Williamson Act contract. Current zoning is General Commercial (C-G), which provides for a range of commercial and office land uses, with a Residential Opportunity (RO) overlay zone. Therefore, the Proposed Project would not conflict with zoning for forest land, timberland, or result in the loss or conversion of forest land. Existing Programs and Policies: None Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 8, Impacts Found Not Significant, Page 11-1 and Appendix A, Initial Study and NOP. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-2 and Appendix A, Initial Study and NOP, Pages 27-28. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 31 5.4.3 Air Quality Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Conflict with or obstruct implementation of the applicable air quality plan? Less than Significant ☐ ☒ b) Result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non- attainment under an applicable federal or State ambient air quality standard? Significant Unavoidable Adverse Impact ☐ ☒ c) Expose sensitive receptors to substantial pollutant concentrations? Less than Significant After Mitigation ☐ ☒ d) Result in other emissions (such as those leading to odors) adversely affecting a substantial number of people? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330, Section 5.2.4 addressed the air quality impacts associated with implementation of the General Plan and Zoning Code Update Program. It concluded that buildout of the General Plan would generate emissions in excess of the South Coast Air Quality Management District’s (SCAQMD) regional thresholds for carbon monoxide (CO), reactive organic gases (ROG), nitrogen oxides (NOx), and particulate matter (PM10). However, the General Plan is consistent with the Air Quality Management Plan (AQMP) and other regional plan strategies to reduce the number and length of trips in the region and would improve the balance between jobs and housing at the sub- regional level. While mitigation measures included in the EIR would reduce emissions, the impact would remain significant and unavoidable. Impacts associated with potential obstruction of applicable air quality plans, violation of air quality standards, exposure of sensitive receptors to substantial pollutant concentrations, and odors were all less than significant without the need for mitigation. SEIR No. 346 concluded that buildout of the Approved Project would remain significant and unavoidable with regard to regional thresholds for criteria pollutants. Impacts associated with exposing sensitive receptors to major sources of air pollution were found to be less than significant with the addition of a new mitigation measure: MM 5.2-7. MM 5.2-7 requires the preparation of a Health Risk Assessment (HRA) for certain projects in order to reduce the air KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 32 quality land use compatibility impacts of the Approved Project to less than significant. All other impacts were found to be less than significant. EIR No. 330 acknowledges that though planned development within the City would ultimately be market driven, for modeling purposes, the Air Quality analysis assumed that all allowable uses would be implemented by the year 2025 and emissions are based on this horizon. Construction activity would cause temporary, short-term emissions of various air pollutants. Though information regarding specific development projects, soil types, and the locations of receptors would be needed in order to quantify the level of impact, it is reasonable to conclude that given the amount of development that the General Plan and Zoning Code Update could accommodate, some major construction activities could be occurring at any given time which could exceed SCAQMD’s adopted significance thresholds. Actual significance would be determined on a project-by-project basis as development applications are submitted. Operational impacts could result from local and regional vehicle emissions generated by future traffic growth, as well as direct emissions due to the use of on-site utilities and consumer goods associated with the proposed land uses. Regarding emissions from mobile sources, because of more stringent emission standards and improved technology related to newer vehicles, future emissions generated within the City would be less than current levels. Emissions from various industrial and commercial processes allowed under the General Plan and Zoning Code Update are controlled at the local and regional level through permitting and would be subject to further study and health risk assessment prior to the issuance of any necessary air quality permits and are not further addressed in the analysis. However, even after the application of Goals and Policies, as well as Mitigation Measures to reduce air quality impacts, cumulative mobile source and area source emissions related to future growth would exceed the daily SCAQMD thresholds for CO2, NOx, ROG, and PM10 in the SCAB region, which is a federal non-attainment area. This is considered a significant and unavoidable adverse impact, and the Anaheim City Council adopted a Statement of Overriding Considerations with regard to this potential impact. Although implementation of development consistent with the General Plan and Zoning Code Update will result in significant regional air quality impacts, it is consistent with the AQMP and other regional plan strategies to reduce the number of trips and the length of trips in the region, and to improve the balance between jobs and housing at the sub-regional level. The General Plan and Zoning Code Update facilitates the development of housing opportunities in close proximity with regional employment and transportation centers. Therefore, the General Plan and Zoning Code Update is consistent with the AQMP, and this is not considered to be a significant impact. Projected CO2 concentrations at build out are below the State and Federal 1-hour and 8-hour standards, therefore, no significant impacts are anticipated. Future residential and commercial development would involve minor odor-generating activities, such as backyard barbeque smoke, lawn mower exhaust, application of exterior paints from home improvement, etc. These types and concentrations of odors are typical of residential communities and are not considered significant air quality impacts. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 33 Impacts Associated with the Proposed Project: The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units and 238 parking spaces on Housing Opportunity Sites 154 and 155. The following analysis is based on the Air Quality, Global Climate Change, and Energy Impact Analysis report prepared by Ganddini Group, dated November 21, 2022 (Appendix A). Where available, the significance criteria established by the applicable air quality management district or air pollution control district may be relied upon to make the following determinations. Would the project: a) Conflict with or obstruct implementation of the applicable air quality plan? The SCAQMD CEQA Handbook states that "New or amended General Plan Elements (including land use zoning and density amendments), Specific Plans, and significant projects must be analyzed for consistency with the AQMP". Strict consistency with all aspects of the plan is usually not required. A Proposed Project should be considered to be consistent with the AQMP if it furthers one or more policies and does not obstruct other policies. The SCAQMD CEQA Handbook identifies two key indicators of consistency: (1) Whether the project will result in an increase in the frequency or severity of existing air quality violations or cause or contribute to new violations, or delay timely attainment of air quality standards or the interim emission reductions specified in the AQMP. (2) Whether the project will exceed the assumptions in the AQMP in 2016 or increments based on the year of project buildout and phase. Both of these criteria are evaluated in the following sections. Criteria 1 – Increase in the Frequency or Severity of Violations Based on the air quality modeling analysis prepared for the Proposed Project, short-term construction impacts will not result in significant impacts based on the SCAQMD regional and local thresholds of significance. This Air Analysis also found that, long-term operations impacts will not result in significant impacts based on the SCAQMD local and regional thresholds of significance. Therefore, the Proposed Project is not projected to contribute to the exceedance of any air pollutant concentration standards and is found to be consistent with the AQMP for the first criterion. Criteria 2 – Exceed Assumptions in the AQMP? Consistency with the AQMP assumptions is determined by performing an analysis of the Proposed Project with the assumptions in the AQMP. The emphasis of this criterion is to ensure that the analyses conducted for the Proposed P roject are based on the same forecasts as the AQMP. The 2020-2045 Regional Transportation/Sustainable Communities Strategy prepared by SCAG (2020) includes chapters on: the challenges in a changing region, creating a plan for our future, and the road to greater mobility and sustainable growth. These chapters currently respond directly to federal and State requirements placed on SCAG. Local governments are KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 34 required to use these as the basis of their plans for purposes of consistency with applicable regional plans under CEQA. For this project, the City of Anaheim Land Use Plan defines the assumptions that are represented in the AQMP. The Project Site has a current land use designation of Residential Medium Density on the City of Anaheim General Plan Land Use Map. The Residential Medium Density land use designation allows residential uses at density of up to 36 du/ac. The Proposed Project includes 83, 3-story townhome dwelling units on approximately 4 acres, at a density of approximately 21 du/ac. Therefore, the Proposed Project is not anticipated to exceed the AQMP assumptions for the Project Site and is found to be consistent with the AQMP for the second criterion. Based on the above, the Proposed Project will not result in an inconsistency with the SCAQMD AQMP. Therefore, a less than significant impact will occur, and no further environmental analysis is required. b) Result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non-attainment under an applicable federal or State ambient air quality standard? Within the SCAQMD, this impact relates to regional criteria pollutant impacts, determined by the comparison of the Proposed Project’s construction and operational emissions to SCAQMD’s regional significance thresholds. The California Emissions Estimator Model (CalEEMod) Version 2022.1 calculated emissions associated with the Proposed Project. Detailed modeling assumptions and methodology are contained in the Air Analysis. Table 2 and Table 3 below provide the results of the modeling. Table 2 - Construction-Related Regional Pollutant Emissions Pollutant Emissions (pounds/day) Activity ROG NOx CO SO2 PM10 PM2.5 Maximum Daily Emissions 1, 2 19.70 34.60 35.90 0.07 8.10 4.29 SCAQMD Thresholds 75 100 550 150 150 55 Exceeds Thresholds? No No No No No No Notes: Source: CalEEMod Version 2022.1 1. On-site emissions from equipment operated on-site that is not operated on public roads. Demolition, site preparation, and on-site grading PM-10 and PM-2.5 emissions show mitigated values for fugitive dust for compliance with SCAQMD Rule 403. 2. Grading, construction, painting, and paving phases may overlap. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 35 Table 3 - Regional Operational Pollutant Emissions Pollutant Emissions (pounds/day) Activity ROG NOx CO SO2 PM10 PM2.5 Maximum Daily Emissions 5.84 3.77 23.80 0.06 1.91 0.50 Reduction from existing office uses to be removed -3.95 -2.24 -21.50 -0.05 -1.58 -0.33 Total 1.89 1.53 2.30 0.01 0.33 0.17 SCAQMD Thresholds 55 55 550 150 150 55 Exceeds Thresholds? No No No No No No Notes: Source: CalEEMod Version 2022.1; the higher of either summer or winter emissions As shown, construction and operational emissions are far below SCAQMD regional emissions thresholds of significance for any pollutant. EIR No. 330 and SEIR No. 346 determined that there would be a significant and unavoidable impact related to cumulatively considerable increase in criteria pollutants. As illustrated above, the Proposed Project would result in less than significant impacts related to criteria pollutants and would not introduce impacts that have not already been analyzed in EIR No. 330 and SEIR No. 346 or that are more significant than previously analyzed, or that the application of uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. c) Expose sensitive receptors to substantial pollutant concentrations? The SCAQMD has developed Localized Significance Thresholds (LSTs) in addition to the regional thresholds described above to address localized impacts of criteria pollutants. The LSTs depend on the location of the Proposed Project, overall size of the Project Site and distance of existing sensitive receptors from the Project Site. The nearest sensitive receptors to the Proposed Project include the existing single-family residential uses with property lines located adjacent to the south and approximately 100 feet (~30 meters) to the north and the existing multi-family residential uses with property lines located adjacent to the west and approximately 270 feet (~82 meters) to the northeast and 75 feet (~23 meters) to the southeast of the project site; therefore, to be conservative, the 25 meter threshold was used. According to SCAQMD LST methodology, LSTs would apply to the operational phase of a project if the Proposed Project includes stationary sources or attracts mobile sources (such as heavy- duty trucks) that may spend long periods queuing and idling at the site, such as industrial warehouse/transfer facilities. The Proposed Project is the development of the site with residential uses and does not include such uses. Therefore, due the lack of stationary source emissions, no long-term localized significance threshold analysis is warranted. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 36 Table 4 - Local Construction Emissions at the Nearest Receptors On-Site Pollutant Emissions (pounds/day) Activity NOx CO PM10 PM2.5 Demolition 27.30 23.50 2.95 1.37 Site Preparation 26.90 24.30 1.23 3.76 Grading 20.00 19.70 3.70 2.21 Building Construction 11.80 13.20 0.55 0.51 Paving 6.52 8.84 0.29 0.26 Architectural Coating 0.88 1.14 0.03 0.03 SCAQMD Thresholds 115 715 6 4 Exceeds Thresholds? No No No No Notes: Calculated from CalEEMod and SCAQMD’s Mass Rate Look-up Tables 2 acre at a distance of 25 meters in SRA 17 Central Orange County. As shown, the Proposed Project would not exceed the LSTs for construction and operation for any pollutants and the impacts would be less than significant for localized criteria pollutants. The Proposed Project would not introduce impacts that have not already been analyzed in EIR No. 330 and SEIR No. 346 or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. d) Result in other emission (such as those leading to odors) adversely affecting a substantial number of people? Construction-Related Odor Impacts Potential sources that may emit odors during construction activities include the application of materials such as asphalt pavement. The objectionable odors that may be produced during the construction process are of short-term in nature and the odor emissions are expected to cease upon the drying or hardening of the odor producing materials. Due to the short-term nature and limited amounts of odor producing materials being utilized, no significant impact related to odors would occur during construction of the proposed project. Diesel exhaust and VOCs would be emitted during construction of the project, which are objectionable to some; however, emissions would disperse rapidly from the Project Site and therefore should not reach an objectionable level at the nearest sensitive receptors. Operations-Related Odor Impacts Potential sources that may emit odors during the ongoing operations of the P roposed Project would include odor emissions from the intermittent diesel delivery truck emissions and trash KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 37 storage areas. Due to the distance of the nearest receptors from the Project Site and through compliance with SCAQMD’s Rule 402 no significant impact related to odors would occur during the ongoing operations of the proposed project. The Proposed Project would not introduce impacts that EIR 330 and SEIR 346 have not already analyzed or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. The analysis concluded that the Proposed Project would not result in regional emissions exceeding SCAQMD thresholds of significance for any criteria pollutant, exceed localized significance thresholds for any criteria pollutant, or generate objectionable odors affecting a substantial number of people. Likewise, air quality impacts of the Proposed Project would not exceed any threshold of significance for criteria pollutants and would not increase the development intensity reflected in the General Plan; therefore, the analysis concluded the Proposed Project would not conflict with the SCAQMD AQMP. Established requirements addressing construction equipment operations, construction material use, storage, and disposal requirements act to minimize odor impacts that may result from construction activities. Construction-source odor emissions would be temporary, short-term, and intermittent in nature and would not result in persistent impacts that would affect substantial numbers of people. Therefore, potential construction-source odor impacts are less than significant. The air quality analysis found that the Proposed Project would generate a net decrease of emissions of VOCs, CO, SOx, PM-10, and PM-2.5, and generate a net decrease of NOx compared to existing conditions (Appendix A, Table 9). The analysis substantiates that the Proposed Project would not result in a carbon monoxide hotspot or generate objectionable odors. Therefore, a less than significant impact will occur, and no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP 122 Mitigation Measures: MM 5.2-1: Prior to the issuance of grading permits, the Property Owner/Developer shall include a note on all grading plans, which requires the construction contractor to implement following measures during grading. These measures shall also be discussed at the pre-grade conference. • Use low emission mobile construction equipment. • Maintain construction equipment engines by keeping them tuned. • Use low sulfur fuel for stationary construction equipment. • Utilize existing power sources (i.e., power poles) when feasible. • Configure construction parking to minimize traffic interference. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 38 • Minimize obstruction of through-traffic lanes. When feasible, construction should be planned so that lane closures on existing streets are kept to a minimum. • Schedule construction operations affecting traffic for off-peak hours. • Develop a traffic plan to minimize traffic flow interference from construction activities (the plan may include advance public notice of routing, use of public transportation and satellite parking areas with a shuttle service). Sources: Appendix A – KB Home Lincoln & Sunkist Air Quality, Global Climate Change, and Energy Impact Analysis, Ganddini Group, Inc., November 21, 2022. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.2, Air Quality, Page 5-13 through 5-34. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 5.1, Air Quality, Page 5.1-1 through 5.1-25; Chapter7, CEQA Mandated Sections, Page 7-4 and Appendix A, Initial Study and NOP, pages 28-29. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 39 5.4.4 Biological Resources Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a candidate, sensitive, or special status species in local or regional plans, policies, or regulations, or by the California Department of Fish and Wildlife, U.S. Fish and Wildlife Service, or NOAA Fisheries? Less than Significant After Mitigation ☐ ☒ b) Have a substantial adverse effect on any riparian habitat or other sensitive natural community identified in local or regional plans, policies, regulations or by the California Department of Fish and Wildlife or U.S. Fish and Wildlife Service? Less than Significant After Mitigation ☐ ☒ c) Have a substantial adverse effect on State or federally protected wetlands (including, but not limited to, marsh, vernal pool, coastal, etc.) through direct removal, filling, hydrological interruption, or other means? Less than Significant After Mitigation ☐ ☒ d) Interfere substantially with the movement of any native resident or migratory fish or wildlife species or with established native resident or migratory wildlife corridors, or impede the use of native wildlife nursery sites? Less than Significant After Mitigation ☐ ☒ KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 40 Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity e) Conflict with any local policies or ordinances protecting biological resources, such as a tree preservation policy or ordinance? Less than Significant ☐ ☒ f) Conflict with the provisions of an adopted Habitat Conservation Plan, Natural Community Conservation Plan, or other approved local, regional, or State habitat conservation plan? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 addressed the potential impacts to biological resources associated with implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.3.4 concluded that the buildout of the General Plan would result in less than significant impacts to biological resources upon implementation of General Plan goals and policies, existing codes and regulations, and MMs 5.3-1 through 5.3-9 in MMP No. 122. Supplemental EIR No. 346 concluded that the buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No. 122A. The sensitive vegetation communities in the City of Anaheim include coastal sage scrub, coast live oak/walnut woodland, riparian areas, and wetlands primarily in the Hill and Canyon Area. The area is also home to a number of sensitive animal species, and it provides important foraging, dispersal, migratory, and wildlife corridors. The areas along the Santa Ana River and the eastern portion of the City contain riparian habitat that may be impacted by development and recreational uses in these areas. Implementation of development consistent with the General Plan and Zoning Code Update could result in both direct and indirect significant adverse impacts to wildlife and habitat occurring in the Hill and Canyon Area and in the Santa Ana River. The Project site is not proximate to these areas. Several areas within the Hill and Canyon Area of the City and its Sphere-of-Influence are utilized as migratory corridors for the movement of wildlife. Development within the Hill and Canyon Area could cause an increase in both vehicular traffic levels and nighttime light levels. Both of these factors have been found to deter the movement of many animals. The Project site is not proximate to these areas. To minimize these impacts, the General Plan and Zoning Code Update establishes goals and policies related to the protection of open space and wildlife habitat and migratory corridors, as well as tree preservation in accordance with the City of Anaheim Street Tree Ordinance. The majority of impacts will occur as a result of project-specific activities and development proposals KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 41 would be assessed for potential impacts pursuant to CEQA and associated State and federal regulations at that time. Mitigation measures may be required at the project level to minimize the impacts of development. Implementation of the adopted NCCP/HCP, the General Plan Goals and Policies, existing codes and regulations, and mitigation measures will reduce all biological impacts to a level of insignificance. Impacts Associated with the Proposed Project: Would the project: a) Have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a candidate, sensitive, or special status species in local or regional plans, policies, or regulations, or by the California Department of Fish and Wildlife or United States Fish and Wildlife Service? The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and ancillary structures and has non- native trees, shrubs, and turf along the property boundaries. The Project Site contains no potential native species habitat areas. Consistent with the analysis of impacts in EIR No. 330 and SEIR No. 346, the development of the Proposed Project has the potential to impact protected bird nests due to the removal of ornamental vegetation or indirectly harm birds though the generation of noise, lights, and other man-made disturbances that could result in the abandonment of eggs or young. Nesting habitat for birds and raptors is protected by California Department of Fish and Game (CDFG) Code Sections 3503, 3503.5, and 3513. The loss of an active nest would be considered a potentially significant impact. The implementation of MM 5.3-3 and MM 5.3-4 from Program EIR No. 330 would reduce any of these potential impacts by requiring pre-construction surveys for nesting birds and limiting tree removal to outside the nesting season, respectively. Through the implementation of these mitigation measures, the Proposed Project would not have any significant impacts related to candidate, sensitive, or special status species that either EIR has not already analyzed or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. b) Have a substantial adverse effect on any riparian habitat or other sensitive natural community identified in local or regional plans, policies, and regulations or by the California Department of Fish and Wildlife or United States Fish and Wildlife Service? The Project Site is entirely developed and surrounded by extensive urban development. The Project Site does not contain any naturally occurring vegetation communities that could be considered as sensitive such as riparian or coastal sage scrub habitats. Therefore, the Proposed Project would not have any significant impacts related to riparian habitat or other sensitive natural community that EIR No. 330 or SEIR No. 346 have not already analyzed or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 42 c) Have a substantial adverse effect on State or federally protected wetlands (including, but not limited to, marsh, vernal pool, coastal, etc.) through direct removal, filling, hydrological interruption, or other means? The Project Site is entirely developed and no wetlands or other hydrological features that meet criteria as waters of the United States or waters of the State are present on the Project Site. Additionally, the Project Site is not located adjacent to any known potentially jurisdictional water body. Therefore, the Proposed Project would not have any significant impacts related to wetlands that EIR No. 330 or SEIR No. 346 have not already analyzed or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. d) Interfere substantially with the movement of any native resident or migratory fish or wildlife species or with established native resident or migratory wildlife corridors, or impede the use of wildlife nursery sites? The Project Site is entirely developed and is surrounded on all sides by urban development, roadways and other man-made structures that serve as barriers to wildlife movement. Therefore, the Proposed Project would not have any significant impacts related to riparian habitat or other sensitive natural community that EIR No. 330 or SEIR No. 346 have not already analyzed or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. e) Conflict with any local policies or ordinances protecting biological resources, such as a tree preservation policy or ordinance? The Proposed Project may be subject to the street tree ordinance based upon the City of Anaheim Director of Community Services review. If applicable, a tree replacement plan would be required and submitted to the Director of Community Services for review and approval pursuant to Anaheim Municipal Code Section 13.12 as identified in PPP Bio-1. f) Conflict with the provisions of an adopted Habitat Conservation Plan, Natural Community Conservation Plan, or other approved local, regional, or State habitat conservation plan? The Project Site is entirely developed and surrounded by urban development. There is no applicable habitat conservation plan or natural community conservation plan affecting the Project Site. Therefore, the Proposed Project would not have any significant impacts related to conflicts with local policies or ordinances protecting biological resources that EIR No. 330 or SEIR No. 346 have not already analyzed or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. Existing Programs and Policies: PPP Bio-1: The Property Owner/Developer shall comply with all provisions of Anaheim Municipal Code Section 13.12 related to tree preservation. PPP Bio-2: The Property Owner/Developer shall comply with the provisions of the Migratory Bird Treaty Act, Federal Endangered Species Act, the California Endangered Species Act, and the Central/Coastal Subregion (NCCP/HCP) for protection of Federal or State listed species. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 43 Applicable MMP No. 122 Mitigation Measures: MM 5.3-3: If construction activity is timed to occur during the nesting season (typically between March 1 and July 1), developers will be required to provide focused surveys for nesting birds pursuant to California Department of Fish and Game requirements. Such surveys shall identify avoidance measures taken to protect active nests. MM 5.3-4: Removal of non-native trees shall be permitted only outside the nesting season. Sources: Appendix B – Results of a Cultural and Biological Resources Due Diligence Study for the 2420 East Lincoln Avenue Project, APNs 083-731-18 and -19, Orange County, California, Brian F. Smith and Associates, Inc., rev. November 18, 2022. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 7, CEQA Mandated Sections, Page 7-4 and Appendix A, Initial Study and NOP, Pages 29-30. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. Pages 2-4. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 44 5.4.5 Cultural Resources Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Cause a substantial adverse change in the significance of a historical resource pursuant to § 15064.5? Less than Significant After Mitigation ☐ ☒ b) Cause a substantial adverse change in the significance of an archaeological resource pursuant to §15064.5 of the CEQA Guidelines? Less than Significant After Mitigation ☐ ☒ c) Disturb any human remains, including those interred outside of formal cemeteries? Less than Significant After Mitigation ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 addressed the potential impacts to cultural resources associated with implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.4.4 concluded that the buildout of the General Plan would result in less than significant impact to cultural resources with the implementation of the General Plan Goals and Policies, existing codes and regulations, and MM 5.4-1, 5.4-2 and 5.4-3 required in MMP No. 122. Supplemental EIR No. 346 concluded that the buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No. 122A. The City of Anaheim has a number of identified historic structures and sites that are eligible for National Register of Historic Resources listing, particularly in the Anaheim Colony area, which may be vulnerable to development activities accompanying revitalization. The City, along with many of its citizens, has taken a key role in the preservation and enhancement of its historic resources. The General Plan and Zoning Code Update supports and expands upon those efforts. Policies within the General Plan Community Design Element establish specific measures that the City and its citizens will take to continue to enhance its historic buildings and districts. Archival research indicates a prehistoric resource area (CA-Ora-303) is located in the Hill and Canyon Area and a 1970 registry of artifacts comprised of manos, hammerstones, choppers, lithic flakes, and faunal bones was assigned to locations within north-facing rock shelters within this area. Subsequent field surveys failed to reveal additional artifacts. Implementation of the General Plan Goals and Policies, existing codes and regulations, and mitigation measures will reduce all cultural resource impacts to a level of insignificance. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 45 Impacts Associated with the Proposed Project: Would the project: a) Cause a substantial adverse change in the significance of a historical resource as pursuant to Section 15064.5? and b) Cause a substantial adverse change in the significance of an archaeological resource pursuant to Section 15064.5? and c) Disturb any human remains, including those interred outside of formal cemeteries? The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. MM 5.4-1 requires the Applicant document the presence/absence of historic resources for areas with documented or inferred resource presence. Based on the records search performed for preparation of Appendix B, the Project Site has been continually occupied since at least 1910. The property was used primarily as a citrus grove, with a single residence, until circa 1965. In 1975, the citrus grove was graded, a Ralph’s was constructed, and a parking lot was paved. The presence of the citrus grove since at least 1910 indicates that the Project Site has been highly disturbed. However, early twentieth century refuse associated with the Paulus family, and possibly subsequent farmers, could be located underneath the structures and parking lot. It is unlikely, however, that any historic refuse deposits would be intact, given the construction and demolition which occurred periodically from the 1970s through the 1980s. Additionally, as the residence was removed as early as 1965, and the Ralph’s was constructed in 1975, it is unlikely that there are any previously recorded cultural resources located within the Project Site. The Project Site is not located within a designated historic district and does not contain any known or documented cultural resources eligible for listing on the California Register of Historic Places or the National Register of Historic Places. As required by MM 5.4-2, the Applicant conducted Cultural and Paleontological Resources Records Searches (Appendix B). The consultant reviewed available historic USGS maps and aerial photographs for the Project Site, in addition to the Phase I Environmental Site Assessment (Appendix D) and available easement deeds. The records search for the Project Site was also requested from the South Central Coastal Information Center (SCCIC) at California State University, Fullerton on August 13, 2021 and results were received on October 5, 2021. The records search results indicate that no previously recorded sites or reports are recorded within or crossing the Project Site. As addressed above, with the implementation of mitigation, the Proposed Project would result in less than significant cultural resources impacts and would not introduce impacts that have not already been analyzed in EIR No. 330 and SEIR No. 346 or that are more significant than previously analyzed, or that the application of uniformly applicable development policies would not KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 46 substantially mitigate. Therefore, no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 Mitigation Measures: MM 5.4-1: City staff shall require property owners/developers to provide studies to document the presence/absence of historic resources for areas with documented or inferred resource presence. On properties where resources are identified, such studies shall provide a detailed mitigation plan, including a monitoring program and recovery and/or in situ preservation plan, based on the recommendations of a qualified specialist. The requirement for historic resources documentation set forth in this mitigation measure has been satisfied by the completion of the Cultural and Biological Due Diligence Study prepared for the proposed project (Appendix B). Consequently, no further action is required. MM 5.4-2: City staff shall require property owners/developers to provide studies to document the presence/absence of archaeological and/or paleontological resources for areas with documented or inferred resource presence. On properties where resources are identified, such studies shall provide a detailed mitigation plan, including a monitoring program and recovery and/or in situ preservation plan, based on the recommendations of a qualified specialist. The requirement for archaeological and paleontological resources documentation set forth in this mitigation measure has been satisfied by the completion of the Cultural and Biological Due Diligence Study prepared for the proposed project (Appendix B). Consequently, no further action is required. MM 5.4-3: All archaeological resources shall be subject to the provisions of CEQA (Public Resources Code) Section 21083.2. Sources: Appendix B – Results of a Cultural and Biological Resources Due Diligence Study for the 2420 East Lincoln Avenue Project, APNs 083-731-18 and -19, Orange County, California, Brian F. Smith and Associates, Inc., rev. November 18, 2022. Appendix D – Phase I Environmental Assessment, 2420-2450 East Lincoln Avenue, Anaheim, California 92806, Hillman Consulting, August 31, 2021. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.4, Cultural Resources, Pages 5-49 through 5-59. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-2 and Appendix A, Initial Study and NOP, Page 30. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. Pages 2-7 to 2-11. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 47 5.4.6 Energy Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Result in potentially significant environmental impact due to wasteful, inefficient, or unnecessary consumption of energy resources, during project construction or operation? Less Than Significant ☐ ☒ b) Conflict with or obstruct a State or local plan for renewable energy or energy efficiency? Less Than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330, prepared for the General Plan and Zoning Code Update Project did not explicitly evaluate energy impacts because this impact area was not included in the CEQA Guidelines Appendix G checklist until 2019, and the City did not have adopted energy policies at the time of preparation. Supplemental EIR No. 346, as prepared for the Housing Opportunity Sites Rezoning Project, discussed energy efficiency and energy policy in conjunction with analysis of greenhouse gas emissions (GHG), summarized in Section 5.4.8. SEIR No. 346 concluded that GHG impacts would be less than significant after mitigation. No potentially significant energy impacts were identified. Impacts Associated with the Proposed Project: The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. Compliance with California Building Standards Code Title 24 energy efficiency requirements (CALGreen), are considered demonstrable evidence of efficient use of energy. In addition to the findings required in Appendix G, Appendix F of the State CEQA Guidelines states that the means of achieving the goal of energy conservation includes the following: • Decreasing overall per capita energy consumption; • Decreasing reliance on fossil fuels such as coal, natural gas and oil; and • Increasing reliance on renewable energy sources. Appendix A analyzed potential construction phase and operational phase energy demands. Information from the CalEEMod 2022.1 Output contained within the same report and utilized for air quality and GHG analyses, was also utilized for this analysis. The CalEEMod outputs detail project-related construction equipment, transportation energy demands, and facility energy demands. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 48 Construction Energy Demands The construction schedule is anticipated to occur over 33 months, between the beginning of May 2023 and the beginning of February 2026. Staging of construction vehicles and equipment will occur on the approximately four-acre site. The total power cost of the on-site electricity usage during the construction of the Proposed Project is estimated to be approximately $10,309.33. Furthermore, Anaheim Public Utilities’ general service rate schedule (GS-1) is approximately $0.18 per kWh of electricity. As shown in Table 15 of the Air Quality, Global Climate Change, and Energy Impact Analysis report by Ganddini Group (Appendix A), the total electricity usage from project construction related activities is estimated to be approximately 58,509 kWh. Fuel consumed by construction equipment would be the primary energy resource expended over the course of P roject construction. Proposed Project construction activities would consume an estimated 87,111 gallons of diesel fuel. As stated previously, Project construction would represent a “single-event” diesel fuel demand and would not require on-going or permanent commitment of diesel fuel resources for this purpose. It is assumed that construction worker trips are from light duty autos, light duty truck 1, and light duty truck 2 at a mix of 25 percent/50 percent/25 percent, respectively, along area roadways. With respect to estimated vehicle miles traveled (VMT), the construction worker trips would generate an estimated 373,915 VMT. Data regarding project-related construction worker trips were based on CalEEMod 2022.1 model defaults. An estimated 14,698 gallons of fuel would be consumed for construction worker trips. With respect to estimated VMT, the vendor and hauling trips would generate an estimated 52,241 VMT. Data regarding project-related construction worker trips were based on CalEEMod 2022.1 model defaults. Construction equipment used over the approximately 33-month construction phase would conform to California Air Resources Board (CARB) regulations and California emissions standards and is evidence of related fuel efficiencies. There are no unusual project characteristics or construction processes that would require the use of equipment that would be more energy intensive than is used for comparable activities; or equipment that would not conform to current emissions standards (and related fuel efficiencies). Equipment employed in construction of the project would therefore not result in inefficient wasteful, or unnecessary consumption of fuel. Operational Energy Demands The Proposed Project is estimated to generate a total of 598 trips per day and the existing office uses to be removed by the Proposed Project generate 610 trips per day. Therefore, the Proposed Project would have a net decrease of 12 trips per day after the reduction from the removal of existing office uses. The vehicle fleet mix was used from the CalEEMod output. Table 20 of the Air Quality, Global Climate Change, and Energy Impact Analysis Report (Ganddini Group, Appendix A) shows that an estimated 72,258 gallons of fuel would be consumed per year for the operation of the Proposed Project. However, the existing offices uses to be removed by the Proposed Project consume approximately 86,339 gallons of fuel per year. Therefore, assuming KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 49 the reduction of existing uses, operation of Proposed Project would result in a net decrease of approximately 14,082 gallons of fuel consumption per year. Trip generation and VMT generated by the Proposed Project are consistent with other similar single-family townhome projects of similar scale and configuration as reflected respectively in the Institute of Transportation Engineers (ITE) Trip Generation Manual (11th Edition, 2021). That is, the Proposed Project does not propose uses or operations that would inherently result in excessive and wasteful vehicle trips and VMT, nor associated excess and wasteful vehicle energy consumption. Furthermore, the State of California consumed approximately 4.2 billion gallons of diesel and 15.1 billion gallons of gasoline in 2015.47,48 Therefore, the increase in fuel consumption from the Proposed Project is insignificant in comparison to the State’s demand. Therefore, project transportation energy consumption would not be considered inefficient, wasteful, or otherwise unnecessary. Building operation and site maintenance (including landscape maintenance) would result in the consumption of electricity (provided by Anaheim Public Utilities) and natural gas (provided by Southern California Gas Company). After the reduction from existing office use being removed as part of the project, the estimated electricity demand for the Proposed Project is a net decrease of approximately 405,795 kWh per year. In 2020, the residential sector of the Orange County consumed approximately 7,765 million kWh of electricity. In addition, after the reduction from existing office use being removed as part of the Proposed Project, the estimated natural gas consumption for the Proposed Project is approximately 1,755,487 kBTU per year. In 2020, the residential sector of the County consumed approximately 387 million therms of gas. Therefore, the increase in both electricity and natural gas demand from the Proposed Project is insignificant compared to the County’s 2020 residential sector demand. Energy use in buildings is divided into energy consumed by the built environment and energy consumed by uses that are independent of the construction of the building such as in plug-in appliances. In California, the California Building Standards Code Title 24 governs energy consumed by the built environment, mechanical systems, and some types of fixed lighting. Non- building energy use, or “plug-in” energy use can be further subdivided by specific end-use (refrigeration, cooking, appliances, etc.). The proposed project would be required to comply with Title 24 standards. Furthermore, the Proposed Project energy demands in total would be comparable to other residential projects of similar scale and configuration. Therefore, the Proposed Project facilities’ energy demands and energy consumption would not be considered inefficient, wasteful, or otherwise unnecessary. Renewable Energy and Energy Efficiency Plan Consistency Regarding federal transportation regulations, the Project Site is located in an already developed area. Access to/from the Project Site is from existing roads. These roads are already in place so the Project Site would not interfere with, nor otherwise obstruct any future intermodal transportation plans or projects in the project area. Regarding the State’s Energy Plan and compliance with Title 24 California Code of Regulations (CCR) energy efficiency standards, the Applicant is required to comply with the California Green KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 50 Building Standard Code requirements for energy efficient buildings and appliances as well as utility energy efficiency programs implemented by Anaheim Public Utilities and Southern California Gas Company. Regarding AB 1493 regulations, an individual project does not have the ability to comply or conflict with these regulations because they are intended for agencies and their adoption of procedures and protocols for reporting and certifying GHG emission reductions from mobile sources. However, the vehicles associated with the Proposed Project would be required to comply with federal and State fuel efficiency standards. Regarding the State’s Renewable Energy Portfolio Standards, the Proposed Project would be required to meet or exceed the energy standards established in the California Green Building Standards Code, Title 24, Part 11 (CALGreen). CALGreen Standards require that new buildings reduce water consumption, employ building commissioning to increase building system efficiencies, divert construction waste from landfills, and install low pollutant-emitting finish materials. The Proposed Project would provide for, and promote, energy efficiencies required under other applicable federal and State standards and regulations, and in so doing would meet or exceed all California Building Standards Code Title 24 standards. Energy consumed by the Proposed Project’s operation is calculated to be comparable to, or less than, energy consumed by other residential uses of similar scale and intensity that are constructed and operating in California. On this basis, the project would not result in the inefficient, wasteful, or unnecessary consumption of energy. Impacts are considered to be less than significant and no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 and No. 122A Mitigation Measures: None Sources: Appendix A – KB Home Lincoln & Sunkist Air Quality, Global Climate Change, and Energy Impact Analysis, Ganddini Group, Inc., November 21, 2022. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 5.2, Chapter 5.2, Greenhouse Gas Emissions, Pages 5.2-1 to 5.2-28. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 51 5.4.7 Geology and Soils Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Directly or indirectly cause potential substantial adverse effects, including the risk of loss, injury, or death involving: i. Rupture of a known earthquake fault, as delineated on the most recent Alquist-Priolo Earthquake Fault Zoning Map issued by the State Geologist for the area or based on other substantial evidence of a known fault? Refer to Division of Mines and Geology Special Publication 42. Less than Significant After Mitigation ☐ ☒ ii. Strong seismic ground shaking? Less than Significant After Mitigation ☐ ☒ iii. Seismic-related ground failure, including liquefaction? Less than Significant After Mitigation ☐ ☒ iv. Landslides? Less than Significant After Mitigation ☐ ☒ b) Result in substantial soil erosion or the loss of topsoil? Less than Significant ☐ ☒ c) Be located on a geologic unit or soil that is unstable, or that would become unstable as a result of the project, and potentially result in on- or off- site landslide, lateral spreading, subsidence, liquefaction or collapse? Less than Significant ☐ ☒ KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 52 Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity d) Be located on expansive soil, as defined in Table 18-1-B of the Uniform Building Code (1994), creating substantial direct or indirect risks to life or property? Less than Significant ☐ ☒ e) Have soils incapable of adequately supporting the use of septic tanks or alternative waste water disposal systems where sewers are not available for the disposal of waste water? Less than Significant ☐ ☒ f) Directly or indirectly destroy a unique paleontological resource or site or unique geologic feature? Less Than Significant After Mitigation ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the geotechnical and soils impacts related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.5.4 concluded that buildout of the General Plan would result in less than significant impacts related to geology and soils upon implementation of General Plan goals and policies, existing codes and regulations, and MM 5.5-1 in MMP No. 122. No areas of the City are identified on an Alquist-Priolo Earthquake Fault Zoning Map. However, build-out of the General Plan has the potential to expose future residents to the effects of geological hazards including ground shaking, seismically induced surface rupture, liquefaction, and slope instability leading to mudslides and landslides. EIR No. 330 concluded that potential impacts related to seismic ground shaking would be reduced to less than significant levels with compliance with the General Plan Goals and Policies; the applicable requirements listed in the Anaheim Municipal Code; and with conformance to the California Building Code. As noted in EIR No. 330, although the majority of the City and its Sphere-of-Influence has flat topography and minimal potential for erosion impacts and landslides. Although the Hill and Canyon Area exhibits hilly terrain that is more susceptible to soil erosion and landslides, this area of the City is not proximate to the Project Site. Development would be subject to local and State codes and requirements for erosion control and grading. In addition, project sites encompassing an area of one or more acres would require compliance with a National Pollutant Discharge Elimination System (NPDES) permit and consequently the development and implementation of a Storm Water Pollution Prevention Plan (SWPPP). With adherence to these codes and regulations and implementation of the General Plan Goals and Policies, Title 17 – Land Development and KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 53 Resources, and the most recent version of the Uniform Building Code, impacts would be reduced to below a level of significance. With the exception of the Hill and Canyon Area, soils observed and encountered throughout the remainder of the City range from “Low” to “High” in expansion potential (Expansivity Potential of Soils and Rock Units in Orange County, California, 1976). Proposed structures should be designed for the appropriate expansion potential and impacts would be less than significant. Impacts to paleontological features was previously discussed in the Cultural Resources section of EIR No. 330 and SEIR No. 346. One geologic formation – the Topanga Formation – has a high potential for yielding paleontological material and grading there, as well as in other formations, would be closely monitored. Buildout of the General Plan would result in less than significant impacts related to paleontological resources with the implementation of MM 5.4-2 in MMP No. 122. Supplemental EIR No. 346 concluded the buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330. No new mitigation measures were required in MMP No. 122. Impacts Associated with the Proposed Project: The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. Geologically, the surficial sediments across the Proposed Project are mapped as Holocene and late Pleistocene young alluvial fan deposits, consisting of unconsolidated silty, sandy alluvium (Morton and Miller 2006). Holocene deposits are estimated to be approximately 130 feet thick in the area of the Proposed Project (Sprotte et al., 1980). During the Holocene, activity of the Santa Ana River points to widespread sheet flooding and wandering, as indicated by extensive and continuous “younger” sand and silt deposits (Greenwood and Pridmore 2001). As required by MM 5.5-1, the Applicant prepared a Geotechnical due diligence study (Appendix C). The study confirmed that the Project Site is underlain by alluvial deposits which predominately consist of fine to medium grained sand with trace fines in the upper 50 feet. Groundwater was not encountered during exploration at depths of 50 feet below existing grade. The Project Site is not located within a fault-rupture hazard zone as defined by the Alquist-Priolo Special Studies Zones Act (CGS, 2018). Also, based on mapping by the State, there are no active faults mapped at the site. The closest major Quaternary-age faults include the Peralta Hills Fault located 1.4 miles to the east and the Yorba Linda Fault located 1.7 miles north of the site. The closest active faults are the Puente Hills Blind Thrust and the Whittier Faults located 5 and 7 miles north of the site, respectively. These faults along with numerous other regionally active faults are capable of producing strong ground shaking at the Project Site. The Project Site is not located within a mapped potential liquefaction hazard zone per the California Division of Mines and Geology Seismic Hazard Maps for the Anaheim Quadrangle (California Division of Mines and Geology, 1998). Based on the site-specific geotechnical exploration and considering the absence of groundwater in the upper 50 feet, the potential for liquefaction at the Project Site is considered very low. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 54 Tsunami and seiche are not considered hazards at the Project Site due to the flat elevation and the distance of the site from the ocean. No confined bodies of water are located immediately adjacent to the site. The anticipated settlements depend upon the loads from the building, the type of building foundation and the geotechnical properties of the supporting subgrade. Per the laboratory test results and the blow counts within the subsurface soils, the seismically induced settlement as a result of strong ground shaking is anticipated to be minor and less than ½-inch. The loss or gain of volume (shrinkage or bulking, respectively) of excavated materials compacted as fill varies according to earth material/type and location. This volume change is represented as a percentage of shrinkage (for volume loss) or bulking (for volume gain) after recompaction of a unit volume. The near-surface undocumented fill and native alluvium on the Project Site are anticipated to have approximately 5 to 15 percent shrinkage. Subsidence is anticipated to be on the order of 0.1 foot across the site. The Proposed Project will connect to existing City water, sewer, and stormwater systems. The use of a septic or alternative wastewater system is not proposed. Appendix C provides recommendations for site preparation activities based on the results of field observations and exploratory borings. Among the recommendations are over-excavation and compaction of existing soils below footings; on-site soils were found to be suitable for reuse as engineered fill. The Project Site’s soils were found to have very low expansion potential and low sulfate content and were determined to be mildly corrosive to buried ferrous metals. As required by MM 5.4-1, the Project Site was also evaluated for paleontological resources in Appendix B. The paleontological sensitivity of the Holocene alluvial sediments in the drainage valleys is low, based upon the general lack of fossils preserved in these types of deposits, and their young geologic age. Within the coastal plains of Orange County, young alluvial fan sediments rarely produce terrestrial vertebrate fossils. Young alluvial fan sedimentary deposits, such as those at the project, are typically assigned a low paleontological sensitivity. As addressed above, the Proposed Project would result in less than significant geological and paleontological impacts with the implementation of standard City requirements and mitigation measures and would not introduce impacts that have not already been analyzed in EIR No. 330 and SEIR No. 346 or that are more significant than previously analyzed, or that the application of uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. Existing Programs and Policies: PPP Geo-1: All grading operations will be conducted in conformance with the Anaheim Municipal Code, Title 17 – Land Development and Resources. PPP Geo-2: The Property Owner/Developer shall submit for approval to the State Water Resources Control Board, a Notice of Intent to be covered under the Storm Water Permit, in compliance with the National Pollutant Discharge Elimination System (NPDES) program. In addition, future projects shall be required to develop and implement a Storm Water Pollution Prevention Plan (SWPPP), which incorporates Best Management Practices (BMPs). KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 55 Applicable MMP No. 122 Mitigation Measures: MM 5.4-2: City staff shall require property owners/developers to provide studies to document the presence/absence of archaeological and/or paleontological resources for areas with documented or inferred resource presence. On properties where resources are identified, such studies shall provide a detailed mitigation plan, including a monitoring program and recovery and/or in situ preservation plan, based on the recommendations of a qualified specialist. The requirement for archaeological and paleontological resources documentations set forth in this mitigation measure has been satisfied by the completion of the Cultural and Biological Due Diligence Study prepared for the proposed project (Appendix B). Consequently, no further action is required. MM 5.5-1: The City shall require geologic and geotechnical investigations in areas of potential seismic or geologic hazards as part of the environmental or development review process. All grading operations will be conducted in conformance with the recommendations contained in the applicable geotechnical investigation. The requirement for a geotechnical investigation set forth in this mitigation measure has been satisfied by the completion of the Geotechnical Exploration and Due Diligence Study (Appendix C). Proof of intent to comply with these operations, such as applicable notes on plans, shall be provided by the property owner/developer prior to issuance of grading permits. Sources: Appendix B – Results of a Cultural and Biological Resources Due Diligence Study for the 2420 East Lincoln Avenue Project, APNs 083-731-18 and -19, Orange County, California, Brian F. Smith and Associates, Inc., rev. November 18, 2022. Appendix C – Geotechnical Exploration and Due Diligence Study, Proposed Residential Development at 2420 and 2450 East Lincoln Avenue, City of Anaheim, California, NMG Geotechnical, Inc., September 3, 2021. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.5, Geology and Soils, Pages 5-57 to 5-84. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-5 and Appendix A, Initial Study and NOP, Page 31. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 56 5.4.8 Greenhouse Gas Emissions Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity • Generate greenhouse gas emissions, either directly or indirectly, that may have a significant impact on the environment? Potentially New or Increased Significant Effect ☐ ☒ • Conflict with an applicable plan, policy or regulation adopted for the purpose of reducing the emissions of greenhouse gases? Potentially New or Increased Significant Effect ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330, prepared for the General Plan and Zoning Code Update Project, did not evaluate greenhouse gas (GHG) emissions impacts because this impact area was not included in the CEQA Guidelines Appendix G checklist and the City did not have adopted GHG thresholds at the time of preparation. In 2013, the Anaheim City Council certified Supplemental EIR No. 346 as a supplemental EIR to EIR No. 330. S EIR No. 346 was prepared to serve as environmental documentation for the Housing Opportunities Sites Rezoning Project. In accordance with the amendments to the CEQA Guidelines, inventories were compiled to forecast GHG emissions generated by the General Plan and Zoning Code Update Project (analyzed by EIR No. 330), as well as the Housing Opportunities Sites Rezoning Project (analyzed by Supplemental EIR No. 346). As identified in Section 5.2 of Supplemental EIR No. 346, the GHG emissions associated with build-out of the General Plan as described by the General Plan and Zoning Code Update Project and the Housing Opportunities Sites Rezoning Project would exceed the SCAQMD’s GHG efficiency threshold. Mitigation measures from EIR No. 330 along with new mitigation measures prepared for Supplemental EIR No. 346 were proposed to reduce these impacts to the extent feasible; however, even with mitigation the impacts would remain significant and unavoidable. The Anaheim City Council adopted a Statement of Overriding Considerations with regard to this potential impact. Impacts Associated with the Proposed Project: The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. The Applicant prepared a Greenhouse Gas analysis (Appendix A). KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 57 Would the project: a) Generate greenhouse gas emissions, either directly or indirectly, that may have a significant impact on the environment? Ganddini Group analyzed the net increase of GHG emissions, which results in 1,189.14 metric tons per year, which is below the interim screening threshold of 3,000 metric tons per year recommended by SCAQMD for non-industrial projects and a net decrease of 27.14 metric tons per year from the existing office use. As illustrated in Table 5, the Proposed Project would not exceed the SCAQMD’s significance thresholds for GHG emissions for residential developments. As previously noted, SEIR No. 346 determined that the buildout of the Housing Opportunity Sites would result in significant and unavoidable impacts related to GHG emissions. As illustrated above, the Proposed Project would not result in a significant impact when related to the applicable SCAQMD significance threshold. As such, the Proposed Project would not introduce impacts that the Certified EIRs have not already analyzed or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. b) Conflict with any applicable plan, policy or regulation adopted for the purpose of reducing the emissions of greenhouse gases? Supplemental EIR No. 346 compared emissions to the CARB Table 5 - Project-Related Greenhouse Gas Emissions Category Greenhouse Gas Emissions (Metric Tons/Year) Bio-CO2 NonBio- CO2 CO2 CH4 N2O CO2e Maximum Annual Operations 2.95 1,127.00 1,130.00 0.37 0.03 1,151.00 Construction1 0.00 37.7.81 37.81 0.00 0.00 38.14 Subtotal Emissions 2.95 1,164.81 1,167.81 0.37 0.03 1,189.14 Reduction from existing office uses to be removed -7.84 -1,120.00 -1,128.00 -0.87 -0.04 -1,162.00 Total Emissions -4.89 44.81 39.81 -0.50 -0.01 27.14 SCAQMD Draft Screening Threshold 3,000 Exceeds Threshold? No Notes: Source: CalEEMod Version 2022.1 for Opening Year 2026. (1) Construction GHG emissions CO2e based on a 30-year amortization rate. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 58 Climate Change 2008 Scoping Plan as the most current plan at the time of publishing in 2013. CARB updated the Scoping Plan in 2017. As demonstrated in the consistency analysis provided in the Air Quality, Global Climate Change, and Energy Impact Analysis prepared by Ganddini Group, the proposed project would comply with all applicable portions of the 2017 Scoping Plan Update. Table 12 of the Air Quality, Global Climate Change, and Energy Impact Analysis (Appendix A) provides further details on the proposed project’s compliance with the 2017 Scoping Plan. SEIR No. 346 determined that buildout of the Housing Opportunity Sites would not conflict with any applicable plan, policy, or regulation adopted for the purpose of reducing GHG emissions. As illustrated above, the Proposed P roject would not result in a conflict with the 2017 Scoping Plan, the applicable GHG emission reduction plan. As such, the Proposed Project would not introduce impacts that SEIR No. 346 has not already analyzed or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate; therefore, no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 Mitigation Measures: See MMs 5.2-1 and 5.2-6 in Section III, Air Quality. Sources: Appendix A – KB Home Lincoln & Sunkist Air Quality, Global Climate Change, and Energy Impact Analysis, Ganddini Group, Inc., November 21, 2022. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 5.2, Chapter 5.2, Greenhouse Gas Emissions, Pages 5.2-1 to 5.2-28. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 59 5.4.9 Hazards and Hazardous Materials Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Create a significant hazard to the public or the environment through the routine transport, use, or disposal of hazardous materials? Less than Significant After Mitigation ☐ ☒ b) Create a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions involving the release of hazardous materials into the environment? Less than Significant After Mitigation ☐ ☒ c) Emit hazardous emissions or handle hazardous or acutely hazardous materials, substances, or waste within one-quarter mile of an existing or proposed school? Less than Significant ☐ ☒ d) Be located on a site which is included on a list of hazardous materials sites compiled pursuant to Government Code Section 65962.5 and, as a result, would it create a significant hazard to the public or the environment? Less than Significant After Mitigation ☐ ☒ e) For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project result in a safety hazard or excessive noise for people residing or working in the project area? Less than Significant After Mitigation ☐ ☒ KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 60 Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity f) Impair implementation of or physically interfere with an adopted emergency response plan or emergency evacuation plan? Less than Significant ☐ ☒ g) Expose people or structures, either directly or indirectly, to a significant risk of loss, injury or death involving wildland fires? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the hazards and hazardous materials impacts related to the implementation of the General Plan and Zoning Code Update Program. Overall, the General Plan and Zoning Code Update decreases the area of land designated for heavy industrial uses and therefore reduces the future number of potential emitters or handlers of hazardous materials, substances, or waste throughout the City. EIR No. 330, Section 5.6.4 concluded that buildout of the General Plan would result in less than significant impacts with mitigation related to hazards and hazardous materials upon implementation of General Plan goals and policies, existing codes and regulations, and MMs 5.6-1 through 5.6-3 in MMP No. 122. SEIR No. 346 concluded that buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No. 122A. Impacts Associated with the Proposed Project: The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. Would the project: a) Create a significant hazard to the public or the environment through the routine transport, use, or disposal of hazardous materials? and b) Create a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions involving the release of hazardous materials into the environment? A Phase I Environmental Site Assessment (ESA) was prepared (Appendix D). The Phase I ESA did not identify any Recognized Environmental Conditions (RECs), Historical Recognized Environmental Conditions (HRECs),or Controlled Recognized Environmental Conditions (CRECs) associated with the Project Site in accordance with the ASTM Standard Practice E1527-13. A KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 61 separate hazardous materials inspection (Appendix D-1) was performed to identify potential hazardous materials on site that would be disturbed as part of the demolition of the existing commercial office buildings. Materials identified include asbestos-containing materials (ACM), lead containing paint, fluorescent light tubes, and electronics such as computers, which require handling or disposal practices outside of conventional solid waste. Only individuals and/or contractors who have undergone all required training, licensing, and certifications in accordance with all applicable federal, State, and local rules and regulations should be utilized for handling and/or removal of the identified materials as addressed in PPP Haz-1. During construction, limited quantities of hazardous substances, including oils, gasoline, diesel fuels, automotive chemicals, and other substances would be used on the project site. However, the use of these materials would be limited to the construction period. The handling, transport, and disposal of such substances must comply with all local, State, and federal laws and regulations (PPP Haz-1). Any hazardous materials utilized during the construction of the residences and other site improvements would be managed in accordance with State and local regulations, as implemented through grading and building permit requirements. This includes preparation of a Stormwater Pollution Prevention Plan (SWPPP) to avoid pollution of surface water during storm events. During the operational phase of the residential development, no significant quantities of hazardous materials would be used, and no hazardous emissions would be generated by the Proposed Project. Therefore, impacts associated with the transport, use, and disposal of hazardous materials would be less than significant and no further environmental analysis is required. c) Emit hazardous emissions or handle hazardous or acutely hazardous materials, substances, or waste within one-quarter mile of an existing or proposed school? The nearest school to the project site is Sunkist Elementary School, located at 500 N. Sunkist Street, Anaheim, approximately 0.6 mile north of the Project Site. The use of hazardous materials would be limited to the construction period, and the handling, transport, and disposal of such substances must comply with all local, State, and federal laws and regulations. Therefore, impacts would be less than significant and no further environmental analysis is required. d) Be located on a site which is included on a list of hazardous materials sites compiled pursuant to Government Code Section 65962.5 and, as a result, would it create a significant hazard to the public or the environment? The Project Site is not included on any list compiled pursuant to Section 65962.5 of the Government Code. e) For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project result in a safety hazard or excessive noise for people residing or working in the project area? The Proposed Project is not in the vicinity of any airport or airstrip. The nearest airport is Fullerton Municipal Airport, located approximately 5.5 miles from the Project Site. The Project Site is not located within an air influence or hazard planning area associated with Fullerton Municipal Airport, and there are no foreseeable hazards for people residing at the Project Site related to KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 62 airport safety hazards or noise. Therefore, impacts would be less than significant and no further environmental analysis is required. f) Impair implementation of or physically interfere with an adopted emergency response plan or emergency evacuation plan? The Proposed Project is subject to building code and fire code requirements, including the requirement for fire sprinklers, and access roads are subject to Anaheim Fire and Rescue Department design review for emergency response and evacuation needs. Therefore, the Proposed Project would not impair or interfere with emergency response or evacuation. Therefore, impacts would be less than significant and no further environmental analysis is required. g) Expose people or structures, either directly or indirectly, to a significant risk of loss, injury or death involving wildland fires? The proposed project is located in an urbanized area in the central portion of Anaheim and is not adjacent to or near the Hill or Canyon areas or other wildland areas that are susceptible to wildfires. The project site is not located in a Very High Fire Hazard Severity Zone as determined by Program EIR No. 330. Furthermore, the proposed project is subject to building code and fire code requirements, including the requirement for fire sprinklers, and the project would be subject to Anaheim Fire and Rescue Department design review. The proposed project would not have any significant impacts related to wildland fires that EIR No. 330 and SEIR 346 have not already analyzed, nor would the proposed project have any impacts that are more significant than previously analyzed, or that the application of uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. Existing Programs and Policies: PPP Haz-1: The Proposed Project shall comply with all relevant local, State, and federal regulations related to hazardous materials. PPP Haz-2: Prior to structural demolition/renovation activities, a Certified Environmental Professional shall confirm the presence or absence of asbestos containing materials (ACMs). Should ACMs be present, demolition materials containing ACMs shall be removed and disposed of at an appropriate permitted facility. Asbestos removal shall be performed by a State certified asbestos containment contractor in accordance with the South Coast Air Quality Management District (SCAQMD) Rule 1403. Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Appendix D – Phase I Environmental Assessment, 2420-2450 East Lincoln Avenue, Anaheim, California 92806, Hillman Consulting, August 31, 2021. Appendix D-1 – Hazardous Materials Inspection, 2420-2450 East Lincoln Avenue, Anaheim, California 92806, Hillman Consulting, September 1, 2021. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 63 City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Pages 7-5 to 7-6 and Appendix A, Initial Study and NOP, Pages 32-33. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 64 5.4.10 Hydrology and Water Quality Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Violate any water quality standards or waste discharge requirements or otherwise substantially degrade surface or ground water quality? Less than Significant ☐ ☒ b) Substantially decrease groundwater supplies or interfere substantially with groundwater recharge such the project may impede sustainable groundwater management of the basin? Less than Significant ☐ ☒ c) Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of a stream or river or through the addition of impervious surfaces, in a manner which would: i. result in substantial erosion or siltation on- or off-site; Less than Significant ☐ ☒ ii. substantially increase the rate or amount of surface runoff in a manner which would result in flooding on- or offsite; Less than Significant ☐ ☒ iii. create or contribute runoff water which would exceed the capacity of existing or planned stormwater drainage systems or provide substantial additional sources of polluted runoff; or Less than Significant ☐ ☒ iv. impede or redirect flood flows? Less than Significant ☐ ☒ d) In flood hazard, tsunami, or seiche zones, risk release of pollutants due to project inundation? Less than Significant ☐ ☒ KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 65 Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity e) Conflict with or obstruct implementation of a water quality control plan or sustainable groundwater management plan? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the hydrology and water quality impacts related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.7.4 concluded that with implementation of General Plan goals and policies, existing codes and regulations, and MMs 5.7-1 through 5.7-3 in MMP No. 122, buildout of the General Plan would result in less than significant impacts related to hydrology and water quality. Supplemental EIR No. 346 concluded that the buildout of the Housing Opportunity Site would not result in new or greater significant impacts than those identified in Program EIR No. 330. No new mitigation measures were required in MMP No. 122A. According to EIR No. 330, implementation of the General Plan and Zoning Code Update would potentially impact the quantity of runoff and other pollutant loadings to receiving waters. Impacts may be significantly greater during the region’s rainy season, which was generally defined as October through May. Policies included in the General Plan and Zoning Code Update would ensure compliance with federal standards by ensuring adequate storm drainage and maintaining adequate water and waste distribution capacity. The City receives up to three-fourths of its drinking water from local groundwater; therefore, it is critical to protect the Orange County Groundwater Basin. This groundwater basin underlies the northern half of Orange County, covering approximately 310 square miles, and has a recharge area which extends north and east of the SR-57/SR-91 interchange to the SR-91 and Imperial Highway interchange. The recharge area represents two-thirds of the total groundwater recharge in Orange County. Implementation of the General Plan and Zoning Code Update would not potentially increase the demand on groundwater supplies. To protect the City’s groundwater and the Orange County Groundwater Basin, the General Plan and Zoning Code Update contains policies directing the City to reduce pollution, enforce water quality management regulations, and conserve water. Increased development throughout Anaheim and its Sphere-of -influence, especially on currently undeveloped properties, will increase the number of impervious surfaces, thereby increasing the amount and speed of runoff. Increased runoff volumes and speeds may create nuisance flooding in areas without adequate drainage facilities. Mitigation measures related to the maintenance of flood control facilities and minimizing stormwater and urban runoff will avoid or substantially lessen potentially significant impacts to a less-than-significant level. Pollution associated with storm water and urban runoff affects the groundwater of Anaheim, as well as neighboring jurisdictions, throughout the region. The problem is particularly acute at the KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 66 beginning of a heavy rainstorm but can be a problem at any time due to the improper disposal of products associated with home, garden, and automotive maintenance. However, the General Plan incorporates various goals and policies which would limit potential impacts relating to water quality. The General Plan and Zoning Code Update seeks to protect water quality by requiring residents and businesses to engage in water quality management practices and pollution control measures. The General Plan Goals and Policies also direct the City to monitor water quality and provide water service that meets or exceeds health standards. Build-out in accordance with the General Plan could potentially expose more people and habitable structures to potential flooding and flood hazards. Increased exposure could occur through development of lands within flood zones. The policies contained in the General Plan seek to protect structures and residents within flood zones by requiring all development proposals to undergo an evaluation process to determine flood risks and ensure compliance with local State and Federal regulations. There is a low-to-moderate potential for flooding due to seiche hazards affecting properties adjacent to the Walnut Canyon Reservoir, an enclosed body of water in the Anaheim Hills. The Project Site is not proximate to this area. The City of Anaheim is not located close enough to the coast to be subject to possible impacts from a tsunami. Impacts Associated with the Proposed Project: Would the project: a) Violate any water quality standards or waste discharge requirements or otherwise substantially degrade surface or groundwater quality? The Proposed Project would be subject to standard regulatory requirements that would minimize impacts related to hydrology and water quality, including preparation of a Stormwater Pollution Prevention Plan (SWPPP) for construction, and a Water Quality Management Plan (WQMP) for operations, each of which would contain best management practices (BMPs). MM 5.7-2 requires that the Applicant conduct a drainage study to identify potential deficiencies in an existing storm drain facility or discharges into an existing deficient facility. The Applicant has prepared a Drainage Study (Appendix F), which found that the Proposed Project can be constructed and meet all requirements of the County of Orange to manage flooding for a 25-year storm event and that all impacts would remain less than significant. MM 5.7-3 requires that the Applicant prepare a WQMP to conform with the City’s NPDES requirements. The Applicant has prepared a Preliminary Water Quality Management Plan (PWQMP) (Appendix E). The Project Site is developed with approximately 86 percent impervious surfaces and 14 percent pervious surfaces. Build-out of the Proposed Project, as shown in Figure 3, Conceptual Site Plan, would result in approximately 82 percent impervious surfaces and 18 percent pervious landscaped areas, which would enhance on-site infiltration of storm water and reduce off-site storm flows from the current condition. The proposed site condition will have similar drainage patterns to the exiting condition except for a portion of runoff conveyed into a proposed BMP feature and infiltrated into the substrata. For the majority of the Project Site, runoff generated would be directed into ribbon gutters and KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 67 curb and gutters and conveyed into a number of storm drain inlets. A storm drain network is proposed to convey the runoff from the inlets into a subsurface StormTech infiltration system (BMP 1). The storm drain network is design such that flows in excess of the StormTech BMP capacity would be conveyed directly to the existing curb inlet located adjacent to the Project Site along Lincoln Avenue. Runoff from approximately the front half of the structures along Lincoln Avenue and Sunkist Avenue (i.e., the half of the structure facing Lincoln Avenue or Sunkist Street) would be collected in a storm drain network and conveyed into either a subsurface StormTech chamber system (BMP 2) or bioretention basins (BMPs 3 and 4). Runoff in excess of the capacities of BMPs 2, 3, and 4 would be conveyed to the existing curb inlet adjacent to the Project Site along Lincoln Avenue. The above-mentioned BMP system is designed to capture and infiltrate the 85th percentile rainfall on the project. As addressed above, the Proposed Project would result in less than significant water quality impacts with the implementation of standard City requirements and mitigation measures and would not introduce impacts that have not already been analyzed in EIR No. 330 and SEIR No. 346 or that are more significant than previously analyzed, or that the application of uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. b) Substantially decrease groundwater supplies or interfere substantially with groundwater recharge such that the project may impede sustainable groundwater management of the basin? The Project Site is developed and does not represent a substantial groundwater recharging area. Anaheim Public Utilities would provide water supply to the Project Site through the City’s municipal water distribution system. Although groundwater would be used for water supply, the Proposed Project would not require on-site extraction of groundwater during operation. The Proposed Project would comply with the policies and goals of the General Plan and the development standards of the Zoning Code, except as requested for modification by the Proposed Project, which would ensure that the Proposed P roject would not increase demand on groundwater supplies beyond those analyzed in the Certified EIRs. Therefore, the Proposed Project would not have any significant impacts related to groundwater recharge or groundwater supplies that the Certified EIRs have not already analyzed, nor would the Proposed Project result in more significant or more severe impacts that uniformly applicable development policies could not substantially mitigate. No further environmental analysis is required. c) Substantially alter the existing drainage pattern of area, including through the alteration of the course of a stream or river or through the addition of impervious surfaces, in a manner which would: (i) result in substantial erosion or siltation on- or off-site; The Project Site is not near any natural waterway and would not cause erosion or siltation due to a change in the course of a stream. According to the Drainage Study prepared for the Proposed Project (Appendix F), the site currently contains approximately 86 percent impervious surfaces and 14 percent pervious surfaces. Buildout of the Proposed Project would provide approximately 82 percent impervious surfaces and 18 percent pervious surfaces. The Proposed Project would not have any significant impacts related impacts related to erosion or siltation that the Certified EIRs have not already analyzed, nor would the Proposed Project result in more significant or more KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 68 severe impacts that could not be substantially mitigated by the application of uniformly applicable development policies. Therefore, no further environmental analysis is required. (ii) substantially increase the rate or amount of surface runoff in a manner which would result in flooding on- or off-site; and (iii) create or contribute runoff water which would exceed the capacity of existing or planned stormwater drainage systems or provide substantial additional sources of polluted runoff; and (iv) impede or redirect flood flows? According to the Drainage Study prepared for the Proposed Project (Appendix F), the existing site hydrologic condition was analyzed to determine the peak flow rates associated with 10-, 25- and 100-year storm events. The 25-year storm event results indicate the Proposed Project will result in a slight increase in peak flow rate (13.5 cfs compared to 11.8 cfs) in the post-project condition in comparison to the existing condition. Therefore, as a part of the Proposed Project, on-site detention consisting of a system of 24 StormTech SC-310 units with a total storage of 1,120 cubic feet would be provided to preclude 25-year storm event peak flow impacts. The Proposed Project would not have any significant impacts related to runoff or flood flows that EIR No. 330 has not already analyzed, nor would the P roposed Project result in more significant or more severe impacts than previously analyzed, or that the application of uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. d) In flood hazard, tsunami, or seiche zones, risk release of pollutants due to project inundation? The Project Site is also not within a 100-year flood hazard area or area affected by seiche, tsunami, or mudflow due to the elevation and the distance of the site from the ocean. No confined bodies of water are located immediately adjacent to the site. The Proposed Project would not have any significant impacts related to flood hazards, tsunami, or seiches that the Certified EIRs have not already analyzed has not already analyzed, nor would the Proposed Project result in more significant or more severe impacts that uniformly applicable development policies could not substantially mitigate. Therefore, no further environmental analysis is required. e) Conflict with or obstruct implementation of a water quality control plan or sustainable groundwater management plan? The Proposed Project would not conflict with or obstruct implementation of a water quality control plan or sustainable groundwater management plan. The Proposed Project would comply with the applicable General Plan Goals and Policies and mitigation measures. The Proposed Project would not have any significant impacts related to a water quality control plan or sustainable groundwater management plan that the Certified EIRs have not already analyzed, nor would the Proposed Project result in more significant or more severe impacts that uniformly KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 69 applicable development policies could not substantially mitigate. Therefore, no further environmental analysis is required. Existing Programs and Policies: PPP HYD-1: The Property Owner/Developer shall comply with all applicable local, State, and federal regulations relating hydrology and water quality. Applicable MM No. 122 Mitigation Measures: MM 5.7-2: Prior to issuance of the grading permit, the City shall require that new developments conduct a drainage study and mitigate its drainage impacts if the development creates a deficiency in an existing storm drain facility or discharges to an existing deficient facility. The requirement for a drainage study set forth in this mitigation measure has been satisfied by the completion of the project-specific drainage study (Appendix F). MM 5.7-3: Prior to issuance of the grading permit, the City shall require that new developments and/or significant redevelopments prepare a Final Water Quality Management Plan to be reviewed and approved by the City Engineer and conform to the City’s National Pollutant Discharge Elimination System (NPDES) related requirements to the satisfaction of the City Engineer. The requirement for a Water Quality Management Plan set forth in this mitigation measure has been conditionally satisfied by the completion of the project-specific Preliminary WQMP (Appendix E). Sources: Appendix E – Santa Ana Region Priority Project Water Quality Management Plan (WQMP), 2420 East Lincon Avenue, October 4, 2022. Appendix F – Drainage Study for 2420 East Lincoln Avenue Project, Rick Engineering Company, October 3, 2022. Appendix G – Sewer Study – 2420-2450 E. Lincon Avenue, PSOMAS, July 20, 2022. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.7, Hydrology and Water Quality, Pages 5-105 to 5-131. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-2 and Appendix A, Initial Study and NOP, Pages 33-35. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 70 5.4.11 Land Use and Planning Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Physically divide an established community? Less than Significant ☐ ☒ b) Cause a significant environmental impact due to a conflict with any land use plan, policy, or regulation adopted for the purpose of avoiding or mitigating an environmental effect? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the land use impacts related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.8.4 concluded that buildout of the General Plan would result in less than significant impacts related to land use and planning upon implementation of General Plan goals and policies and existing codes and regulations. No mitigation measure were required in MMP No. 122. SEIR 346 concluded that buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No. 122A.The General Plan Land Use Plan (Figure LU-4 of the General Plan Land Use Element), along with the General Plan Goals and Policies, strive to preserve, revitalize, and ensure land use compatibility throughout the City. The General Plan identifies areas for smaller lot, multi-family, and mixed- use development by strategically locating these uses and limiting designations within and adjacent to single-family neighborhoods, as well as providing additional guidance under the Community Design Element to ensure quality development and integration with surrounding areas. The Land Use Plan provides the basis for the General Plan and Zoning Code Update and represents a guide for the City future development. The land use patterns and areas identified are intended to provide the basis for more detailed land use designations, densities and development standards established in the Zoning Code. The Land Use Plan provides enough dwelling unit, population, and employment capacity to exceed the OCP-2000 census-based projections for the year 2025. In addition, the General Plan complies with the provisions of the NCCP/HCP for the Central/Coastal Sub-region. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 71 Impacts Associated with the Proposed Project: Would the project: a) Physically divide an established community? and b) Cause a significant environmental impact due to a conflict with any land use plan, policy, or regulation adopted for the purpose of avoiding or mitigating an environmental effect? The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. The Project Site is developed with a commercial use and redevelopment would not divide an established community. The Project Site was reclassified to the Residential Opportunity (RO) Overlay Zone in the Rezoning Project, which as analyzed in SEIR No. 346. The Rezoning Project was a part of the City’s effort to facilitate development on properties identified as Opportunity Sites in the Housing Element. The Proposed Project’s land use is consistent with the Project Site’s existing Medium Density Residential General Plan designations and implements the RO Overlay Zone. The Proposed Project would also implement the City’s vision for this Opportunity Site by adding more housing to the southeast area of the City. There is no applicable habitat conservation plan or natural community conservation plan affecting the Project Site. The Proposed Project does not have any significant effects on the environment that either have not already been analyzed in the Certified EIRs or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate, therefore, no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.8, Land Use and Relevant Planning, Pages 5-133 to 5-158. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-7 and Appendix A, Initial Study and NOP, Page 35. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 72 5.4.12 Mineral Resources Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Result in the loss of availability of a known mineral resource that would be of value to the region and the residents of the State? Less than Significant ☐ ☒ b) Result in the loss of availability of a locally-important mineral resource recovery site delineated on a local general plan, specific plan or other land use plan? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the mineral resources impacts related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.9.4 concluded that buildout of the General Plan would result in less than significant impacts related to mineral resources upon implementation of General Plan goals and policies and existing codes and regulations. No impacts were identified, and no mitigation measures were required in MMP No. 122. SEIR No. 346 concluded that buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No.122A. The State of California designates one MRZ-20 area and three specific areas of regionally significant mineral resources within the City. These areas are not proximate to the Project Site. Changes in land use resulting from implementation of the General Plan and Zoning Code Update would not significantly impact mineral resources in the MRZ-2 area because land in this area is largely built out or already planned for development. Impacts Associated with the Proposed Project: Would the project: a) Result in the loss of availability of a known mineral resource that would be of value to the region and the residents of the State? and b) Result in the loss of availability of a locally-important mineral resource recovery site delineated on a local general plan, specific plan or other land use plan? The Proposed Project involves the demolition of a commercial office site and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. There are no regionally significant mineral resource areas on or proximate to the Project Site. The Proposed Project KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 73 would not impact any parcels other than those analyzed in the Certified EIRs and would therefore not have the potential to impact mineral resources beyond those previously analyzed. The Proposed Project does not have any significant effects on the environment that either have not already been analyzed in the Certified EIRs or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate, therefore, no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.9, Mineral Resources, Pages 5-159 to 5-164. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-2 and Appendix A, Initial Study and NOP, Pages 35-36. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 74 5.4.13 Noise Would the project result in: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Generation of a substantial temporary or permanent increase in ambient noise levels in the vicinity of the project in excess of standards established in the local general plan or noise ordinance, or applicable standards of other agencies? Significant Unavoidable Adverse Impact ☐ ☒ b) Generation of excessive groundborne vibration or groundborne noise levels? Less than Significant ☐ ☒ c) For a project located within the vicinity of a private airstrip or an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project expose people residing or working in the project area to excessive noise levels? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the noise impacts related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.10.4 concluded that short-term construction noise as well as other long-term operational noise sources such as events, railroad and aircraft activity would not result in significant noise and vibration impacts. However, the EIR No. 330 noise analysis concluded that noise sensitive uses along several roadways would experience a substantial noise increase in excess of 65 dBA CNEL. Mitigation measures required by MMP No. 122 would reduce these potential noise impacts. Implementation of the proposed General Plan goals and policies, existing codes and regulations, and mitigation measures would reduce all potential short-term and long-term noise impacts to the extent feasible. However, even with implementation of mitigation measures and General Plan goals and policies, many roadways within the City would generate significant noise impacts. As a result, in locations where these roadways are adjacent to existing sensitive land uses, the impacts related to traffic noise would remain significant. The City Council adopted a Statement of Overriding Considerations for this impact. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 75 Supplemental EIR No. 346 concluded that buildout of the Housing Opportunity Sites would not result in new or greater significant impacts than those identified in Program EIR No. 330. No new mitigation measures were required in MMP No. 122A. Short-term noise impacts are impacts associated with demolition, site preparation, grading, and construction of the proposed land uses. Two types of short-term noise impacts could occur during construction. First, the transport of workers and movement of materials to and from the Project Site could incrementally increase noise levels along local access roads The second type of short- term noise impact is related to noise generated at the job site during demolition, site preparation, grading, and/or physical construction. The major source of noise in the City is from traffic traveling on its various roadways and freeways, including the I-5, SR-91, SR-55, SR-57, SR-241, Beach Boulevard (SR-39), and Imperial Highway (SR-90). Vehicles traveling on these routes have the potential to produce noise impacts on future development within the City of Anaheim. Implementation of the General Plan Goals and Policies, existing codes and regulations, and mitigation measures will reduce potential short- term and long-term noise impacts to the extent feasible. However, many of the roadways in the City are expected to generate noise levels in excess of 65 CNEL. In locations where these roadways are adjacent to existing sensitive land uses, the impacts are anticipated to remain significant. This is considered a significant and unavoidable adverse impact, and the Anaheim City Council adopted a Statement of Overriding Considerations with regard to this potential impact. An aspect of construction is its accompanying vibration. Excessive groundborne vibration is typically caused by activities such as blasting or the use of pile drivers during construction. However, these impacts would be assessed at the time specific development applications are submitted. The Fullerton Municipal Airport is located approximately 2 miles away from Anaheim. In the most current data available, the airport projected a maximum of 265,500 total operations for year 2000. However, the 65 CNEL Noise Contour for Fullerton Airport does not extend into the City of Anaheim and no significant impacts are anticipated. Several heliports within the City of Anaheim are utilized for helicopter take-off and landing. There are no private airstrips within the City. Implementation of the General Plan Goals and Policies, existing codes and regulations, and mitigation measures will reduce potential noise impacts from these sources. Impacts Associated with the Proposed Project: Would the project: a) Result in the generation of a substantial temporary or permanent increase in ambient noise levels in the vicinity of the project in excess of standards established in the local general plan or noise ordinance, or applicable standards of other agencies? The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. The Applicant has prepared a Noise Impact Analysis (Appendix H). The analysis concluded the Proposed Project would result in no new significant impacts and no new mitigation measures were identified. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 76 Off-Site Traffic Noise Analysis The Proposed Project includes demolition of 56,274 square feet of existing office uses and redevelopment of the Project Site with 83 three-story townhome dwelling units. The Trip Generation Analysis prepared for the Proposed Project by Ganddini Group (August 23, 2022) showed that the Proposed Project, when compared to traffic generated by the existing office uses, would result in a net decrease of approximately 12 vehicle trips per day with a net decrease of 46 trips during the AM peak hour and a net decrease of 34 trips during the PM peak hour. Typically, a doubling of traffic volumes is required to result in an increase of 3 dBA, which is considered to be a barely audible change. At a net decrease of 12 daily vehicle trips, the project- generated trips will not result in a doubling of traffic volumes along any affected road segment. This impact would be less than significant. No mitigation is required. Exterior Noise Analysis The City of Anaheim General Plan Noise Element (N-8) identifies exterior noise levels between 65 and 70 dBA CNEL as “conditionally acceptable” in private patios or balconies that are greater than 6 feet deep of single-family attached and multi-family residential units. The General Plan Noise Element (Page N-8) notes that exterior noise levels are to be attained in “habitable” exterior areas and need not encompass the entirety of a property. Special consideration should be given in the case of infill projects located along the City’s arterial corridors or railroad lines for exemption from the requirements of the exterior noise level standards (Table N-3), in order to achieve an appropriate balance between providing a quality living environment and attractive project design. Three proposed buildings have exterior patios facing Lincoln Avenue. Exterior noise levels at these patios will range between 69 and 70 dBA CNEL and would comply with the “normally acceptable” ambient noise levels adopted in the General Plan Noise Element. The Project would also be required to comply with the requirements of Anaheim Municipal Code Section 18.40.090 related to interior and exterior noise levels and required attenuation. Per Anaheim Municipal Code Section 18.40.090.050, exterior noise within common recreation areas of any single-family attached or multi-family dwelling project must be attenuated to a maximum of 65 dB CNEL. Common recreation areas proposed for active outdoor use are provided in between the proposed buildings and will not be exposed to noise levels that exceed 65 dBA CNEL. Impacts related to exterior noise levels at the Project Site would be less than significant. Interior Noise Analysis The General Plan Noise Element interior noise level standard is 45 dBA CNEL. Future traffic noise levels are expected to reach 71 dBA CNEL at the façade of the closest proposed residential dwelling units to Lincoln Avenue and Sunkist Street. For proposed windows and sliding glass doors that would be exposed to exterior noise levels that exceed 65 dBA CNEL, upgraded windows would be utilized to ensure that vehicle noise does not result in interior noise levels that exceed 45 dBA CNEL. Implementation of the design measure below will avoid significant impacts related to interior noise levels. Construction Noise Construction noise represents a short-term increase on the ambient noise levels. Construction- related noise levels are expected to create temporary and intermittent high-level noise KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 77 conditions at sensitive receptors surrounding the Project Site. Modeled unmitigated construction noise levels reached up to 71.5 dBA Leq at the nearest multi-family residential property line to the west, 73.5 dBA Leq at the nearest single-family residential property line to the north, 66.7 dBA Leq at the nearest multi-family residential property line to the northeast, 69.1 dBA Leq at the nearest multi-family residential property line to the southeast, and 78.5 dBA Leq at the nearest single-family residential property line to the south of the Project Site. Construction noise sources are regulated within the City of Anaheim under Section 6.70.010 of the City’s Municipal Code which exempts construction activities from the noise standards between the hours of 7:00 AM and 7:00 PM. The City of Anaheim has not adopted a numerical threshold that identifies what a substantial increase would be. For purposes of this analysis, the Federal Transit Administration (FTA) Transit Noise and Vibration Impact Assessment (2018) criteria would be used to establish significance thresholds. For residential uses, the daytime noise threshold is 80 dBA Leq averaged over an 8- hour period (Leq (8-hr); and the nighttime noise threshold is 70 dBA Leq (8-hr). For commercial uses, the daytime and nighttime noise threshold is 85 dBA Leq (8-hr). In compliance with the City’s Code, construction would not occur during the noise-sensitive nighttime hours. Impacts would be less than significant, and no mitigation is required. As addressed above, the Proposed Project would result in less than significant impacts related to noise and would not introduce impacts that have not already been analyzed in EIR No. 330 and SEIR No. 346 or that are more significant than previously analyzed, or that the application of uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. b) Result in the generation of excessive groundborne vibration or groundborne noise levels? Construction activity can result in varying degrees of ground vibration, depending on the equipment and methods used, distance to the affected structures, and soil type. peak particle velocity (PPV) level of 0.3 in/sec is generally accepted as the threshold at which there is a risk to “architectural” damage to older residential structures and a PPV level of 0.5 in/sec as the threshold at which there is a risk to “architectural” damage to modern industrial/commercial buildings. If a vibratory roller is used within 20 feet of an existing structure or if a large bulldozer is used within 12 feet of an existing structure, there would be some potential for this equipment to result in architectural damage and significant impacts (California Department of Transportation, 2020). A best management practice limiting the use of a vibratory roller within 20 feet or a large bulldozer within 12 feet of the existing residential structures to the south and west of the Project Site would be implemented to avoid significant impacts. Groundborne vibration becomes strongly perceptible to sensitive receptors at a level of 0.1 PPV. Operation of a vibratory roller may result in groundborne vibration levels of up to 0.1 PPV at a distance of 41 feet and a large bulldozer at a distance of 23 feet. Therefore, project construction could cause annoyance to the residential uses to the south and west of the Project Site. However, annoyance would be short-term and will occur only during site grading and preparation which would be limited to daytime hours. Vibration impacts would be less than significant and no further environmental analysis is required. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 78 c) For a project located within the vicinity of a private airstrip or an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project expose people residing or working in the project area to excessive noise levels? As previously addressed, the 65 CNEL Noise Contour for Fullerton Airport does not extend into the City of Anaheim and no impacts are anticipated. Several heliports within the City of Anaheim are utilized for helicopter take-off and landing. There are no private airstrips within the City. Therefore, a less than significant impact will occur, and no further environmental analysis is required. Project Design Feature: PDF NOI-1: Windows and sliding glass doors on building elevations that will be exposed to exterior noise levels that exceed 65 dBA CNEL, will be upgraded to ensure that vehicle noise does not result in interior noise levels that exceed 45 dBA CNEL inside the residence. Existing Programs and Policies: PPP NOI-1: The following Best Management Practices, included as Conditions of Approval, would reduce any noise level increases produced by the construction equipment to the nearby noise- sensitive residential land uses: • Prior to approval of grading plans and/or issuance of building permits, the Property Owner/Developer shall include a note on the plans indicating that noise-generating Project construction activities shall only occur between the hours of 7:00 a.m. to 7:00 p.m. on any day (City of Anaheim Municipal Code, Section 6.050.010). The Project construction supervisor shall ensure compliance with the permitted construction hours. • The Property Owner/Developer shall post a construction site notice near the construction site access point or in an area that is clearly visible to the public. The notice shall include the following: job site address; permit number, name, and phone number of the contractor and owner; dates and duration of construction activities; construction hours allowed; and the City of Anaheim and construction contractor phone numbers where noise complaints can be reported and logged. • Ongoing during construction, the Construction Contractors shall do all of the following: o All construction equipment whether fixed or mobile, will be equipped with properly operating and maintained mufflers, consistent with manufacturer standards. o All stationary construction equipment will be placed so that emitted noise is directed away from the noise sensitive receptors nearest the Project Site. o As applicable, shut off all equipment when not in use. o To the degree possible, equipment staging will be located in areas that create the greatest distance between construction-related noise and vibration sources, and sensitive receptors surrounding the Project Site. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 79 o Jackhammers, pneumatic equipment, and all other portable stationary noise sources will be directed away and shielded from existing residences in the vicinity of the Project Site. Either one-inch plywood or sound blankets can be utilized for this purpose. They should reach up from the ground and block the line of sight between equipment and existing residences. The shielding should be without holes and cracks. o No amplified music and/or voice will be allowed on the Project Site. o Haul truck deliveries will not occur outside of the hours presented as exempt for construction per City’s Municipal Code Section 6.70.010. PPP NOI-2: A best management practice limiting the use of a vibratory roller within 20 feet or a large bulldozer within 12 feet of the existing residential structures to the south and west of the Project Site will be implemented to avoid significant impacts. Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Appendix H – KB Home Lincoln & Sunkist Noise Impact Analysis, Ganddini Group, Inc., November 21, 2022. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.10, Noise, Pages 5-165 to 5-198. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 5.3, Noise, Page 5.3-1 through 5.3- 22; Appendix A, Initial Study and NOP, Pages 36-37. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 80 5.4.14 Population and Housing Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Induce substantial unplanned population growth in an area, either directly (for example, by proposing new homes and businesses) or indirectly (for example, through extension of roads or other infrastructure)? Less than Significant ☐ ☒ b) Displace substantial numbers of existing people or housing, necessitating the construction of replacement housing elsewhere? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the population and housing impacts related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.12.4 concluded that buildout of the General Plan would result in less than significant impacts related to population and housing upon implementation of General Plan goals and policies, and existing codes and regulations. No impacts were identified, and no mitigation measures were required in MMP No. 122. SEIR No. 346 concluded that buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No. 112A. Implementation of the General Plan provides opportunities to construct units housing units within one of the State’s largest employment concentrations. Areas anticipated for additional residential development include The Platinum Triangle and The Colony and Downtown Area. The close proximity of the future housing units and employment opportunities responds directly to the City’s jobs/housing balance policies. Implementation of the General Plan, combined with other cumulative development in the area, will result in a potential cumulative impact on employment, housing, and population. This potential impact is considered substantial, but not adverse, in light of the Proposed Project’s contribution to improved jobs/housing balance and transportation demand management promoted by SCAG’s regional policies. Therefore, there are no significant unavoidable adverse impacts related to population and housing. The Project Site is identified as Housing Opportunity Sites 154 and 155 in the City’s 5th Cycle (2014-2021) Housing Element with a maximum buildout of 139 residential units. The City of Anaheim is currently seeking certification of the 6th Cycle (2021-2029) Housing Element. The Proposed Project is included in the 6th Cycle Housing Element as Pipeline Project P-71. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 81 Impacts Associated with the Proposed Project: Would the project: a) Induce substantial unplanned population growth in an area, either directly (for example, by proposing new homes and businesses) or indirectly (for example, through extension of roads or other infrastructure)? and b) Displace substantial numbers of existing people or housing, necessitating the construction of replacement housing elsewhere? The Proposed Project involves the demolition of a commercial office site and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The General Plan land use designation of the Project Site is Medium Density Residential. The Project Site is zoned for General Commercial “C-G” uses and is within the Residential Opportunity (RO) Overlay Zone. The RO Zone provides “by-right” housing development opportunities consistent with a property’s residential General Plan land use designation. The RO Overlay Zone is intended to be applied to properties that are currently zoned and/or developed with non-residential uses but designated for multiple-family residential uses by the City’s General Plan. The Overlay Zone is further intended to serve as an implementation tool of the City’s Housing Element of the General Plan by facilitating residential development on identified “housing opportunity sites.” The maximum buildout of the Project Site, as listed in Table 3-2 of SEIR No. 346, is 139 residential units. Therefore, the Proposed Project would not induce population growth in the area to a greater degree than was evaluated in the Certified EIRs. Removal of the existing industrial use would not displace any people or housing. The Proposed Project does not have any significant effects on the environment that either have not already been analyzed in the Certified EIRs or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate, therefore, no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.12, Population and Housing, Pages 5-203 to 5-212. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-7, and Appendix A, Initial Study and NOP, Page 37. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 82 5.4.15 Public Services Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity Result in substantial adverse physical impacts associated with the provision of new or physically altered governmental facilities, need for new or physically altered governmental facilities, the construction of which could cause significant environmental impacts, in order to maintain acceptable service ratios, response times or other performance objectives for any of the public services: a) Fire protection? Less than Significant After Mitigation ☐ ☒ b) Police protection? Less than Significant After Mitigation ☐ ☒ c) Schools? Less than Significant After Mitigation ☐ ☒ d) Parks? Less than Significant ☐ ☒ e) Other public facilities? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the impacts on public services related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330 determined development of the project area would have a substantial demand for fire and police protection services and would indirectly result in the demand for school services, parks, and libraries. EIR No. 330, Section 5.11.4 concluded that buildout of the General Plan would result in less than significant impacts to police and fire protection upon implementation of MM 5.11-1 in MMP No. 122. EIR Section 5.13.4 concluded that buildout of the General Plan would result in less than significant impacts to school services upon payment of school fees pursuant to SB 50 and implementation of MM 5.13-1; less than significant impacts to recreational facilities through continued compliance with the City of Anaheim Park Dedication Ordinance; and less than significant impacts to library and no mitigation measures are required in MMP No. 122. SEIR No. 346 concluded that buildout of the Housing Opportunity Sites would result in no new impacts than were identified in EIR 330 and no new mitigation measures were required in MMP No. 122A. Police and Fire Implementation of the General Plan would increase the overall demand on fire and police protection services in the City of Anaheim. There would also be an increase in the number of KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 83 responses within the City which would increase the demand for existing apparatus, equipment, and personnel. Therefore, the City of Anaheim's costs to maintain equipment and apparatus and to train and equip personnel would also increase. In addition, the redistribution of the population into areas where there are currently no residences, could necessitate the reassignment of certain kinds of resources pertaining to fire and police services. However, the additional personnel and materials costs may be offset through the increased revenue, and fees, generated by future development. School Services While the City acknowledged that future growth will result in increased need for school facilities, the City is precluded per SB 50 to consider this a significant impact for the purposes for CEQA. The payment of development fees will offset the costs to each school district of providing educational facilities to these students. In addition, the General Plan Goals and Policies for the Community Development Department to work with school districts to identify sites for new schools and school expansions in West and Central Anaheim and the Platinum Triangle area will further reduce potential impacts. Parks Development in accordance with the General Plan and Zoning Code Update will increase demands on existing recreational facilities. Implementation of the Green Element Goals and Policies and compliance with the City's Park Dedication Ordinance reduces any impacts to recreational facilities to a less-than-significant level. Library Services Any increase in the population or employee population of the City of Anaheim is anticipated to have an impact on Library Services. However, the projected growth of the City has been included in the Library Facilities' Master Plan and would meet the need for library building space. Impacts Associated with the Proposed Project: Would the project result in substantial adverse physical impacts associated with the provision of new or physically altered governmental facilities, need for new or physically altered governmental facilities, the construction of which could cause significant environmental impacts, in order to maintain acceptable service ratios, response times or other performance objectives for any of the public services: a-e) Fire protection, police protection, schools, parks, or other public facilities? The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. The maximum buildout of Housing Opportunity Sites 154 and 155, as listed in Table 3-2 of S EIR No. 346, is 139 residential units. Therefore, based on a reduction in the number of anticipated residential units on the Project Site, the demand for public services generated by the Proposed Project would be less than those of 139 residential units evaluated in the Certified EIRs. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 84 The Project Site will continue to be primarily served by Fire Station #5, located at 2540 E. La Palma Avenue, and the Police Department Main Station, located at 425 S. Harbor Blvd. In order to provide adequate emergency vehicle access, the Proposed Project would have one driveway on Lincoln Avenue and one driveway on Sunkist Street with widths consistent with the 24 feet minimum requirement in the Anaheim Municipal Code. The Applicant would also comply with MM 5.11-1 to pay police and fire impact fees at the time of issuance of building permits. These fees will help cover costs for any additional personnel, apparatus, equipment, and materials associated with the Project. Therefore, a less than significant impact will occur, and no further environmental analysis is required. The Project Site is within the Anaheim Union High School District with a district-wide enrollment of 29,828 and the Anaheim Elementary School District with current district-wide enrollment of 15,252 students and current capacity of 17,725. Students will attend Juarez Elementary, Sycamore Junior High, and Katella High School. Juarez Elementary School has 777 enrolled students, Sycamore Junior High has 1,325 enrolled students, and Katella High has 2,720 students. Current student generation factors used by the Anaheim Elementary School District are 0.23 per unit for single-family attached homes, and 0.15 per unit for multi-family units. Current student generation factors used by the Anaheim Union High School District are 0.0806 per unit for junior high schools and 0.1548 per unit for high schools. Based on these generation factors, the project would generate a total of 39 students consisting of 19 elementary students, 7 junior high students, and 13 high school students. Table 5.13-14 in EIR No. 330 used multi-family student generation rates of 0.116 per unit for elementary, 0.013 per unit for junior high, and 0.032 per unit for high school. SEIR No. 346 assumed these same generation rates. Housing Opportunity Sites 154 and 155 were assumed to have 139 multi-family units. Therefore, the student capacity analyzed in SEIR No. 346 assumed a total of 24 students consisting of 17 elementary students, 2 junior high students, and 5 high school students. This increase of 15 students would not cause the school districts to exceed their respective enrollment capacities. The Applicant would be required to pay school impact fees pursuant to Senate Bill 50 (SB 50, codified in Government Code Section 65995), which was enacted in 1988 to address how schools are financed and how development projects may be assessed for associated school impacts. SB 50 provides three ways to determine funding levels for school districts. The default method allows school districts to levy development fees to support school construction necessitated by that development and receive a 50 percent match from State bond money. The payment of development fees would offset the costs to each District of providing educational facilities to these students. Therefore, the Proposed Project would be required to pay the current development impact fees for residential development. Therefore, impacts would be less than significant and no further environmental analysis is required. As indicated in EIR No. 330, the projected growth of the City, including the Project Site, has been included in the Library Facilities’ Master Plan and would meet the need for library building space. Impacts to library service would remain less than significant and no further environmental analysis is required. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 85 Existing Programs and Policies: PPP PS-1: The Property Owner/Developer would pay school impact fees pursuant to Senate Bill 50 (Government Code Section 65995). Applicable MMP No. 122 Mitigation Measures: MM 5.11-1: Future projects will be reviewed by the City of Anaheim on an individual basis and will be required to comply with requirements in effect at the time building permits are issued (i.e., impact fees, etc.) or if an initial study is prepared and the City determines the impacts to be significant, then the project will be required to comply with appropriate mitigation measures (i.e., fire station sites, etc.). Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.11, Police and Fire, Pages 5-199 to 5-202 and 5.13; Public Services and Facilities, Pages 5-213 to 5-250; and Chapter 5.14, Recreation, Pages 5-259 to 5-262. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-7 an d Appendix A, Initial Study and NOP, Page 37. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. National Center for Education Statistics. 2022. https://nces.ed.gov/ccd/schoolsearch/index.asp. Accessed November 21, 2022. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 86 5.4.16 Recreation Would the Project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Would the project increase the use of existing neighborhood and regional parks or other recreational facilities such that substantial physical deterioration of the facility would occur or be accelerated? Less than Significant ☐ ☒ b) Does the project include recreational facilities or require the construction or expansion of recreational facilities which might have an adverse physical effect on the environment? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the impacts to recreation and recreational facilities related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.14.4 concluded that buildout of the General Plan would increase demand for parks in the City overall, and specifically in areas where residential uses would be permitted where no such uses existed at the time. Residential developments in the City are required to dedicate land for parkland and/or pay in- lieu fees to offset impacts on demands for parks. Impacts were less than significant after compliance with the City’s park dedication ordinance and no mitigation measures were required in MMP No. 122. SEIR No. 346 concluded that buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in Program EIR No. 330 and no new mitigation measures were required in MMP No. 122A. Development in accordance with the General Plan and Zoning Code Update will increase demands on existing recreational facilities. However, continued compliance with the City of Anaheim park dedication ordinance would mitigate any potential impacts to recreational facilities. Implementation of the Green Element Goals and Policies and compliance with the City's park dedication ordinance reduces any impacts to recreational facilities to a less-than-significant level. Impacts Associated with the Proposed Project: Would the project: a) Increase the use of existing neighborhood and regional parks or other recreational facilities such that substantial physical deterioration of the facility would occur or be accelerated? and KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 87 b) Include recreational facilities or require the construction or expansion of recreational facilities which might have an adverse physical effect on the environment? The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. Community residents would have access to common recreational amenities including a dog park, community garden, and tot lot., in addition to private patios and balconies. Private open space and common recreational areas serving apartment residents would total over 24,852 square feet, which exceeds the code requirements for open space by nearly 2,000 square feet. Refer to previous Figure 5, Open Space Plan. In addition to the private common recreational amenities serving the Proposed Project, future residents would have access to public parks located within walking distance. The closest public park, Pioneer Park, 2565 E. Underhill Avenue, Anaheim, CA 92806, is 0.6 mile, or a 12-minute walk, northeast of the Project Site. It is a 15.8-acre park and includes a children’s play area, picnic tables, fitness zone, and sports fields. Juarez Park is located 0.8 miles south of the Project Site, at 841 S. Sunkist Street, Anaheim, CA 92806. It is a 9.5-acre park and includes a children’s play area, picnic tables, and sports fields. Other parks and recreation amenities within a one-mile radius of the Project Site include Boysen Park, Rio Vista Park and Anaheim Coves Trail. With ample public parks in the Project vicinity, the Proposed Project would not increase the use of any an existing park such that substantial physical deterioration would occur. The maximum buildout of the Project Site, as listed in Table 3-2 of SEIR No. 346, is 139 residential units. The Proposed Project includes 83 residential units. Therefore, the Proposed Project would not induce population growth in the area to a greater degree than was evaluated in SEIR No. 346. With implementation of PPP REC-1 the Proposed Project does not have any significant impacts related to recreation that either have not already been analyzed in the Certified EIRs or that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate, therefore, no further environmental analysis is required. Existing Programs and Policies: PPP REC-1: Prior to issuance of building permits, the Property Owners/Developers shall comply with Anaheim Municipal Code, Section 17.08.250, which requires the provision of parkland and/or the payment of fees, consistent with the Quimby Act. Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.14, Recreation, Pages 5-250 to 5-262. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-7 and Appendix A, Initial Study and NOP, Pages 37-38. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 88 City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 89 5.4.17 Transportation Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Conflict with a program, plan, ordinance, or policy addressing the circulation system, including transit, roadway, bicycle and pedestrian facilities? Less than Significant ☐ ☒ b) Would the project conflict or be inconsistent with CEQA Guidelines section 15064.3, subdivision (b)? ☐ ☒ c) Substantially increase hazards due to a geometric design feature (e.g., sharp curves or dangerous intersections) or incompatible uses (e.g., farm equipment)? Less than Significant ☐ ☒ d) Result in inadequate emergency access? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the transportation and traffic impacts related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.15.3, which concluded that buildout of the General Plan would result in significant traffic impacts at seven intersections. With implementation of MM 5.15-1 through 5.15-8, Program EIR No. 330 identified traffic impacts at three intersections as significant and unavoidable. Program EIR No. 330 also identified impacts at one Congestion Management Program intersection, Harbor Boulevard and Ball Road, as significant and unavoidable. The City Council adopted a Statement of Overriding Considerations related to this impact. Buildout of the General Plan would result in less than significant impacts to air traffic levels and air traffic patterns; roadway design hazards; emergency access; and parking capacity. No mitigation measures related to these impacts were required in MMP No. 122. SEIR No. 346 concluded that buildout of the Housing Opportunity Sites would result in significant traffic impacts at 20 intersections. With implementation of new MM 5.15-8, Supplemental EIR No. 346 identified traffic impacts at seven of the intersections as significant and unavoidable due to physical adopted a Statement of Overriding Considerations related to this impact. Buildout of the Housing Opportunity Sites would not result in new or greater significant impacts than those identified in EIR No. 330 related to roadway design hazards, emergency access, or alternative transportation. No new mitigation measures were required in MMP No. 122A. Implementation of the General Plan and Zoning Code Update is anticipated to result in roadways citywide accommodating a modest amount of growth from the existing baseline to the future KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 90 scenario. Several arterial highways within the City are projected to accommodate a significant amount of growth in daily traffic. The General Plan and Zoning Code update would result in 25 of the 250 study intersections operating at an unacceptable level of service (LOS E or F) during at least one of the peak periods. Four of the intersections would operate at unacceptable levels in both the AM and PM peak periods. Mitigation measures will ensure that the Proposed Project contributes to planned roadway improvements on a "fair-share" basis. The planned roadway improvements are feasible and avoid or substantially lessen potentially significant traffic and circulation impacts to a less-than-significant level. However, necessary improvements to the Harbor Boulevard/Ball Road intersection could impact adjacent land uses. As a result, a significant unavoidable adverse impact would remain if the City Council decides not to implement the necessary improvements to the Harbor Boulevard/Ball Road intersection. The Anaheim City Council adopted a Statement of Overriding Considerations with regard to this potential impact. Criteria for Preparation of a Traffic Impact Analysis The City of Anaheim require traffic studies to assess a project’s effect on LOS and other operational standards established by the City for General Plan consistency. Preparation of a traffic impact study in accordance with the requirements outlined in the City of Anaheim Criteria for the Preparation of Traffic Impact Studies (“the City TIS Guidelines”) is required in the following cases: • When the AM or PM peak hour trip generation is expected to exceed 100 vehicle trips from the proposed development. • Projects on the Congestion Management Program (CMP) Highway System which generate 1,600 average daily trips (ADT) or adjacent to the CMP Highway System which generate 2,400 ADT. • Projects that will add 51 or more trips during either the AM or PM peak hours to any monitored CMP intersection. • Any project where variations from the standards and guidelines provided in this manual are being proposed. The Proposed Project is forecast to generate fewer than 100 net new trips during the AM or PM peak hours. Additionally, the Proposed Project is not located on the CMP Highway System and would not exceed the CMP trip contribution thresholds of 2,400 ADT or 51 trips to a CMP- monitored intersection during the AM or PM peak hours. Therefore, the Proposed Project does not meet any of the City-established thresholds requiring the preparation of a traffic impact study for LOS analysis based on the net trip generation forecast and further analysis is not warranted. Trip Generation Analysis The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. The Project Site contains commercial buildings, parking areas, and landscaping. Ganddini Group prepared a Trip Generation Analysis for the proposed project on August 23, 2022 (Appendix I). Based on the estimated trip generation, the Proposed Project would generate less than 100 KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 91 weekday peak hour vehicle trips and no further traffic impact analysis is required in accordance with the City of Anaheim Criteria for Preparation of Traffic Impact Studies. Vehicle Miles Traveled (VMT) Analysis The Proposed Project VMT screening evaluation was performed in accordance with guidance from the City of Anaheim Transportation Impact Analysis Guidelines for California Environmental Quality Act Analysis (June 2020) [“City VMT Guidelines”], which were developed based on guidance from the OPR Technical Advisory. The City VMT Guidelines establish three types of project screening that can apply to effectively screen projects from project-level assessment. A project only needs to fulfill one of the following three screening types to qualify for screening. These screening criteria are: • Transit Priority Area (TPA) Screening • Low VMT-generating Area Screening • Project Type Screening Some project types are presumed to have a less than significant transportation impact absent substantial evidence to the contrary as their uses are local serving in nature. Local serving retail generally improves the convenience of shopping close to home and has the effect of reducing vehicle travel. The City VMT Guidelines identify the following uses that can be screened from project-level assessment as they are presumed to have a less than significant impact due to their local serving nature. One category includes projects generating less than 110 daily vehicle trips. The Proposed Project is forecast to result in a net decrease of approximately 12 daily trips compared to the existing land use. Therefore, the Proposed Project satisfies the City-established project type screening criteria for projects generating less than 110 daily trips. Impacts Associated with the Proposed Project: Would the project: a) Conflict with a program, plan, ordinance or policy addressing the circulation system, including transit, roadway, bicycle and pedestrian facilities? Ganddini Group prepared a Trip Generation Analysis (August 23, 2022, Appendix I), which forecast the Proposed Project would result in a net decrease of approximately 12 fewer daily trips compared to the existing land use, including 46 fewer trips during the AM peak hour and 34 fewer trips during the PM peak hour. Pedestrian facilities, including sidewalks and crosswalks are available in the project vicinity. Internal pedestrian connectivity would be provided by walkways that connect the common open space amenities and connect to the existing City sidewalks along Lincoln Avenue and Sunkist Street. The Proposed Project would also be located near various alternative transportation modes and routes, include transit stops for OCTA Routes 42, 57 and 153. The Proposed Project would not have any significant impacts related to conflicts with a program plan, ordinance, or policy addressing the circulation system that the Certified EIRs has not already analyzed and would not result in more significant or more severe impacts than those analyzed in the Certified EIRs. No further environmental analysis is required. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 92 b) Would the project conflict or be inconsistent with CEQA Guidelines Section 15064.3, subdivision (b)? The State of California adopted changes to the CEQA Guidelines in December 2018, which require all lead agencies to adopt VMT as a replacement for automobile delay-based Level of Service (LOS) as the new measure for identifying transportation impacts for land use projects. This statewide mandate went into effect July 1, 2020. Ganddini Group prepared a Vehicle Miles Traveled Screening Assessment for the proposed project on August 23, 2022 (Appendix J). The VMT analysis evaluated the applicable screening thresholds in the City of Anaheim Traffic Impact Analysis Guidelines for California Environmental Quality Act Analysis (June 2020) to determine whether the Proposed Project would create impacts related to VMT. Some project types are presumed to have a less than significant transportation impact, as their uses can be considered local serving in nature. Among the list of various uses, projects generating less than 110 daily vehicle trips can be presumed to have a less than significant impact. According to the VMT analysis, the existing office use to be removed is estimated to generate approximately 610 daily trips, including 86 trips during the AM peak hour and 81 trips during the PM peak hour. The P Proposed Project is forecast to generate approximately 598 daily trips, including 40 trips during the AM peak hour and 47 trips during the PM peak hour. Therefore, the Proposed Project is forecast to result in a net decrease of approximately 12 fewer daily trips compared to the existing land use, including 46 fewer trips during the AM peak hour and 34 fewer trips during the PM peak hour. As such, the Proposed Project will generate less than 110 daily vehicle trips. Therefore, the Proposed Project can be presumed to have a less than significant impact under Type 3: Project Type Screening per the City’s Guidelines for VMT analysis. Thus, impacts would be less than significant, and no mitigation is required. No further environmental analysis is required. c) Substantially increase hazards due to a geometric design feature (e.g., sharp curves or dangerous intersections) or incompatible uses (e.g., farm equipment)? The Proposed Project would replace an existing driveway access to the project site on Lincoln Avenue and Sunkist Street with new driveways on Lincoln Avenue and Sunkist Street. The driveways would provide right turn in and right turn out access to both streets. The Proposed Project would also include an internal roadway to provide circulation within the development. The Proposed Project driveways and internal roadway would be developed to comply with the City Building Division and Fire & Rescue Department standards. The Proposed Project would develop 83 townhomes and would not include the use of any incompatible vehicles or equipment, such as farm equipment. The Proposed Project is surrounded by residential uses; therefore, the Proposed Project’s residential development would be compatible with the surrounding uses. The Proposed Project would not substantially increase hazards due to design or incompatible uses. The Proposed Project would not have any significant impacts related to hazardous design features that the Certified EIR has not already analyzed and would not result in more significant or more severe impacts than those analyzed in the Certified EIR. No further environmental analysis is required. d) Result in inadequate emergency access? As previously discussed, the Proposed Project would provide site access via a driveway on Lincoln Avenue and a driveway on Sunkist Street, which are required to be compliant with City Building KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 93 Division and Fire & Rescue Department standards. This compliance includes that the Proposed Project driveways and internal circulation would accommodate standard fire lane turning radiuses and hammerhead turnaround maneuvers. To ensure compliance, the Anaheim Fire & Rescue would review project plans for final approval prior to issuance of a building permit. Further, it is not anticipated that construction of the Proposed Project would require the closure of any public roadways. Temporary construction activities would not impede the use of the public roads for emergencies or access for emergency response vehicles. The Proposed Project would not have any significant impacts related to emergency access that the Certified EIRs have already analyzed and would not result in more significant or more severe impacts than those analyzed in the Certified EIRs. No further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 Mitigation Measures: MM 5.15-5: Prior to issuance of each building permit, appropriate Transportation Impact and Improvement Fees shall be paid by the property owner/developer to the City of Anaheim in amounts determined by the City Council Resolution in effect at the time of issuance of the building permit with credit given for City-authorized improvements provided by the Property Owner/Developer; and participate in all applicable reimbursement or benefit districts which have been established. MM 5.15-6: Prior to approval of the first final subdivision map or issuance of the first building permit, whichever occurs first, and subject to nexus requirements, the property owner/ developer shall irrevocably offer for dedication (with subordination of easements), including necessary construction easements, the ultimate right(s)-of-way as shown in the Circulation Element of the Anaheim General Plan adjacent to their property. Applicable MMP No. 122A Mitigation Measure: MM 5.15-8: The General Plan Circulation Element and associated Planned Roadway Network Map (Figure C-1 of the General Plan), identifies those roadways that are planned to accommodate current development and future growth established by the Land Use Element. Roadways will be constructed as development occurs and as funding becomes available. In addition to the roadways identified on the Planned Roadway Network Map, the improvements identified in Table 5.4-7 will be necessary to maintain acceptable levels of service within the anticipated theoretical buildout identified in the General Plan. Sources: Appendix I – KB Home Lincoln & Sunkist Project Trip Generation Analysis, Ganddini Group, Inc., August 23, 2022. Appendix J – KB Home Lincoln & Sunkist Project Vehicle Miles Traveled Screening Assessment, Ganddini Group, Inc., August 23, 2022. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.15, Traffic and Circulation, Pages 5-263 to 5-322. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 94 City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 5.2, Transportation/Traffic, Page 5-13 through 5-34; Appendix A, Initial Study and NOP, pages 39-40. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 95 5.4.18 Tribal Cultural Resources Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity Would the project cause a substantial adverse change in the significance of a tribal cultural resource, defined in Public Resources Code section 21074 as either a site, feature, place, cultural landscape that is geographically defined in terms of the size and scope of the landscape, sacred place, or object with cultural value to a California Native American tribe, and that is: a) Listed or eligible for listing in the California Register of Historical Resources, or in a local register of historical resources as defined in Public Resources Code section 5020.1(k), or Less than Significant After Mitigation ☒ b) A resource determined by the lead agency, in its discretion and supported by substantial evidence, to be significant pursuant to criteria set forth in subdivision (c) of Public Resources Code Section 5024.1. In applying the criteria set forth in subdivision (c) of Public Resource Code Section 5024.1, the lead agency shall consider the significance of the resource to a California Native American tribe. Less than Significant After Mitigation ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 and SEIR No. 346 did not explicitly evaluate tribal cultural resources because this impact area was not included in the CEQA Guidelines Appendix G checklist until 2014. However, they did address the potential impacts to cultural resources associated with implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.4.4 concluded that the buildout of the General Plan would result in less than significant impact to cultural resources with the implementation of the General Plan Goals and Policies, existing codes and regulations, and MM 5.4-1, 5.4-2 and 5.4-3 required in MMP No. 122. Supplemental EIR No. 346 concluded that the buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No. 122A. Impacts Associated with the Proposed Project: a) Would the project cause a substantial adverse change in the significance of a tribal cultural resource, defined in Public Resources Code section 21074 as either a site, feature, place, cultural landscape that is geographically defined in terms of the size and scope of the landscape, sacred place, or object with cultural value to a California Native American tribe, and that is: KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 96 (i.) Listed or eligible for listing in the California Register of Historical Resources, or in a local register of historical resources as defined in Public Resources Code Section 5020.1(k), or (ii.) A resource determined by the lead agency, in its discretion and supported by substantial evidence, to be significant pursuant to criteria set forth in subdivision (c) of Public Resources Code Section 5024.1. In applying the criteria set forth in subdivision (c) of Public Resource Code Section 5024.1, the lead agency shall consider the significance of the resource to a California Native American tribe. The following analysis is based on a Cultural and Biological Resources Due Diligence Study prepared by Brian F. Smith and Associates, Inc. (Appendix B). As discussed in the Cultural Resources section, the project site is not listed or eligible for listing in the California Register of Historical Resources, or in a local register of historical resources as defined in Public Resources Code Section 5020.1(k). Assembly Bill 52 (AB 52) requires lead agencies to conduct a formal consultation process with California Native American Tribes to identify potential significant impacts to Tribal Cultural Resources (TCRs), as defined in Public Resources Code Section 21074, as part of CEQA. The Proposed Project is exempt from CEQA as documented in this Appendix N Checklist. A Sacred Lands File search was requested from the NAHC for the project to identify any sacred, religious, or ceremonial sites recorded within the area of the subject property, which returned negative results. The property records search from the South Central Coastal Information Center (SCCIC) at California State University, Fullerton indicate that no previously recorded sites or reports are recorded within or crossing the Project Site. There are no previously documented prehistoric archaeological sites or ethnographically documented camps within or near the project site—indicating a low probability for TCRs to exist. Past development that has occurred on the project site and surrounding area, including grading, further decrease the probability of any tribal resources. Impacts would be less than significant and no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 Mitigation Measures: MM 5.4-1: City staff shall require property owners/developers to provide studies to document the presence/absence of historic resources for areas with documented or inferred resource presence. On properties where resources are identified, such studies shall provide a detailed mitigation plan, including a monitoring program and recovery and/or in situ preservation plan, based on the recommendations of a qualified specialist. The requirement for historic resources documentations set forth in this mitigation measure has been satisfied by the completion of the Cultural and Biological Due Diligence Study prepared for the proposed project (Appendix B). Consequently, no further action is required. MM 5.4-2: City staff shall require property owners/developers to provide studies to document the presence/absence of archaeological and/or paleontological resources for areas with KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 97 documented or inferred resource presence. On properties where resources are identified, such studies shall provide a detailed mitigation plan, including a monitoring program and recovery and/or in situ preservation plan, based on the recommendations of a qualified specialist. The requirement for archaeological and paleontological resources documentation set forth in this mitigation measure has been satisfied by the completion of the Cultural and Biological Due Diligence Study prepared for the proposed project (Appendix B). Consequently, no further action is required. MM 5.4-3 All archaeological resources shall be subject to the provisions of CEQA (Public Resources Code) Section 21083.2. Sources: Appendix B – Results of a Cultural and Biological Resources Due Diligence Study for the 2420 East Lincoln Avenue Project, APNs 083-731-18 and -19, Orange County, California, Brian F. Smith and Associates, Inc., rev. November 18, 2022. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.4, Cultural Resources, Pages 5-49 through 5-59. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-2 and Appendix A, Initial Study and NOP, Page 30. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. Pages 2-7 to 2-11. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 98 5.4.19 Utilities and Service Systems Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Require or result in the relocation or construction of new or expanded water, wastewater treatment or storm water drainage, electric power, natural gas, or telecommunications facilities, the construction or relocation of which could cause significant environmental effects? Less than Significant After Mitigation ☐ ☒ b) Have sufficient water supplies available to serve the project and reasonably foreseeable future development during normal, dry and multiple dry years? Less than Significant After Mitigation ☐ ☒ c) Result in a determination by the wastewater treatment provider which serves or may serve the project that it has adequate capacity to serve the project’s projected demand in addition to the provider’s existing commitments? Less than Significant ☐ ☒ d) Generate solid waste in excess of State or local standards, or in excess of the capacity of local infrastructure, or otherwise impair the attainment of solid waste reduction goals? Less than Significant ☐ ☒ e) Comply with federal, State, and local management and reduction statutes and regulations related to solid waste? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the impacts to utilities and service systems related to the implementation of the General Plan and Zoning Code Update Program. EIR No. 330, Section 5.12.4 concluded that buildout of the General Plan would result in less than significant impacts related to utilities and service systems, including water services, sewer services, solid waste, natural gas, telephone and cable services, with implementation of MM 5.13-3 and 5.13-6 in MMP No. 122. Supplemental EIR 346 concluded that buildout of the Housing Opportunity Sites would result in no new or increased significant impacts than those identified in EIR No. 330 and no new mitigation measures were required in MMP No. 122A. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 99 According to the City’s 2020 Urban Water Management Plan, the City relies on a combination of imported water, local groundwater, and a small amount of recycled water to meet its water needs. The City works together with two primary agencies, Metropolitan and the Orange County Water District (OCWD), to ensure a reliable water supply that would continue to serve the City in periods of drought and shortage. The City’s main source of water supply is groundwater from the Orange County Groundwater Basin. The City has historically relied on approximately 70 percent groundwater (previous 10-year average) and 30 percent imported water from Metropolitan to supply its customers. The same water supply mix is anticipated to be available to the City through 2040. The City’s Sewer and Storm Drain Maintenance Division is responsible for maintenance of the City’s sewer and storm drain lines. The Proposed Project is within the Combined Central Anaheim Area Master Plan of Sanitary Sewers (CCAAMPSS), adopted in December 2017. The CCAAMPSS study area consists of approximately 10,627 acres in gross area and serves a population of approximately 134,000 people. The area is essentially fully developed with a mix of residential, commercial, and industrial land uses. The Anaheim Public Utilities currently provides electricity to residents and business industry. The distribution system currently consists of over 1,200 circuit miles of transmission and distribution lines, over 700 miles of which are underground. In order to facilitate the safe and efficient transfer of electricity to residences and businesses, 14 distribution substations are located throughout the City. Anaheim obtains its electric supply from its resources located in or near Anaheim and across the western United States. To round out its electric supply, the City of Anaheim participates in seasonal power exchanges as well as additional market purchases where necessary. Telecommunication services are provided to the City through various companies including AT&T, Spectrum, Cox Communications, and Frontier. Impacts Associated with the Proposed Project: Would the project: a) Require or result in the relocation or construction of new or expanded water, wastewater treatment or stormwater drainage, electric power, natural gas, or telecommunications facilities, the construction or relocation of which could cause significant environmental effects? Water Services The total average water demand projection for build out of the General Plan is 112,043 AFY or approximately 100 mgd. These projections are consistent with the City of Anaheim's current water demand projections. The Proposed Project would connect to existing water lines and would not require additional water infrastructure to be built of expanded. According to the 2020 Urban Water Management Plan, the City anticipates being able to meet water demand with adequate supplies through the year 2045 under normal, dry, and multiple dry year conditions. The plan’s Drought Risk Assessment shows no water shortages are projected if a drought were to occur over the next five years. The maximum buildout of the Project Site, as listed in Table 3-2 of Supplemental EIR No. 346, is 139 residential units. Because the Proposed Project would have fewer residential units than analyzed in Supplemental EIR No. 346 and the Project Site is currently developed, water demand would be less than analyzed in the Certified EIRs. With the KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 100 implementation of MM 5.13-1, the proposed project would not have significant impacts related to water facilities that the Certified EIRs have not already analyzed, nor would the Proposed Project have any impacts that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate. Therefore, no further analysis is required. Wastewater Services The sewage flow projection for build-out of the General Plan totals approximately 72 mgd. This citywide sewage flow would be spread out over many tributary basins and would not constitute a significant impact. To mitigate potential impacts, each new development project is reviewed to determine if it is located within an area served by deficient sewer facilities. If so, a property owner/developer will conduct a sanitary sewer study and mitigate any identified deficiencies and participate in the Infrastructure Improvement Fee Program, if one is adopted for the area. The Proposed Project involves the demolition of two commercial office buildings and construction of 83 residential townhouse units on Housing Opportunity Sites 154 and 155. As required by MM 5.13-4, the Applicant prepared a Sewer Study (Appendix G). The proposed flow factor for townhome units is 240 gpd/du. The Proposed Project demolition of two commercial office buildings would result in a total flow decrease from the existing commercial site of 8,718 gpd. The proposed flow increase for the Proposed Project to Sunkist Street is 19,920 gpd, for a total net average daily flow increase to the downstream tributary sewer collection system of 11,202 gpd. The project flow is proposed to discharge into an 8-inch line on Sunkist Street, approximately 250 feet south of Lincoln Avenue. The sewer study demonstrates that the Proposed Project would not increase sewer flows beyond those programmed in the Combined Central Anaheim Area Master Plan of Sanitary Sewers (CCAAMPSS) and that adequate sewer flows would be maintained with implementation of the Proposed Project. The Proposed Project would not have any significant impacts related to wastewater treatment that the Certified EIRs has not already analyzed, nor would the Proposed Project have any impacts that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate. Therefore, no further analysis is required. Stormwater As discussed in Section 5.4.10, Hydrology and Water Quality, site runoff will have similar drainage patterns to the existing condition, and the Proposed Project would convey stormwater to a subsurface StormTech chamber system or bioretention basins during flooding events. Additionally, the proposed project’s BMPs and landscaping plan, which would include water- efficient irrigation systems and water conservation measures, would comply with MM 5.13-1. The proposed project would not have any significant impacts related to runoff and stormwater drainage that the Certified EIRs have not already analyzed, nor would the Proposed Project result in more significant or more severe impacts that that uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. Electricity, Natural Gas, and Telecommunications The Project Site is an urban infill site served by existing electricity, natural gas, and telecommunication facilities. Impacts associated with electricity, natural gas, and KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 101 telecommunications facilities would not be greater than those analyzed in the Certified EIRs. The proposed project would not have any significant impacts related to telecommunications facilities that the Certified EIRs have not already analyzed, nor would the Proposed Project result in more significant or more severe impacts that could not be substantially mitigated. Therefore, no further environmental analysis is required. b) Have sufficient water supplies available to serve the project and reasonably foreseeable future development during normal, dry and multiple dry years? As previously discussed, the City of Anaheim’s projected water supplies are able to meet future water demands. Additionally, the maximum buildout of the project site, as listed in Table 3-2 of the SEIR No. 346, is 139 residential units. The Proposed Project would result in the construction of 83 townhomes. Because the Proposed Project would have fewer residential units than analyzed in Supplemental EIR No. 346 and the Project Site is currently developed with office uses, water demand would be lesser than those analyzed in the Certified EIRs, and impacts associated with water facilities would not be greater than those analyzed in the Certified EIRs. The Proposed Project’s water demand would be within the projected water supply availability. The Proposed Project would not have any significant impacts related to water supply availability that the Certified EIRs have not already analyzed, nor would the proposed project have any impacts that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate. Therefore, no further analysis is required. c) Result in a determination by the wastewater treatment provider which serves or may serve the project that it has adequate capacity to serve the project’s projected demand in addition to the provider’s existing commitments? According to the Sewer Study prepared for the Proposed Project, the sewer collection system has sufficient capacity to accommodate the additional flow generated by the P roposed Project. The Proposed Project would not have any significant impacts related to wastewater that the Certified EIRs have not already analyzed, nor would the Proposed Project result in more significant or more severe impacts that uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. d) Generate solid waste in excess of State or local standards, or in excess of the capacity of local infrastructure, or otherwise impair the attainment of solid waste reduction goals? Solid Waste Services The population projections associated with build out of the General Plan are consistent with the Orange County Integrated Waste Management District (IWMD) projections and the Regional Landfill Options for Orange County (RELOOC) program. Therefore, no significant impacts are anticipated provided IWMD continues to expand landfill capacity consistent with adopted County growth projections. The maximum buildout of the project site, as listed in Table 3-2 of the Supplemental EIR No. 346, is 139 residential units. The Proposed Project would result in the construction of 83 townhomes. Because the Proposed Project would have fewer residential units than analyzed in Supplemental EIR No. 346, solid waste generation would be lesser than those analyzed in the Certified EIRs. The proposed project would not have any significant impacts related to solid waste that the Certified KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 102 EIRs have not already analyzed, nor would the Proposed Project have any impacts that are more significant than previously analyzed, or that uniformly applicable development policies would not substantially mitigate. Therefore, no further analysis is required. e) Comply with federal, State, and local management and reduction statutes and regulations related to solid waste? The Proposed Project would comply with all federal, State, and local requirements related to solid waste. The Proposed Project would not have any significant impacts related to solid waste statutes and regulations that the Certified EIRs have not already analyzed, nor would the Proposed Project result in more significant or more severe impacts that could not be substantially mitigated. Therefore, no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 Mitigation Measures: MM 5.13-1: Prior to issuance of building permits, future projects shall demonstrate compliance with the following water conservation measures to the satisfaction of the Anaheim Public Utilities Department: • Install a separate irrigation meter when the total landscaped area exceeds 2,500 square feet. (City of Anaheim Water Conservation Measures) • Use of efficient irrigation systems such as drip irrigation systems and automatic systems that include moisture sensors. (City of Anaheim Water Conservation Measures) • Use of low-flow sprinkler heads in the irrigation system. (City of Anaheim Water Conservation Measures) • Use of water-conservation landscape plant materials, wherever feasible. (City of Anaheim Water Conservation Measures) • Low-flow fittings, fixtures, and equipment including low flush toilets and urinals. (City of Anaheim Water Conservation Measures) • Use of cooling tower and waterway recirculation systems. (City of Anaheim Water Conservation Measures) • Use of water efficient ice machines, dishwashers, clothes washers, and other water using appliances. (City of Anaheim Water Conservation Measures). MM 5.13-4: Prior to approval of a final subdivision map or issuance of a grading or building permit, whichever occurs first, the City Engineer shall review the location of each project to determine if it is located within an area served by deficient sewer facilities or the Proposed Project, with peak flows provided by the property owner, will create a deficiency in an existing sewer line. If the City Engineer determines that either condition exists, the property owner/developer shall conduct a sanitary sewer study to be reviewed and approved by the City Engineer. If the project will increase sewer flows beyond those programmed in the appropriate master plan sewer study for the area or if the project currently discharges to an existing deficient KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 103 sewer system or will create a deficiency in an existing sewer line, the property owner/developer shall be required to guarantee mitigation of the impact to adequately serve the area to the satisfaction of the City Engineer and City Attorney’s Office. The property owner/developer shall be required to install the sanitary sewer facilities, as required by the City Engineer to mitigate the impacts of the proposed development based upon the applicable sewer deficiency study, prior to acceptance for maintenance of public improvements by the City or final building and zoning inspection for the building/structure, whichever occurs first. Additionally, the property owner/developer shall participate in the Infrastructure Improvement (Fee) Program, if adopted for the project area, as determined by the City Engineer, which could include fees, credits, reimbursements, or a combination thereof. The requirement for City Engineer review of sewer facilities serving each project set forth in this mitigation measure has been satisfied by the completion of the Sewer Study prepared for the project by PSOMAS., which has been reviewed and approved by the City Engineer. Sources: Appendix G – Sewer Study – 2420-2450 E. Lincon Avenue, PSOMAS, July 20, 2022. Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.13, Public Services and Facilities, Pages 5-213 to 5-250. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Appendix A, Initial Study and NOP, Page 40-41. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. City of Anaheim 2020 Urban Water Management Plan. June 2021. Available at https://www.anaheim.net/DocumentCenter/View/37199/Anaheim-2020-UWMP?bidId=. Accessed November 21, 2022. City of Anaheim Central Anaheim Master Plan of Sanitary Sewers. December 2017. Available at https://www.anaheim.net/DocumentCenter/View/20610/CAMPSS_12182017_FINAL-revised. Accessed November 21, 2022. City of Anaheim About Electric Services. https://www.anaheim.net/2104/About-Electric- Services. Accessed November 21, 2022. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 104 5.4.20 Wildfire Would the project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Substantially impair an adopted emergency response plan or emergency evacuation plan? Less than Significant ☐ ☒ b) Due to slope, prevailing winds, and other factors, exacerbate wildfire risks, and thereby expose project occupants to, pollutant concentrations from a wildfire or the uncontrolled spread of a wildfire? Less than Significant ☐ ☒ c) Require the installation or maintenance of associated infrastructure (such as roads, fuel breaks, emergency water sources, power lines or other utilities) that may exacerbate fire risk or that may result in temporary or ongoing impacts to the environment? Less than Significant ☐ ☒ d) Expose people or structures to significant risks, including downslope or downstream flooding or landslides, as a result of runoff, post-fire slope instability, or drainage changes? Less than Significant ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the impacts to wildfires related to the implementation of the General Plan and Zoning Code Update Program in the Hazards and Hazardous Materials section of the report. Refer to EIR No. 330, Section 5.6. Development in accordance with the General Plan and Zoning Code Update was determined to have a less than significant impact on hazards related to wildfire and no mitigation measures were required. EIR No. 346 affirmed the finding of less than significant impacts and stated that there were no new impacts identified requiring additional analysis as a result of implementation of the Housing Opportunity Sites Rezoning Project. Impacts Associated with the Proposed Project: The Project Site is located in an urbanized area of Anaheim bordered by urban development. The Project Site is not located adjacent to areas or lands classified as Very High Fire Hazard Severity Zone. In addition, the Project Site is an urban infill site that is not intermixed with wildlands. As KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 105 such, the Proposed Project would not subject people or structures to a significant risk of loss, injury, or death because of exposure to wildfires. The Proposed Project does not have other features with the potential to exacerbate wildfire, downstream flooding, or landslide risks. Because the Proposed Project is located in an urbanized area, it would not require the installation of maintenance of associated infrastructure that may exacerbate fire risk or result in ongoing impacts to the environment. The Proposed Project would not have any significant impacts related to wildfires that the Certified EIRs have not already analyzed, nor would the Proposed Project result in more significant or more severe impacts that uniformly applicable development policies would not substantially mitigate. Therefore, no further environmental analysis is required. Existing Programs and Policies: None Applicable MMP No. 122 and 122A Mitigation Measures: None Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. Chapter 5.6, Hazards and Hazardous Materials, Pages 5-100 to 5- 104. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. Chapter 7, CEQA Mandated Sections, Page 7-7 and Appendix A, Initial Study and NOP, Pages 37-38. City of Anaheim Housing Opportunities Sites Rezoning Project Final Supplemental Environmental Impact Report, The Planning Center/DC&E, September 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 106 5.4.21 Mandatory Findings of Significance Does the Project: EIR No. 330/346 Determination Potentially Significant Impact Not Identified in EIR No. 330/346 No New Impact/No Substantial Increase in Impact Severity a) Does the project have the potential to substantially degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, substantially reduce the number or restrict the range of a rare or endangered plant or animal or eliminate important examples of the major periods of California history or prehistory? Less than Significant ☐ ☒ b) Does the project have impacts that are individually limited, but cumulatively considerable? ("Cumulatively considerable" means that the incremental effects of a project are considerable when viewed in connection with the effects of past projects, the effects of other current projects, and the effects of probable future projects)? New information Showing Potentially New or Increased Significant Effects ☐ ☒ c) Does the project have environmental effects which will cause substantial adverse effects on human beings, either directly or indirectly? New information Showing Potentially New or Increased Significant Effects ☐ ☒ Narrative Summary: Impacts analyzed in EIR No. 330 and SEIR No. 346/No new impacts. EIR No. 330 analyzed the project’s impacts related to the implementation of the General Plan and Zoning Code Update Program. Impacts Associated with the Proposed Project: a) Does the project have the potential to substantially degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 107 substantially reduce the number or restrict the range of a rare or endangered plant or animal, or eliminate important examples of the major periods of California history or prehistory? As described in Section 5.4.4, Biological Resources, Program EIR No. 330 determined that buildout of the General Plan would result in less than significant impacts related to nesting birds with implementation of MM 5.3-3 and MM 5.3-4. These mitigation measures would require focused surveys to identify avoidance measures to protect active nests and restricting removal of nonnative trees to protect nesting birds. With implementation of these mitigation measures, it was determined that there would be no significant impacts related to the potential to substantially degrade the quality of the environment, reduce fish or wildlife habitat, reduce fish or wildlife populations below self-sustaining levels, eliminate a plant or animal community, or reduce the number or range of a rare or endangered plant or animal. As described in Section 5.4.5, Cultural Resources, Program EIR No. 330 determined that impacts related to cultural resources would be less than significant with the implementation of the General Plan Goals and Policies, existing codes and regulations, and MM 5.4-1, 5.4-2 and 5.4-3 required in MMP No. 122. As such, there would be no significant impacts related to the potential for elimination of important examples of major periods of California history or prehistory. b) Does the project have impacts that are individually limited, but cumulatively considerable? (“Cumulatively considerable” means that the incremental effects of a project are considerable when viewed in connection with the effects of past projects, the effects of other current projects, and the effects of probable future projects)? EIR No. 330 identified cumulatively considerable impacts related to air quality, noise, and traffic. Mitigation measures MM 5.2-1 through MM 5.2-6 (air quality), MM 5.10-1 and MM 5.10-2 (noise), and MM 5.15-1 through MM 5.15-8 (traffic) were required to mitigate impacts to these analysis areas. SEIR No. 346 identified cumulatively considerable impacts related to air quality, greenhouse gas emissions, noise, and traffic. Mitigation measures MM 5.2-1, MM 5.2-6, and MM 5.2-7 (air quality and greenhouse gas emissions); MM 5.10-1 (noise); and MM 5.15-4, MM 5.15- 5, MM 5.15-6, and MM 5.15-8 (traffic) were required to mitigate impacts to these analysis areas. Based on the analysis provided in Section 5.4.3, Air Quality; Section 5.4.13, Noise, and Section 5.4.17, Transportation, the Proposed Project would not substantially increase cumulative impacts related to these analysis areas. No new mitigation measures would be required. As presented throughout this Appendix N Checklist, the Proposed Project has not been found to generate new or substantially more severe environmental effects than those previously analyzed in EIR No. 330 or SEIR No. 346; therefore, there is no likelihood of the Proposed Project causing substantial adverse effects on human beings, either directly or indirectly, beyond that which was previously analyzed in the Certified EIRs. c) Does the project have environmental effects, which will cause substantial adverse effects on human beings, either directly or indirectly? Based on the descriptions and analysis presented in Sections 5.4.1 through 5.4.20 of this Appendix N, the Proposed Project would not generate new or substantially more severe environmental effects than those previously analyzed in Program EIR No. 330 or Supplemental EIR No. 346. With implementation of MM BIO-1, MM CUL-1, MM CUL-2, MM TCR-1, MM TCR-2, KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 108 MM TCR-3, MM TCR-4, MM GEO-1, MM GEO-2, and MM HAZ-1, the Proposed Project would not result in substantial adverse effects on human beings. Therefore, there is no likelihood of the Proposed Project causing substantial adverse effects on human beings, either directly or indirectly, beyond that which was previously analyzed in the Certified EIRs. Impacts would be consistent with what the Certified EIRs analyzed. Existing Programs and Policies: As identified in this analysis. Applicable MMP No. 122 and 122A Mitigation Measures: As identified in this analysis. Sources: Anaheim General Plan and Zoning Code Update Final Environmental Impact Report No. 330, The Planning Center, May 2004. City of Anaheim Housing Opportunities Sites Rezoning Project Draft Supplemental Environmental Impact Report, The Planning Center/DC&E, July 2013. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 109 6 LIST OF PREPARERS Sagecrest Planning+Environmental Laurel Reimer, Senior Project Manager Kelly Ribuffo, Project Manager Subconsultants Katie Wilson, M.S. – Ganddini Group Catherine Howe, M.S. – Ganddini Group Brian F. Smith – Brian F. Smith and Associates, Inc. Reza Saberi, GE – NMG Geotechnical, Inc. Terri Wright, CEG - NMG Geotechnical, Inc. Shilpa Sunil – Hillman Consulting, LLC Ryan Terwilliger – Millman Consulting, LLC Joshua Williams – Hillman Consulting, LLC Davis Tang – Hillman Consulting, LLC Jayne Janda-Timba – Rick Engineering Mike Swan - PSOMAS Roma Stromberg, INCE, M.S. – Ganddini Group Perrie Ilerchil, PE – Ganddini Group Giancarlo Ganddini – Ganddini Group City Staff Planning Services Division Heather Allen, Principal Planner Public Works Development Services Division Naiim Khoury, Consultant 7 REFERENCES Assembly Bill 32: Global Warming Solutions Act. 2006. Available at: http://www.arb.ca.gov/cc/ab32/ab32.htm. California Air Pollution Control Officers Association (CAPCOA). CEQA & Climate Change. January 2008. California Department of Conservation (DOC). Agricultural Preserves 2010 Status Report, Williamson Act Parcels, Orange County, California. Available at: http://www.conservation.ca.gov/dlrp/lca/stats_reports/Documents/2010%20Williamson%20A ct%20Status%20Report.pdf DOC. Farmland Mapping and Monitoring Program Map for Orange County. DOC. Seismic Hazard Zones Map, Orange 7.5-Minute Quadrangle. April 15, 1998. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 110 California Department of Fish and Wildlife (CDFW). Natural Community Conservation Plan and Habitat Conservation Plan for the County of Orange Central and Coastal Sub-region. 1996. Available at: https://www.wildlife.ca.gov/Conservation/Planning/NCCP/Plans/Orange-Coastal. California Department of Toxic Substances Control. Cortese List. Available at: http://www.dtsc.ca.gov/SiteCleanup/Cortese_List.cfm. Accessed November 20, 2022. California Department of Transportation. Eligible (E) and Officially Designated (OD) [Scenic Highway] Routes. Available at: http://www.dot.ca.gov/hq/LandArch/scenic/cahisys.htm. California Geologic Survey. Special Publication 117A, Guidelines for Evaluating and Mitigating Seismic Hazards in California. City of Anaheim. 2020 Urban Water Management Plan. June 2021. Available at https://www.anaheim.net/DocumentCenter/View/37199/Anaheim-2020-UWMP?bidId=. Accessed November 21, 2022. City of Anaheim. About Electric Services. https://www.anaheim.net/2104/About-Electric- Services. Accessed November 21, 2022. City of Anaheim. Anaheim Outdoors Connectivity Plan. April 2013. City of Anaheim. Central Anaheim Master Plan of Sanitary Sewers. December 2017. Available at https://www.anaheim.net/DocumentCenter/View/20610/CAMPSS_12182017_FINAL-revised. Accessed November 21, 2022. City of Anaheim. Citywide Historic Preservation Plan. May 2010. Available at: http://www.anaheim.net/planning/aRT/PlanCouncil-May2010.pdf. City of Anaheim. Criteria for Preparation of Traffic Impact Studies. City of Anaheim. General Plan Circulation Element Green Element: Mineral Resource Map Noise Element. Pg. N-9 City of Anaheim. General Plan and Zoning Code Update Environmental Impact Report No. 330. May 25, 2004. City of Anaheim. Municipal Code. 1974; updated as recently as February 2013. City of Anaheim. Sewer Capacity Map. National Center for Education Statistics. 2022. https://nces.ed.gov/ccd/schoolsearch/index.asp. Accessed November 21, 2022. Orange County Public Works. Drainage Area Management Plan. 2003. Orange County Transportation Authority. Orange County Congestion Management Plan. 2011. Senate Bill 375: Sustainable Communities and Climate Protection Act of 2008. 2008. Available at: http://www.leginfo.ca.gov/pub/07-08/bill/sen/sb_0351- 0400/sb_375_bill_20080930_chaptered.pdf. KB Home Lincoln & Sunkist Townhomes Project Appendix N Checklist Page | 111 Southern California Air Quality Management District (SCAQMD). 2007 Air Quality Management Plan. Available at: http://www.aqmd.gov/home/library/clean-air-plans/air-quality-mgt- plan/2007-air-quality-management-plan. SCAQMD. Rule 403, Fugitive Dust. Amended June 3, 2005. Available at: http://www.aqmd.gov/docs/default-source/rule-book/rule-iv/rule-403.pdf?sfvrsn=4. State of California, Governor’s Office of Planning and Research. CEQA and Climate Change: Addressing Climate Change Through California Environmental Quality Act (CEQA) Review. June 19, 2008. Pg. 4. United States Environmental Protection Agency (US EPA). Federal Water Pollution Control Act (known as the Clean Water Act). November 27, 2002. KB Home Lincoln & Sunkist Townhomes KB Home Lincoln & Sunkist Townhomes Project Project Description Location: 2420 and 2450 Lincoln Avenue Anaheim, CA 92806 APNs: 083-731-18, 083-731-19 Applicant: KB Home Attn: John Abboud 9915 Mira Mesa Blvd, Suite 100 San Diego, CA 92614 Phone: (858) 877-4267 Email: jabboud@kbhome.com Representative: Sagecrest Planning+Environmental Attn: Laurel Reimer 27128 Paseo Espada, Suite 1524 San Juan Capistrano, CA 92675 Phone: 714-783-1863 Email: lreimer@sagecrestplanning.com Owner: Albert & Sons Real Estate I, LLC P.O. Box 12738 Newport Beach, CA 92658 Project Request: The request is for a Conditional Use Permit and Tentative Tract Map to allow the construction of a multi-family, for-sale residential townhome community. While Chapter 18.34 of the Anaheim Municipal Code allows for by-right housing development in the Residential Opportunity (RO) Overlay Zone, a Conditional Use Permit is requested as allowed under AMC 18.06.160.030 to reduce the setbacks along Sunkist Avenue and to reduce the building-to-building setbacks. Site Description: The site is located at the southwest corner of East Lincoln Avenue and Sunkist Street with a street address of 2420 and 2450 Lincoln Avenue (Project Site). The site consists of two parcels with Assessor’s Parcel Numbers (APNs) 083-731-18 and -19. The trapezoid shaped site totals 4.01 acres in size and measures approximately 615’ wide and varies from roughly 345’ to 182’ deep. The site is improved with two office buildings formerly occupied by the Employment Development Department of the State of California. The site is zoned for General Commercial but has a General Plan Land Use designation of Residential-Medium with a Residential Opportunity (RO) Overlay. Single family homes are located immediately south of the site and across Lincoln Avenue to the north. A two-story multifamily development is located immediately to the west. A Mobil gas station and one- and two-story multifamily developments are located to the east across Sunkist Street. ATTACHMENT NO. 4 KB Home Lincoln & Sunkist Townhomes Lincoln Avenue is designated as a Primary Arterial and Sunkist Street is a Secondary Arterial by the Circulation Element of the General Plan. Proposal: KB Home proposes to demolish all existing site improvements in order to construct 83 for-sale, 3- story townhomes at a density of 21.3 dwelling units/acre. The project will consist of 10 buildings and five product types. The project’s unit breakdown is as follows: Product Type # of Units Bed/Bath Size (SF) Total Size (SF) Plan I 34 2/2.5 1,415 48,110 Plan 2 14 3/2.5 1,460 20,440 Plan 3 10 3/3.5 1,800 18,000 Plan 4 8 4/3.5 1,761 14,088 Plan 5 17 4/3.5 1,834 31,178 Total: 83 Units and 131,816 SF The project will implement the development standards set forth in the Multiple Family (RM-3.5) Residential Zone: Development Standard RM 3.5 Requirement Provided Comments Density 0-27.2 du/acre 21.3 du/acre Building Height 40’ 39’-6” Minimum Floor Area 2-Bedroom = 825 SF 3-Bedroom = 1,000 SF 4-Bedroom = 1,200 SF 2-Bedroom = 1,415 SF 3-Bedroom = 1,460 SF 4-Bedroom = 1,761 SF Site Coverage 50% 33% Structural Setbacks North = 20’ South = 55’ East = 20’ West = 20’ North = 15’ – 38’ South = 55’ East = 10’ West = 47’ Provides 23’ average Modification requested Building to Building 40’ 15’ Modification requested Recreation Area 275 SF/unit = 22,825 SF 24,852 SF Storage Area 100 SF/unit 100 SF/unit Parking 237 238 Each townhome will be provided with an attached two-car garage with overhead storage space. An additional 72 surface parking stalls along the interior property lines will bring the total on-site parking to 238 parking spaces. The project will provide a total of 24,852 square feet of recreation- leisure area, including 15,627 square feet of common open space featuring a tot lot, community barbeques, seating area, dog park, and community garden. The remainder of the common open space will be provided in landscaped areas and walkways. In addition to the common open space, each unit will have a private deck varying from 70 to 90 square feet in size and 19 units will have private patios. In total, the project will provide 9,225 square feet of private open space. KB Home Lincoln & Sunkist Townhomes The four buildings with frontages along Lincoln Avenue and Sunkist Street will have a height of 39’- 6” and the six interior buildings will have a height of 39’. The unit entryways along Lincoln Avenue and Sunkist Street will have a grade differential to create a stoop-type entry. The entryways along Lincoln will also include a 3’-tall fence to create an additional buffer from the street. Site access will be provided by one driveway on Lincoln Avenue and one driveway on Sunkist Street. A 24-foot-wide drive aisle will encircle the project and provide garage access for 42 units. Four 20’- wide and up to 140.7’-deep alleyways will provide garage access for 41 units. The alleyways will feature landscaping and multi-colored pavement in a wave design. The project will require between 4 feet and 11 feet of dedication along Lincoln Avenue to achieve ultimate right-of-way width. It will also require reconstruction of all sidewalks and the addition of a 5’-wide landscaped parkway. Modification Requests The project proposes to reduce the structural setbacks along the Sunkist Street frontage from 20’ to 10’. Additionally, the project proposes to reduce the setback between buildings from 40’ to 15’. These adjustments are being requested pursuant to AMC § 18.06.160.030, which allows modifications to be approved in order to achieve a good project design, privacy, livability, and compatibility with surrounding uses. Pedestrian orientation and increased walkability are hallmarks of livable communities. The project will eliminate the existing large parking lot and out-of-scale box buildings with a new residential development. The project will adjust the sidewalks away from the street, provide a new landscaped parkway, and provide stooped entries to contribute to the pedestrian orientation of the area, encourage walkability, and promote community interaction. Reducing the setbacks will allow for an enhanced project design that includes large open space areas, walkable paths between the buildings, and a site layout that accommodates forward movement of all vehicles throughout the property. Accommodation for pedestrian safety and unobstructed vehicle movement has been taken into consideration. Reduction of the Sunkist Street setback allows the buildings to be placed further from the adjoining residential developments along the southern and western property lines. The use of enhanced landscaping along these property lines will minimize any potential privacy impact that the project would have on adjoining neighbors. The buildings will feature attractive and enhanced architectural elements including façade articulation, height variation, contrasting colors and materials, and dense landscaping in the setback and pedestrian access areas. The alleyways providing garage access for 41 of the units will feature landscaping and multi-colored pavement in a wave design to give the impression that the alleys are an extension of the common open space. While not counted towards the open space requirement, these enhanced alleyways will provide over 10,000 square feet of additional common space for neighbors to play, socialize and engage with each other. KB Home Lincoln & Sunkist Townhomes Additionally, reducing the setbacks will allow the development to incorporate larger bedroom counts. These 4-bedroom dwelling units will accommodate the needs of larger families and reduce incidents of overcrowding in the existing housing stock. Surrounding land uses include single-family and multiple-family dwelling units. The primary exception is the gas station with mini mart, located on the southeast corner of Lincoln Avenue and Sunkist Street, and the quick lube and car wash located on the northeast corner of Lincoln Avenue and Sunkist Street. These types of businesses are intended to be at a neighborhood scale and serve those who live and work in the immediate vicinity. The placement of 83 new dwelling units will not only be compatible with surrounding residential uses, but with the neighborhood scale businesses. We respectfully request review of this application. Should you have any questions regarding this request, please feel free to contact me at (714) 931-9655 or lreimer@sagecrestplanning.com. Sincerely, Laurel Reimer Senior Project Manager Sagecrest Planning+Environmental 5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:NOVEMBER 8, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESSHEET INDEXA-1 COVER SHEETA-2 SITE PLANA-3 CIRCULATION EXHIBITA-4 TRASH EXHIBITA-5 FIRE EXHIBITA-6 OPEN SPACE EXHIBITA-7 SHADOW STUDYA-8 UNIT PLANSA-9 UNIT PLANSA-10 UNIT PLANSA-11 UNIT PLANSA-12 BUILDING AA-13 BUILDING A ELEVATIONSA-14 BUILDING BA-15 BUILDING B ELEVATIONSA-16 BUILDING CA-17 BUILDING C ELEVATIONSA-18 BUILDING DA-19 BUILDING D ELEVATIONSA-20 BUILDING EA-21 BUILDING E ELEVATIONSA-22 BUILDING FA-23 BUILDING F ELEVATIONSA-24 PERSPECTIVESA-25 PERSPECTIVESCOVER SHEETA-1ATTACHMENT NO. 5 LINCOLN AVENUES SUNKIST STREET TOT LOTCOMMUNITY GARDENDOGPARK1F2E3E4E5A6D7B8A9A10CAMUAMUAMUAMUAMUAMUAMUAMUAMU24.0'24.0'DRIVEAISLE15.0'15.0'55.0'SETBACK18.0'10.0'5.9'22.1'5.0'LANDSCAPEBUFFER18.0'20.0'REQ. AVG.SETBACK24.0'DRIVEAISLE11.0'103.0'13.0'28.0'18.0'10.0' LANDSCAPE BUFFER24.0'DRIVE AISLE70.5'64.0'140.7'20.0'ALLEY20.0'ALLEY17.5'24.2'15.0'38.0'15.0'30.4'23.1'20.0'ALLEYR20.0'R20.0'R20.0'R20.0'24.0'DRIVEAISLEBACKFLOWPREVENTERBACKFLOWPREVENTERFEV10.0'SETBACKMAILBOXES14.1'23.0'PROP. AVG.SETBACKEXISTINGWALL TOREMAINEXISTING WALL TO REMAINREFER TO LANDSCAPE FORMORE DETAIL36" HT FENCE AT PATIOSALONG LINCOLN. TYP.REFER TO LANDSCAPE PLANSMECHANICAL EQUIPMENT TO BESCREENED FROM PUBLIC VIEW.REFER TO LANDSCAPE PLANS.42.6'32.1'R3-5(R) SIGNAGERIGHT TURN IN/OUT ONLYR3-5(R) SIGNAGERIGHT TURN IN/OUT ONLY33.7'GARAGESPEED BUMPS TYP. AT COURTS18.0'9.0'TYPICAL PARKING DIMENSIONSNOT TO SCALE9.0'9.0'2.0'PER STANDARD DETAIL 4702.0'2.0'2.0'4" STRIPING5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:NOVEMBER 8, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESCONCEPTUAL SITE PLAN0 15 30 60NA-2PROJECT SUMMARY3-STORY TH & CARRIAGESHOMES83 RESIDENCESAREA4.0 ACRESNET AREA3.9 ACRESDENSITY21.3 DU/ACLOT COVERAGE 33%PRODUCT MIXCARRIAGES34 PLAN 1 2B/2.4B 1,415 S.F.14 PLAN 2 3B/2.5B 1,460 S.F.10 PLAN 3 3B/3.5B 1,800 S.F.58 SUBTOTALTOWNHOMES 8 PLAN 4 4B/3.5B 1,761 S.F.17 PLAN 5 4B/3.5B 1,834 S.F.25 SUBTOTAL83 TOTAL UNITS PARKING REQUIRED2BD 34 X 2.25 77 SPACES3BD 24 X 3 72 SPACES4BD 25 X 3.5 88 SPACESTOTAL237 SPACESPARKING PROVIDEDGARAGES166ON SITE 72TOTAL238 SPACESEV PARKING238 SPACES X 10% = 24 FUTURE EV SPACESFRONT SETBACK ALONG LINCOLNREQUIRED20 FT AVERAGEPROVIDED23 FT AVERAGELEGENDBUILDING NUMBERBUILDING TYPE AMU ACCESSIBLE MULTISTORY UNIT FEV FUTURE EV SPACE8A7' X 50' SIGHT TRIANGLE25' X 25' SIGHT TRIANGLEDECORATIVE STAMPEDASPHALT CONCRETE PAVEMENTSPEED BUMP LINCOLN AVENUES SUNKIST STREET TOT LOTCOMMUNITY GARDENDOGPARK1F2E3E4E5A6D7B8A9A10CAMUAMUAMUAMUAMUAMUAMUAMUAMU*********24.0'24.0'DRIVEAISLE15.0'15.0'55.0'SETBACK18.0'10.0'5.9'22.1'5.0'LANDSCAPEBUFFER18.0'20.0'REQ. AVG.SETBACK24.0'DRIVEAISLE11.0'103.0'13.0'28.0'18.0'10.0' LANDSCAPE BUFFER24.0'DRIVE AISLE70.5'64.0'140.7'20.0'ALLEY20.0'ALLEY17.5'24.2'15.0'38.0'15.0'30.4'23.1'20.0'ALLEYR20.0'R20.0'R20.0'R20.0'24.0'DRIVEAISLEBACKFLOWPREVENTERBACKFLOWPREVENTERFEV10.0'SETBACKMAILBOXES14.1'23.0'PROP. AVG.SETBACKEXISTINGWALL TOREMAINEXISTING WALL TO REMAINREFER TO LANDSCAPE FORMORE DETAIL36" HT FENCE AT PATIOSALONG LINCOLN. TYP.REFER TO LANDSCAPE PLANSMECHANICAL EQUIPMENT TO BESCREENED FROM PUBLIC VIEW.REFER TO LANDSCAPE PLANS.42.6'32.1'R3-5(R) SIGNAGERIGHT TURN IN/OUT ONLYR3-5(R) SIGNAGERIGHT TURN IN/OUT ONLY33.7'GARAGESPEED BUMPS TYP. AT COURTSPLANTERSTYP.DECORATIVECOLOREDCONCRETEUNITENTRYUNITENTRYUNITENTRYDRIVE AISLEBOLLARDSUNITENTRYUNITENTRYUNITENTRYAC UNITTYP.20.0'ALLEY20.0'OVERHANG35.3'GARAGE TO GARAGE28.5'GARAGE TO GARAGE21.5'OVERHANG29.5'OVERHANGUNITENTRYUNITENTRYUNITENTRYUNITENTRYAMU**AMUSPEEDBUMP5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:NOVEMBER 8, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESCIRCULATION EXHIBIT0 15 30 60NA-3LEGENDPATH OF TRAVELVEHICULAR CIRCULATIONPEDESTRIAN ACCESSACCESSIBLE THRESHOLD7' X 50' SIGHT TRIANGLE25' X 25' SIGHT TRIANGLE AMU ACCESSIBLE MULTISTORY UNIT 10% OF 83 DU = 9 UNITS (PLAN 3)DECORATIVE STAMPED ASPHALT CONCRETE PAVEMENTSPEED BUMPBUILDING NUMBERBUILDING TYPETYPICAL COURT*8A LINCOLN AVENUES SUNKIST STREET TOT LOTCOMMUNITY GARDENDOGPARK1F2E3E4E5A6D7B8A9A10C(54 BINS)(9 BINS)(12 BINS)(12 BINS)(12 BINS)(9 BINS)(12 BINS)(12 BINS)(6 BINS)(12 BINS)AMUAMUAMUAMUAMUAMUAMUAMUAMU24.0'24.0'DRIVEAISLE15.0'15.0'55.0'SETBACK18.0'10.0'5.9'22.1'5.0'LANDSCAPEBUFFER18.0'20.0'REQ. AVG.SETBACK24.0'DRIVEAISLE11.0'103.0'13.0'28.0'18.0'10.0' LANDSCAPE BUFFER24.0'DRIVE AISLE70.5'64.0'140.7'20.0'ALLEY20.0'ALLEY17.5'24.2'15.0'38.0'15.0'30.4'23.1'20.0'ALLEYR20.0'R20.0'R20.0'R20.0'24.0'DRIVEAISLEBACKFLOWPREVENTERBACKFLOWPREVENTERFEV10.0'SETBACKMAILBOXES14.1'23.0'PROP. AVG.SETBACKEXISTINGWALL TOREMAINEXISTING WALL TO REMAINREFER TO LANDSCAPE FORMORE DETAIL36" HT FENCE AT PATIOSALONG LINCOLN. TYP.REFER TO LANDSCAPE PLANS(57 BINS)(15 BINS) (15 BINS) (12 BINS)MECHANICAL EQUIPMENT TO BESCREENED FROM PUBLIC VIEW.REFER TO LANDSCAPE PLANS.42.6'32.1'R3-5(R) SIGNAGERIGHT TURN IN/OUT ONLYR3-5(R) SIGNAGERIGHT TURN IN/OUT ONLY33.7'GARAGESPEED BUMPS TYP. AT COURTS5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:NOVEMBER 8, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESTRASH EXHIBIT0 15 30 60NA-4LEGENDRED CURB FOR TRASH PICK UPTRASH BINS - STORAGE LOCATIONTRASH BINS - COLLECTION LOCATIONTRASH TRUCK ROUTETRASH SUMMARY83 RESIDENCES X 3 BINS = 249 TOTAL TRASH BINS LINCOLN AVENUES SUNKIST STREET TOT LOTCOMMUNITY GARDENDOGPARK1F2E3E4E5A6D7B8A9A10CAMUAMUAMUAMUAMUAMUAMUAMUAMU24.0'24.0'DRIVEAISLE15.0'15.0'55.0'SETBACK18.0'10.0'5.9'22.1'5.0'LANDSCAPEBUFFER18.0'20.0'REQ. AVG.SETBACK24.0'DRIVEAISLE11.0'103.0'13.0'28.0'18.0'10.0' LANDSCAPE BUFFER24.0'DRIVE AISLE70.5'64.0'140.7'20.0'ALLEY20.0'ALLEY17.5'24.2'15.0'38.0'15.0'30.4'23.1'20.0'ALLEYR20.0'R20.0'R20.0'R20.0'24.0'DRIVEAISLEBACKFLOWPREVENTERBACKFLOWPREVENTERFEV10.0'SETBACKMAILBOXES14.1'23.0'PROP. AVG.SETBACKEXISTINGWALL TOREMAINEXISTING WALL TO REMAINREFER TO LANDSCAPE FORMORE DETAIL36" HT FENCE AT PATIOSALONG LINCOLN. TYP.REFER TO LANDSCAPE PLANSMECHANICAL EQUIPMENT TO BESCREENED FROM PUBLIC VIEW.REFER TO LANDSCAPE PLANS.42.6'32.1'R3-5(R) SIGNAGERIGHT TURN IN/OUT ONLYR3-5(R) SIGNAGERIGHT TURN IN/OUT ONLY33.7'GARAGESPEED BUMPS TYP. AT COURTS5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:NOVEMBER 8, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRE EXHIBIT0 15 30 60NA-5LEGENDVEHICULAR CIRCULATIONFIRE ACCESS ROADFIRE HYDRANT 21'-0" x 20'-0"GARAGE24'-312"24'-1012"TRR100 CU FT HANGING STORAGE 8.5' X 18' CLEAR PARKING SPACE8.5' X 18' CLEAR PARKING SPACE17'-0"18'-0"ORGDECK22'-0" x 13'-0"GREAT ROOM7'-0"10'-3"29'-10"24'-1012"12'-0" x 14'-0"KITCHENPDR24'-1012"29'-10"11'-0" x 15-0"MSTR BDRM11'-6" x 12'-6"BEDROOMW/DBABA26'-4"21'-9"20'-0" x 20'-0"GARAGETRR100 CU FT HANGING STORAGE 8.5' X 18' CLEAR PARKING SPACE8.5' X 18' CLEAR PARKING SPACE17'-0"18'-0"ORG30'-7"24'-7"12'-0" x 15'-0"KITCHEN21'-0" x 14'-0"GREAT ROOMPDRDECK8'-412"8'-4"30'-7"24'-7"10'-6" x 13-0"MSTR BDRM11'-0" x 10'-6"BEDROOM10'-0" x 10'-0"BEDROOMBABAW/DPLAN 1: 2BD/2.5BA1ST FLR - 51 S.F.2ND FLR- 648 S.F.3RD FLR- 716 S.F.TOTAL 1,415 S.F.DECK 72 S.F.GARAGE 509 S.F.PLAN 2: 3BD/2.5BA1ST FLR - 67 S.F.2ND FLR- 664 S.F.3RD FLR- 729 S.F.TOTAL 1,460 S.F.DECK 70 S.F.GARAGE 486 S.F.5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORUNIT PLANSA-8FIRST FLOORSECOND FLOORTHIRD FLOOR0 4 8 12 22'-0" x 20'-0"GARAGE9'-6" x 11'-0"BEDROOM33'-112"22'-11"TRR100 CU FT HANGING STORAGE 17'-0"18'-0"8.5' X 18' CLEAR PARKING SPACE8.5' X 18' CLEAR PARKING SPACEORGPLAN 3: 3BD/3.5BA1ST FLR - 295 S.F.2ND FLR- 803 S.F.3RD FLR- 702 S.F.TOTAL 1,800 S.F.DECK 70 S.F.GARAGE 469 S.F.PDR24'-0" x 14'-0"GREAT ROOM12'-0" x 12'-0"KITCHEN25'-10"36'-0"DECK9'-412"7'-6"W/D11'-0" x 12'-6"BEDROOM13'-6" x 11-6"MSTR BDRMBAMSTR BA25'-10"29'-10"5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORUNIT PLANSA-90 4 8 12 12'-0" x 10'-0"BEDROOM37'-7"20'-8"20'-0" x 20'-0"GARAGETRR100 CU FTHANGING STOR.8.5' X 18' CLEAR PARKING SPACE 8.5' X 18' CLEAR PARKING SPACE 17'-0"18'-0"ORGBAPLAN 4: 4BD/3.5BA1ST FLR - 298 S.F.2ND FLR- 715 S.F.3RD FLR- 748 S.F.TOTAL 1,761 S.F.DECK 90 S.F.GARAGE 461 S.F.DECKPDRW/D16'-0" x 13'-0"LIVING16'-0" x 9'-0"DINING16'-0" x 9'-0"KITCHEN20'-8"40'-1" 7'-0"13'-912"11'-0" x 12-6"MSTR BDRM10'-0" x 11'-0"BEDROOM10'-0" x 10'-0"BEDROOM20'-8"40'-1"BABA5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORUNIT PLANSA-100 4 8 12 12'-0" x 10'-0"BEDROOM20'-8"39'-6" 37'-7" 1'-11"20'-0" x 20'-0"GARAGETRR100 CU FT HANGING STOR.8.5' X 18' CLEAR PARKING SPACE 8.5' X 18' CLEAR PARKING SPACE 17'-0"18'-0"ORGBAPLAN 5: 4BD/3.5BA1ST FLR - 316 S.F.2ND FLR- 743 S.F.3RD FLR- 775 S.F.TOTAL 1,834 S.F.DECK 86 S.F.GARAGE 461 S.F.10'-0" x 15'-0"KITCHEN10'-0" x 14'-0"DINING16'-0" x 16'-0"LIVINGPDRDECK20'-8"41'-6" 7'-912"10'-11"40'-1" 1'-11" 5B WINDOW LOCATIONS OCCURS ONLY AT END CONDITIONS 5C WINDOW LOCATIONS OCCURS ONLY AT END CONDITIONS 15'-0"SEPARATION BETWEEN BUILDINGSPLAN 5AINTERIOR CONDITIONPLAN 5BEND CONDITIONPLAN 5CEND CONDITIONW/D12'-0" x 14-0"MSTR BDRM10'-0" x 11'-6"BEDROOM10'-0" x 10'-0"BEDROOMLINEN20'-8"39'-7"40'-1"BABA15'-0"SEPARATION BETWEEN BUILDINGS5B WINDOW LOCATIONSOCCURS ONLY AT END CONDITIONS5C WINDOW LOCATIONSOCCURS ONLY AT END CONDITIONSPLAN 5AINTERIOR CONDITIONPLAN 5BEND CONDITIONPLAN 5CEND CONDITION5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORUNIT PLANSA-110 4 8 12 PLAN 1PLAN 1PLAN 1 PLAN 1PLAN 1 PLAN 1PLAN 3PLAN 3PLAN 2PLAN 2130'-1112"49'-4"4'-312"3'-812"4'-312"3'-812"4'-312"3'-812"3'-812"4'-312"3'-812"4'-312"3'-812"4'-312"PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 3PLAN 3PLAN 2PLAN 2PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 3PLAN 3PLAN 2PLAN 2VALLEYRIDGE4:12VALLEYVALLEY4:12HIP HIP5:12 5:125:12SOLARREADYAREA600 SFSOLARREADYAREA600 SFSOLAR READY AREAREQUIRED = 7,944 SF X 15% = 1192 SFPROVIDED = 1200 SF5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORBUILDING AA-120 8 16 24 ROOF PLANSCALE: 1/16" = 1'-0" 39'-0"162873916287395416287395415287394MATERIAL SCHEDULE1 ROOF - CONCRETE TILE2 FASCIA - 2X RESAWN WOOD3 WALL - STUCCO4 TRIM - 2X STUCCO OVER5 METAL RAILING6 DECORATIVE SHUTTERS7 DECORATIVE GABLE ACCENT8 DECORATIVE FOAM EAVE9 EXTERIOR LIGHTING(CHATHAM 89273BLE-46)GARAGEGARAGEGREAT ROOMGREAT ROOMBEDROOMBEDROOM9'-1"8'-1"9'-1"100 CU FTHANGINGSTORAGE100 CU FTHANGINGSTORAGE7'-0"5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFRONTBUILDING A ELEVATIONSA-130 8 16 24 LEFTREARRIGHTTYPICAL SECTION PLAN 1PLAN 1PLAN 1 PLAN 1PLAN 1 PLAN 1PLAN 2PLAN 2PLAN 2PLAN 2120'-412"52'-10"4'-312"3'-812"4'-312"3'-812"4'-312"3'-812"3'-812"4'-312"3'-812"4'-312"3'-812"4'-312"PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 2PLAN 2PLAN 2PLAN 2PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 2PLAN 2PLAN 2PLAN 2RIDGE4:12 VALLEYHIPHIPVALLEYVALLEYVALLEY4:12 5:125:125:125:12 SOLARREADYAREA600 SFSOLARREADYAREA600 SFSOLAR READY AREAREQUIRED = 7,925 SF X 15% = 1188 SFPROVIDED = 1200 SF5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORBUILDING BA-140 8 16 24 ROOF PLANSCALE: 1/16" = 1'-0" 39'-0"1528739416287395416287395415287394MATERIAL SCHEDULE1 ROOF - CONCRETE TILE2 FASCIA - 2X RESAWN WOOD3 WALL - STUCCO4 TRIM - 2X STUCCO OVER5 METAL RAILING6 DECORATIVE SHUTTERS7 DECORATIVE GABLE ACCENT8 DECORATIVE FOAM EAVE9 EXTERIOR LIGHTING(CHATHAM 89273BLE-46)9'-1"8'-1"9'-1"GARAGEGARAGEGREAT ROOMGREAT ROOMBEDROOMBEDROOM5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFRONTBUILDING B ELEVATIONSA-150 8 16 24 LEFTREARRIGHTTYPICAL SECTION PLAN 1PLAN 1PLAN 1 PLAN 1PLAN 1 PLAN 1PLAN 3PLAN 3PLAN 3PLAN 3141'-612"49'-4"4'-312"3'-812"4'-312"3'-812"4'-312"3'-812"3'-812"4'-312"3'-812"4'-312"3'-812"4'-312"PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 3PLAN 3PLAN 3PLAN 3PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 1PLAN 3PLAN 3PLAN 3PLAN 3RIDGE4:12VALLEYVALLEY4:12 HIPHIP5:125:12SOLARREADYAREA600 SFSOLARREADYAREA600 SFSOLAR READY AREAREQUIRED = 7,962 SF X 15% = 1195 SFPROVIDED = 1200 SF5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORBUILDING CA-160 8 16 24 ROOF PLANSCALE: 1/16" = 1'-0" 39'-0"162873912873954128739541628739MATERIAL SCHEDULE1 ROOF - CONCRETE TILE2 FASCIA - 2X RESAWN WOOD3 WALL - STUCCO4 TRIM - 2X STUCCO OVER5 METAL RAILING6 DECORATIVE SHUTTERS7 DECORATIVE GABLE ACCENT8 DECORATIVE FOAM EAVE9 EXTERIOR LIGHTING(CHATHAM 89273BLE-46)GARAGEGARAGEGREAT ROOMGREAT ROOMBEDROOMBEDROOM9'-1"8'-1"9'-1"100 CU FTHANGINGSTORAGE100 CU FTHANGINGSTORAGE7'-0"5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFRONTBUILDING C ELEVATIONSA-170 8 16 24 LEFTREARRIGHTTYPICAL SECTION PLAN 1PLAN 1PLAN 1 PLAN 1PLAN 2PLAN 2PLAN 2PLAN 295'-4"52'-10"4'-312"3'-812"4'-312"3'-812"3'-812"4'-312"3'-812"4'-312"PLAN 1PLAN 1PLAN 1PLAN 1PLAN 2PLAN 2PLAN 2PLAN 2PLAN 1PLAN 1PLAN 1PLAN 1PLAN 2PLAN 2PLAN 2PLAN 2RIDGE4:12 VALLEYHIPHIPVALLEYVALLEYVALLEY4:125:125:125:125:12 SOLARREADYAREA500 SFSOLARREADYAREA500 SFSOLAR READY AREAREQUIRED = 6,384 SF X 15% = 957 SFPROVIDED = 1000 SF5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORBUILDING DA-180 8 16 24 ROOF PLANSCALE: 1/16" = 1'-0" 39'-0"1528739416287395416287395415287394MATERIAL SCHEDULE1 ROOF - CONCRETE TILE2 FASCIA - 2X RESAWN WOOD3 WALL - STUCCO4 TRIM - 2X STUCCO OVER5 METAL RAILING6 DECORATIVE SHUTTERS7 DECORATIVE GABLE ACCENT8 DECORATIVE FOAM EAVE9 EXTERIOR LIGHTING(CHATHAM 89273BLE-46)9'-1"8'-1"9'-1"GARAGEGARAGEGREAT ROOMGREAT ROOMBEDROOMBEDROOM5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFRONTBUILDING D ELEVATIONSA-190 8 16 24 LEFTREARRIGHTTYPICAL SECTION PLAN 5APLAN 4PLAN 4PLAN 5APLAN 5BPLAN 5C39'-6"124'-8"PLAN 5CPLAN 5APLAN 5APLAN 5BPLAN 4PLAN 4PLAN 5BPLAN 5APLAN 5APLAN 5CPLAN 4PLAN 4RIDGE4:12 4:124:12 4:124:12 RIDGERIDGEVALLEY VALLEYVALLEYVALLEYVALLEY SRA80 SFSRA335 SFSRA335 SFSRA80 SFSOLAR READY AREAREQUIRED = 5,490 SF X 15% = 824 SFPROVIDED = 830 SF5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORBUILDING EA-200 8 16 24 ROOF PLANSCALE: 1/16" = 1'-0" 39'-6"1528739461112MATERIAL SCHEDULE1 ROOF - CONCRETE TILE2 FASCIA - 2X RESAWN WOOD3 WALL - STUCCO4 TRIM - 2X STUCCO OVER5 METAL RAILING6 DECORATIVE SHUTTERS7 DECORATIVE AWNING8 DECORATIVE GABLE ACCENT9 DECORATIVE RAFTER TAILS10 DECORATIVE METAL GRILLE11 DECORATIVE CORBEL12 EXTERIOR LIGHTING (CHATHAM 89273BLE-46)128396128396152839411129'-1"9'-1"9'-1"GARAGEGREAT ROOMBEDROOM5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFRONTBUILDING E ELEVATIONSA-210 8 16 24 LEFTREARRIGHTTYPICAL SECTION PLAN 5APLAN 4PLAN 4PLAN 5APLAN 5BPLAN 5C39'-6"145'-6"PLAN 5APLAN 5CPLAN 5APLAN 5APLAN 5BPLAN 4PLAN 4PLAN 5APLAN 5BPLAN 5APLAN 5APLAN 5CPLAN 4PLAN 4PLAN 5ARIDGE4:12 4:124:12 4:124:12 RIDGERIDGEVALLEY VALLEYVALLEYVALLEYVALLEYSRA270 SFSRA630 SFSRA80 SFSOLAR READY AREAREQUIRED = 6,383 SF X 15% = 957 SFPROVIDED = 980 SF5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFIRST FLOORSECOND FLOORTHIRD FLOORBUILDING FA-220 8 16 24 ROOF PLANSCALE: 1/16" = 1'-0" 39'-6"15287394612MATERIAL SCHEDULE1 ROOF - CONCRETE TILE2 FASCIA - 2X RESAWN WOOD3 WALL - STUCCO4 TRIM - 2X STUCCO OVER5 METAL RAILING6 DECORATIVE SHUTTERS7 DECORATIVE AWNING8 DECORATIVE GABLE ACCENT9 DECORATIVE RAFTER TAILS10 DECORATIVE METAL GRILLE11 DECORATIVE CORBEL12 EXTERIOR LIGHTING (CHATHAM 89273BLE-46)12839612839615283941112GARAGEGREAT ROOMBEDROOMBEDROOMBEDROOM9'-1"9'-1"9'-1"100 CU FTHANGING STOR7'-0"5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESFRONTBUILDING F ELEVATIONSA-230 8 16 24 LEFTREARRIGHTTYPICAL SECTION 5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESBUILDING APERSPECTIVESA-24BUILDING F - LINCOLN AVEALLEY - NORTHALLEY - SOUTH 5256 S. Mission Road, Ste 404Bonsall, CA 92003760.724.1198ARCHITECTURESCALE:SEPTEMBER 9, 2022KB HOME9915 MIRA MESA BLVD., STE 100SAN DIEGO, CA 92131858.877.4256ANAHEIM, CALINCOLN & SUNKIST TOWNHOMESBUILDING E - LINCOLN AVEPERSPECTIVESA-25COMMON AREAALLEY - NORTHALLEY - SOUTH W S G E 562 OHE FO T AC AC AC AC AC AC ACAC ACACACACACACACAC AC AC AC AC AC AC AC AC AC AC AC ACAC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC ACEVERTLR TRACT BOUNDARY TRACT BOUNDARY TRACT BOUNDARYTRACT BOUNDARY L=36.11' R=25.00° |=82°45'49" L=17.02' R=2625.09° |=0°22'17" N 01°03'43"E ~ 0.23' NO SCALE VICINITY MAP SCALE: 1" = 60' KEY MAP CIVIL ENGINEER: ARCHITECT:UTILITY PURVEYORS: OWNER/ DEVELOPER: WATER SEWER ELECTRICITY PHONE/INTERNET (714) 765-3300 CITY OF ANAHEIM, PUBLIC WORKS (714) 765-3300 CITY OF ANAHEIM, PUBLIC WORKS SHEET INDEX 1 2 3 4 5 TITLE SHEET 6 LEGAL DESCRIPTION BASIS OF BEARINGS VESTED OWNER DATUM STATEMENT BENCHMARK STATEMENT 55 E L INCOLN AVE E SOUTH ST E SUNKIST STDR E WESTPORT S PEREGRINE STW WESTPORT DR STATE COLLEGE BLVDSITE PROJECT W S 560 RIGHT OF WAY PROPOSED EXISTING TOP OF GRATE FINISHED FLOOR ASPHALT CONCRETE INVERT ELEVATION CENTERLINE FINISH GRADE PAD ELEVATION HIGH POINT PORTLAND CEMENT CONCRETE EXISTING GROUND CURB FACE GARAGE FLOOR FRONT GOLDEN STATE WATER COMPANY ORANGE COUNTY FIRE AUTHORITY FINISH SURFACE FLOW LINE FIRE HYDRANT BOTTOM TOP OF PIPE PROP RW FG FL TG FF AC IE CL FS PE HP PCC EG EX/EXIST CF GFF GSWC OCFA FH BOT TP ABBREVIATIONS PROPOSED EASEMENT CENTER LINE PROPOSED WATER PROPOSED SEWER PROPOSED STORM DRAIN PROPOSED CURB PROJECT BOUNDARY RIGHT-OF-WAY PROPOSED CONTOUR PROPOSED CONCRETE PROPOSED ASPHALT CONCRETE PROPOSED WATER VALVE PROPOSED BACKFLOW PREVENTER PROPOSED SEWER MANHOLE PROPOSED SEWER CLEANOUTPROPOSED SEWER SERVICE LATERAL PROPOSED WATER SERVICE LATERAL PROPOSED FIRE HYDRANT PROPOSED CURB INLET DETENTION CHAMBERS PROPOSED UNDERGROUND LEGEND (714) 765-5158 CITY OF ANAHEIM, PUBLIC UTILITES VERIZON (469) 886-4238 AT&T (714) 507-3526 SYSTEM (CCS 83), ZONE VI, NAD 83, (2017.50 EPOCH) COORDINATES SHOWN ARE BASED ON THE CALIFORNIA COORDINATE AVERAGE ELEVATION ABOVE MEAN SEA LEVEL = 191.00' MAY BE OBTAINED BY MULTIPLYING GROUND DISTANCES BY .99999282 DISTANCES SHOWN HEREON ARE GROUND DISTANCES. GRID DISTANCES ELEVATION 189.276' (NAVD 88) BM = 1K-34-06 ORANGE COUNTY VERTICAL CONTROL SECTIONSSUNKIST STREETE . L INCO LN AV ENU E UNIT 75UNIT 82 UNIT 81UNIT 76 UNIT 77UNIT 80 UNIT 79UNIT 78 UNIT 74UNIT 83 UNIT 64UNIT 73 UNIT 72UNIT 65 UNIT 66UNIT 71 UNIT 67UNIT 70 UNIT 69UNIT 68 UNIT 58UNIT 59 UNIT 60UNIT 57 UNIT 56UNIT 61 UNIT 55 UNIT 54UNIT 63 UNIT 62 UNIT 44UNIT 53 UNIT 52UNIT 45 UNIT 46UNIT 51 UNIT 47UNIT 50 UNIT 49 UNIT 48 UNIT 36UNIT 43 UNIT 42UNIT 37 UNIT 38UNIT 41 UNIT 40 UNIT 39 UNIT 26UNIT 35 UNIT 34UNIT 27 UNIT 28UNIT 33 UNIT 32UNIT 29 UNIT 30UNIT 31 UNIT 20 UNIT 21 UNIT 22 UNIT 23 UNIT 24 UNIT 25 UN IT 19 UN IT 18 UN IT 17 UN IT 16 UN IT 15 UN IT 14 UN IT 13 UN IT 12 UN IT 11 UN IT 10 UN IT 9 UN IT 8 UN IT 1 UN IT 2 UN IT 3 UN IT 4 UN IT 5 UN IT 6 UN IT 7 MAPPING ALBERT & SONS REAL ESTATE 1, LLC, A CALIFORNIA LIMITED LIABILITY COMPANY FLOOD ZONE DESIGNATION SITE SUMMARY: LANDSCAPE ARCHITECT: COUNTY SURVEYOR. AS SHOWN HEREON. SAID GPS RECORDS ON FILE IN THE OFFICE OF THE ORANGE N 77°58'46" W PER RECORDS ALSO BEING THE CENTERLINE OF LINCOLN AVENUE GPS 5249 N=2253183.52 E= 6063915.11, 2017.50 EPOCH. SAID BEARING BEING HORIZONTAL CONTROL STATION GPS 5248 N=2252622.81 E= 6066548.42 AND THE BEARING SHOWN HEREON ARE BASED ON THE BEARING BETWEEN OCS LEVEES FROM 1% ANNUAL CHANCE FLOOD. DRAINAGE AREAS LESS THAN 1 SQUARE MILE, AND AREAS PROTECTED BY 1% CHANCE FLOOD WITH AVERAGE DEPTHS OF LESS THAN 1 FOOT OR WITH ZONE X IS DEFINED AS AREAS OF 0.2% ANNUAL CHANCE FLOOD, AREAS OF FLOOD INSURANCE RATE MAP NO. 06059C0134J DATED DECEMBER 3, 2009. ENTIRE PROJECT AREA IS WITHIN FEMA DESIGNATED FLOOD ZONE X PER CONTACT: DAMIAN TAITANO BONSALL, CA 92003 5256 S MISSION RD, SUITE 404 SUMMA ARCHITECTURE STORM DRAIN GAS (714) 765-3300 CITY OF ANAHEIM, PUBLIC WORKS SO. CAL. GAS COMPANY (800) 427-2200 CONTACT: JOHN O'MALLEY TEMECULA, CA 92590 28924 OLD TOWN FRONT STREET, SUITE 202 WEILAND DESIGN GROUP, INC PHONE: (949) 588-0707 CONTACT: BARRY J. COWAN, PE IRVINE, CA 92618 36 DISCOVERY, SUITE 240 RICK ENGINEERING COMPANY EXISTING WATER EXISTING SEWER EXISTING STORM DRAIN EXISTING GAS EXISTING ELECTRIC EXISTING MINOR CONTOUR PROPOSED FENCE PROPOSED GUTTER PROPOSED DRAINAGE SWALE PROPOSED AIR RELEASE VALVE PROPOSED BLOW-OFF EXISTING OVERHEAD ELECTRIC EXISTING FIBER OPTIC EXISTING TELEPHONE EXISTING RETAINING WALL IN THE OFFICE OF SAID COUNTY RECORDER. AS INSTRUMENT NO. 2018000253764, OF OFFICIAL RECORDS, ORANGE, STATE OF CALIFORNIA, RECORDED JULY 11, 2018 NO. LLA-0000770, IN THE CITY OF ANAHEIM, COUNTY OF PARCELS A AND B DESCRIBED IN LOT LINE ADJUSTMENT STATE OF CALIFORNIA, AND IS DESCRIBED AS FOLLOWS: IN THE CITY OF ANAHEIM, COUNTY OF ORANGE, THE LAND REFERED TO HEREIN BELOW IS SITUATED SITE PLAN GRADING PLAN UTILITY PLANL=182.05'R=2715.09°|=3°50'30"N89°13'50"W 615.13'N1°04'18"E 344.90'N 7 7 °58 '46 "W 613 .22 ' FIRE SERVICE LINE FS PROPOSED POST INDICATOR VALVE 7 FIRE PLAN BUILDING 10 BUILDING 9 BUILDING 8 BUILDING 7 BUILDING 6 BUILDING 5 BUILDING 4 BU ILD ING 3 BU ILD ING 2 BU ILD ING 1 S PIV TENTATIVE TRACT MAP NO. 19237 FOR CONDOMINIUM PURPOSES (APN 083-731-18 & 083-731-19) 2420-2450 EAST LINCOLN AVENUE TITLE SHEET PHONE: (858) 877-4262 CONTACT: JESSE KLEIST SAN DIEGO, CA 92131 9915 MIRA MESA BLVD, SUITE 100 KB HOME COASTAL, INC 21 DU/AC NET: 20 DU/ACGROSS:DENSITY: = 10 BUILDINGS (83 UNITS) TOTAL + 5 BUILDINGS (10 UNITS EACH) + 1 BUILDING (8 UNITS) + 1 BUILDING (7 UNITS) PROPOSED DWELLING UNITS: 3 BUILDINGS (6 UNITS EACH) 3.93 ACRES (171,037 SF) NET: SITE AREA: GROSS: 4.02 ACRES (175,118 SF) PROPOSED: 1 EXISTING: 2NO. OF LOTS: PROPOSED: RESIDENTIAL-MEDIUM EXISTING: RESIDENTIAL-MEDIUMGENERAL PLAN: OVERLAY ZONE R-O (RESIDENTIAL OPPORTUNITY) PROPOSED: C-G (GENERAL COMMERICAL) & OVERLAY ZONE R-O (RESIDENTIAL OPPORTUNITY) ZONING: EXISTING: C-G (GENERAL COMMERICAL) & PROPOSED: MULTI-FAMILY RESIDENTIAL LAND USE: EXISTING: OFFICE USE ASSESSOR PARCEL NO. (APN): 083-731-18 & 19 CITY OF ANAHEIM, CA 92806 SITE ADDRESS: 2420 & 2450 EAST LINCOLN AVENUE INSTRUMENT PRIOR TO ISSUANCE OF ANY BUILDING PERMIT. BE REVEIWED, APPROVED, AND RECORDED BY SEPARATE EGRESS RIGHTS TO THE CITY OF ANAHEIM. EASEMENTS SHALL SOLID WASTE COLLECTION SERVICE INCLUDING INGRESS AND DEDICATED PUBLIC EASEMENTS FOR EMERGENCY ACCESS AND INTERIOR DRIVE AISLES, AS INDICATED ON PLAN, SHALL BE PROPOSED EASEMENTS: LOT 1 INIT.DATE DESCRIPTION APP'D DATE SHEET OF SITE ADDRESS: SCALE:DRAWN BY:CHECKED BY: PREPARED BY:OWNER OR DEVELOPER: SOILS ENGINEER: REVISIONS NO. CITY OF ANAHEIM 1 STAT EOF CALIFORNIAREGISTEREDPROFESSIONAL E NGI NEERNo.46568 A R A BRY C OWNJGH JGH 02-NOV-2022 14:37 C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\ORN CorpStds 2005.dscript C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\19467_01_Title.dgn J-19467 AS NOTED 7 DATE: PHONE: (949) 442-2442 CONTACT: IRVINE, CA 92614 17991 FITCH NMG GEOTECHNICAL, INC. PHONE: (858) 877-4262 CONTACT: JESSE KLEIST SAN DIEGO, CA 92131 9915 MIRA MESA BLVD, SUITE 100 KB HOME COASTAL 2420-2450 E. LINCOLN AVENUE, ANAHEIM, CA 92806 TENTATIVE TRACT MAP NO. 19237 DATE: 11/2/2022XS XS XS XSNO PARKINGNO PARKINGVPIV COX COX X X X X EVX MHX EV COX COX COX X X X X X X EV EVX XSVAR XEVXERTLRV XTPB X TLRXEVX EVX XTPB XTPBUVXWX TLRX EVX XTPBEVX WX EVX XTPB EV X X XT P B UVXT X UVX XT PB E V X EVXX INIT.DATE DESCRIPTION APP'D DATE SHEET OF SITE ADDRESS: SCALE:DRAWN BY:CHECKED BY: PREPARED BY:OWNER OR DEVELOPER: SOILS ENGINEER: REVISIONS NO. CITY OF ANAHEIM STAT EOF CALIFORNIAREGISTEREDPROFESSIONAL E NGI NEERNo.46568 A R A BRY C OWNJGH JGH 02-NOV-2022 14:37 C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\ORN CorpStds 2005.dscript C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\19467_02_Maping.dgn J-19467 AS NOTED 7 DATE: PHONE: (949) 442-2442 CONTACT: IRVINE, CA 92614 17991 FITCH NMG GEOTECHNICAL, INC. PHONE: (858) 877-4262 CONTACT: JESSE KLEIST SAN DIEGO, CA 92131 9915 MIRA MESA BLVD, SUITE 100 KB HOME COASTAL 2420-2450 E. LINCOLN AVENUE, ANAHEIM, CA 92806 TENTATIVE TRACT MAP NO. 19237 DATE: 11/2/20222 PLOTTED ON LINCOLN AVE. RIGHT OF WAY 30' HALF WIDTH ORIGINAL AS SHOWN HEREON OF LINCOLN AVENUE SUNKIST AND A PORTION RIGHT OF WAY ON AS SHOWN HEREON OF LINCOLN AVENUE A PORTION RIGHT OF WAY ON PLOTTED PLOTTED PLOTTED PLOTTED NO.ITEM DATARECORD DESCRIPTION REMARKS DEEDS OF85 PAGE 275,BOOK AS 1915 7,MAY UTILITYPUBLIC AND ROAD FOREASEMENT RECORDS OFFICIALOF 218 PAGE8437, BOOK AS1967 15,NOVEMBER PIPELINES FOREASEMENT RECORDSOFFICIAL OF 1116PAGE 11057, BOOKAS 1974 15,JANUARY UTILITYPUBLIC AND ROAD FOREASEMENT RECORDS OFFICIAL OF465 PAGE 11417,BOOK AS 1975 30,MAY UTILITYPUBLIC AND ROAD FOREASEMENT RECORDSOFFICIAL OF 968PAGE 11677, BOOKAS 1976 18,MARCH UTILITES PUBLC FOREASEMENT UTILITYPUBLIC AND ROAD FOREASEMENT DEDICATE TOOFFER RECORDSOFFICIAL OF89-705384 NO.RECORDING AS1989 29,DECEMBER FACILITIESWATER FOR EGRESS ANDINGRESS INCLUDINGUTILITY PUBLIC FOREASEMENT EGRESSAND INGRESSFACILITIES, COMMUNICATION UNDERGROUND FOREASEMENT TOPOGRAPHY NOTE OFFICIAL RECORD 89-072800 OF RECORDING NO. 1989 AS FEBRUARY 10, OFFICIAL RECORDS 2001-0106330 OF RECORDING NO. 2001 AS FEBRUARY 27, PARCEL A PARCEL B INST. NO. 2018000253764 O.R. RECORDED JULY 11, 2018 LLA-0000770 INST. NO. 2018000253764 O.R. RECORDED JULY 11, 2018 LLA-0000770 3 6 6 9 10 2 5 4 NO. 80-235 PARCEL MAP PARCEL 2 PARCEL 1 267.70'(N 00°10'16" E 267.71 R1)MM 169/ 11-12 TRACT NO. 4717RANCHO SAN JUAN CAJON DE SANTA ANA, M.M. 5/10PORTION OF SECTION 12,T .4 S., R. 10 W.4 (N 89°52'20" E 615.10' R1 AND R2)(N 78 °52 '36 " W 6 13 .22 ' R 1 AND R 2 )R=2715.09'L=182.05'|=350'30"&MR1&(RR2)L1 (N 89°52'20" E 660.10' R1 AND R2)(N 00°10'28" E 398.88' R1 AND R2)382'53'30'23'20' 45' ESTABLISHED BY INTERSECTION SHEET NO. 5248 AND R2. GPS HORIZONTAL CONTROL DATA LINCOLN AND SUNKIST PER O.C. ACCEPTED AS CL INTERSECTION FD. 2" BRASS DISK IN WELL 50'5'20'AND DISTANCE PER R1 AND R2. ESTABLISHED RECORD ANGLE 40'20'PARCEL 2 LINE EASTERLY23'7'10'8 R1 AND R2N85°59'14"W PCC(RAD.) N85°05'24"W PCC(RAD.) N85°29'18"W PRC(RAD.) R1 AND R2 N86°21'31"W PRC(RAD.)C2 MAPPING L C L INCOLN AV ENU E LRECORD DISTANCE PER R1 AND R2. ESTABLISHED ON LINE AT FOLLOWING ARE EXCEPTIONS THERE TO: REPORT ORDER NO. 00150903-987-OC1-K27, DATED APRIL 22, 2021. THE REFERENCE IS MADE TO CHICAGO TITLE COMPANY PRELIMINARY TITLE R5 INDICATES RECORD DATA PER RSB 87/26. MM 10/38. R4 INDICATES RECORD DATA PER PARCEL MAP MM 372/15-16. R3 INDICATES RECORD DATA PER TRACT NO. 8910 MAP NO. 80-235, MM 150/48. R2 INDICATES RECORD DATA PER PARCEL NO. 2018000253764 O.R. RECORDED JULY 11, 2018 AS INST. R1 INDICATES RECORD DATA PER LLA-0000770 MAP REFERENCES X SNF FD. LEGEND C 3C 4C4 4°52'59" 310.00' 26.42' C3 4°52'59" 540.00' 46.02' C2 82°31'05" 25.00' 36.01' (R1 AND R2) C2 82°45'49" 25.00' 36.11' C1 0°22'17" 2625.09' 17.02' (R&M R1 AND R2) ---- ----------- --------- -------- NAME DELTA RADIUS ARC CURVE TABLE L1 N 0°10'16" E 0.23' (R1 AND R2) L1 N 1°03'43" E 0.23' ---- ---------------- --------- NAME DIRECTION LENGTH LINE TABLE EXISTING LOT LINE RIGHT OF WAY PROPOSED INTERVAL IS ONE FOOT. GROUND SURVEY METHODS ON SEPT. 01, 2021. THE CONTOUR THE TOPOGRAPHY SHOWN HEREIN WAS COMPILED FROM (N 00°10'28" E 344.90' R1 AND R2)0 GRAPHIC SCALE 1" = 30' 1530 30 60 90C1EXISTING EASEMENTS INDICATES SEARCH NOTHING FOUND. INDICATES FOUND INDICATES TITLE REPORT ITEM INDICATES FOUND MONUMENT AS NOTED. INDICATES EXISTING EASEMENT LINE INDICATES LOT LINE INDICATES CENTER LINE INDICATES PROPOSED RIGHT-OF-WAY INDICATES BOUNDARY PROPOSED RIGHT OF WAY DEDICATION AREA TO THE CITY OF ANAHEIM. AREA TO BE DEDICATED11'45' 45'C SUNKIST STREET NOT TO SCALE (FF PER PLAN) FINISHED FLOOR (SOUTH SIDE) BUILDING FACE 42' 18' PARKING 24' DRIVE AISLE CL NOT TO SCALE 16' 103' 50'53' 35'34' 8' 8' SDWK EX R/W NORTHERLY LINCOLN AVENUE EXISTING 5' 10' TYPICAL SECTION: LINCOLN AVENUE 5' NOT TO SCALE CL 13'13' TYPICAL SECTION: SUNKIST STREET 90' SITE PROJECT SITE PROJECT STA 1+75.00 TO STA 2+98.00 STA 1+88.00 TO STA 3+68.00 10'5' 58' 2% (4" THICK) NEW SIDEWALK 2% 2% 6" CURB EX R/W SOUTHERLY EX R/W EASTERLY EX R/W WESTERLY 6' MAX 3' SECTION C-C NOT TO SCALE 2% EXISTING GROUND SECTION B-B PARKING 18' 42' DRIVE AISLE 24'5'4' 55' (WEST SIDE) BUILDING FACE (4" THICK) NEW SIDEWALK 0" CURBPROP. C&G 2% MAX 3' NOT TO SCALE SECTION A-A CL 53' SDWK LINCOLN AVENUE EXISTING 5' 10' 5' EX R/W SOUTHERLY 1.5% 25' MAX 1' (NORTH SIDE) BUILDING FACE 4" STEP 2% 4.5' (4" THICK) NEW SIDEWALK (FF PER PLAN) FRONT DOOR NOT TO SCALE SECTION D-D CL 5'5' 6'11' NOT TO SCALE SECTION D-D CL 64' LINCOLN AVENUE EXISTING EX R/W SOUTHERLY 2% (4" THICK) NEW SIDEWALK 2 :1 R/W PROP PROP RETAINING WALL (4" THICK) NEW SIDEWALK DRAINANGE SWALE 2% NOT TO SCALENOT TO SCALE SECTION E-E 20' SETBACK 11.5 13.5 55' SETBACK (NORTH SIDE) BUILDING FACE 1% 0" CURB 1% MAX 2' (FF PER PLAN) FRONT DOOR 24' DRIVE AISLE (4" THICK) NEW SIDEWALK 2%SDWK NOT TO SCALE SECTION F-F MAX 4.25' MAX 4.25' 2.0% MAX 0.5% MIN - VARIES 2.0% MAX 0.5% MIN - VARIES PKWY LS NEW PKWY LS NEW PKWY LS NEW EX. CMU SCREEN WALL 2% EXIST SDWK 5' PKWY LS NEW SDWK NEW 12.5' EXIST SDWK REMOVE EXIST SDWK SDWK NEW 9.5' SDWK EXIST REMOVE 8' TO REMAIN. EXIST C&G 32' 45' 32' 45' (4" THICK) NEW SIDEWALK STAIRS 33' 2.5' TO REMAIN. EXIST C&G BOUNDARY TRACT BOUNDARY TRACT MEDIAN RAISED EXIST TO BE REMOVED. EXIST C&G DEDICATION R/W 51' 54' 3' NEW C&G 4' SECTIONS 3 BUILDING FACE BUILDING FACE (GFF PER PLAN) GARAGE FINISHED FLOOR (GFF PER PLAN) GARAGE FINISHED FLOOR (GFF PER PLAN) GARAGE FINISHED FLOOR (GFF PER PLAN) GARAGE FINISHED FLOOR EXIST CMU SCREEN WALL EXIST CMU SCREEN WALL NEW C&G DRIVE AISLE 20' 14.25' (MIN)14.25' (MIN) CL (ALLEY) COURT COMMON NOTE: ** ** ** ** NOTE ON TITLE SHEET. AND EGRESS RIGHTS TO THE CITY OF ANAHEIM. SEE EASEMENT AND SOLID WASTE COLLECTION SERVICES INCLUDING INGRESS TO BE DEDICATED PUBLIC EASEMENTS FOR EMERGENCY ACCESS WHERE SHOWN IN SECTION THIS SHEET: TO REMAIN. EXIST C&G SUNKIST STREET EXISTING 53' CL NOT TO SCALE 114' 50'53' 54'34'8' SDWK EX R/W NORTHERLY LINCOLN AVENUE EXISTING 11' 4'4' 5'5' SDWK R/W PROP DEDICATION R/W TYPICAL SECTION: LINCOLN AVENUE SITE PROJECT STA 2+98.00 TO STA 5+83.00 EX R/W SOUTHERLY 2% PKWY LS NEW TO BE REMOVED. EXIST C&G SDWK EXIST REMOVE (4" THICK) NEW SIDEWALK NEW C&G * FROM STA 2+98 TO 4+63. TRANSITIONS FROM 43' TO 54' * EXIST RAISED MEDIAN 43'9.5' CL NOT TO SCALE 114' 50'53' 54'34'8' SDWK EX R/W NORTHERLY LINCOLN AVENUE EXISTING 11' 4'4' 5'5' SDWK R/W PROP DEDICATION R/W TYPICAL SECTION: LINCOLN AVENUE SITE PROJECT STA 5+83.00 TO STA 7+22.00 EX R/W SOUTHERLY 2% PKWY LS NEW TO BE REMOVED. EXIST C&G NEW C&G * EXIST RAISED MEDIAN *51'* FROM STA 5+83 TO 6+34. TRANSITIONS FROM 43' TO 51' (4" THICK) NEW SIDEWALK * SDWK EXIST REMOVE 9' IMPROVEMENTS. WIDENING LIMIT OF STREET FROM EXISTING C&G. SAWCUT LINE 1-FOOT IMPROVEMENTS. WIDENING LIMIT OF STREET FROM EXISTING C&G. SAWCUT LINE 1-FOOT 3' 1' 11' INIT.DATE DESCRIPTION APP'D DATE SHEET OF SITE ADDRESS: SCALE:DRAWN BY:CHECKED BY: PREPARED BY:OWNER OR DEVELOPER: SOILS ENGINEER: REVISIONS NO. CITY OF ANAHEIM STAT EOF CALIFORNIAREGISTEREDPROFESSIONAL E NGI NEERNo.46568 A R A BRY C OWNJGH JGH 02-NOV-2022 14:38 C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\ORN CorpStds 2005.dscript C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\19467_03_Sections.dgn J-19467 AS NOTED 7 DATE: PHONE: (949) 442-2442 CONTACT: IRVINE, CA 92614 17991 FITCH NMG GEOTECHNICAL, INC. PHONE: (858) 877-4262 CONTACT: JESSE KLEIST SAN DIEGO, CA 92131 9915 MIRA MESA BLVD, SUITE 100 KB HOME COASTAL 2420-2450 E. LINCOLN AVENUE, ANAHEIM, CA 92806 TENTATIVE TRACT MAP NO. 19237 DATE: 11/2/2022 X X X X MHX EV X X X X X X EV XSVAR XEVXERTLRV XTPB X TLRXEVX EVX XTPB XTPBUVXWX TLRX EVX XTPBEVX XTPB EV X X XT P B UVXT X UV X XT PB E V X EVXEVXER TLRAC AC AC AC AC AC ACAC ACACACACACACACAC AC AC AC AC AC AC AC AC AC AC AC ACAC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC 191 192 193PROJECT BOUNDARYPROJECT BOUNDARYRIGHT OF WAY SETBACK EXIST SCREEN WALLEXIST SCREEN WALLSETBACK R3-5 (R) SIGN R3-5 (R) SIGN R6-1 (R) SIGN L=36.11' R=25.00° |=82°45'49" L=17.02' R=2625.09° |=0°22'17" S IGH T TR IANG LE SIGHT TRIANGLESIGHT TRIANGLECOUNT R IGH T OF WAY EX IST R IGH T OF WAY PROP R IGH T OF WAY TO REMAIN. AT&T CEV STRUCTURE SEWER LIFT STATION INIT.DATE DESCRIPTION APP'D DATE SHEET OF SITE ADDRESS: SCALE:DRAWN BY:CHECKED BY: PREPARED BY:OWNER OR DEVELOPER: SOILS ENGINEER: REVISIONS NO. CITY OF ANAHEIM STAT EOF CALIFORNIAREGISTEREDPROFESSIONAL E NGI NEERNo.46568 A R A BRY C OWNJGH JGH 02-NOV-2022 14:38 C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\ORN CorpStds 2005.dscript C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\19467_04_SitePlan.dgn J-19467 AS NOTED 7 DATE: PHONE: (949) 442-2442 CONTACT: IRVINE, CA 92614 17991 FITCH NMG GEOTECHNICAL, INC. PHONE: (858) 877-4262 CONTACT: JESSE KLEIST SAN DIEGO, CA 92131 9915 MIRA MESA BLVD, SUITE 100 KB HOME COASTAL 2420-2450 E. LINCOLN AVENUE, ANAHEIM, CA 92806 TENTATIVE TRACT MAP NO. 19237 DATE: 11/2/2022XS XS XS XSNO PARKINGNO PARKINGVPIV 4 E . L INCO LN AV ENU E SUNKIST STREET103'24'18'90'24'11'24' 24'18' 24' B B 1+00 2+00 3+ 00 4+ 00 5+00 6+00 7+ 00 1+002+003+0010'24'18'10'24'9' 18'18'9'10'21.5'4'1 5' 15' 20'4'5'10.39'103'50'53'16'34'35'10'8'5'5'53'50'34'8'4'54'45' 45' 13'32'32'13' C A 20'20'20' UN IT 1 UN IT 2 UN IT 3 UN IT 4 UN IT 5 UN IT 6 UN IT 7 UN IT 8 UN IT 9 UN IT 10 UN IT 11 UN IT 12 UN IT 13 UN IT 14 UN IT 15 UN IT 16 UN IT 17 UN IT 18 UN IT 19 UNIT 20 UNIT 21 UNIT 22 UNIT 23 UNIT 24 UNIT 25 UNIT 26 UNIT 27 UNIT 28 UNIT 29 UNIT 30UNIT 31 UNIT 32 UNIT 33 UNIT 34 UNIT 35 UNIT 39 UNIT 36 UNIT 37 UNIT 38 UNIT 40 UNIT 41 UNIT 42 UNIT 43UNIT 44 UNIT 45 UNIT 46 UNIT 47UNIT 50 UNIT 51 UNIT 52 UNIT 53UNIT 54 UNIT 55 UNIT 56 UNIT 57 UNIT 58UNIT 59 UNIT 60 UNIT 61 UNIT 62 UNIT 63UNIT 64 UNIT 65 UNIT 66 UNIT 67 UNIT 68UNIT 69 UNIT 70 UNIT 71 UNIT 72 UNIT 73 UNIT 74 UNIT 75 UNIT 76 UNIT 77 UNIT 78UNIT 79 UNIT 80 UNIT 81 UNIT 82 UNIT 83 15 ' 9'9'11.5'10'UNIT 48UNIT 49 3' (TYP.) 7'64'7'7'10'55'15'21.4' MIN 35.3' MIN 28.5' MIN 20' MIN 28.5' MIN 20' MIN 36.5' MIN 28' MIN 23.5' MIN 30.2' MIN 30.4'37.7'9'4'4' PROPOSED ASPHALT CONCRETE PROPOSED CONCRETE REQUIRED SETBACK TRACT BOUNDARY LEGEND 9 9 10 87 10 10 9 D 5' D A E E C 18'9'18'9'18'9'NEW DWY24'NEW DWY 24 ' N89°13'50"W 615.13' N 77 °58 '46 "W 613 .22 ' F F L=182.05'R=2715.09°|=3°50'30"N1°04'18"E 344.90'SITE PLAN11'S IGH T TR IANG LE 0 GRAPHIC SCALE 1" = 30' 1530 30 60 90 BU ILD ING 1 BU ILD ING 2 BU ILD ING 3 BUILDING 4BUILDING 5 BUILDING 6BUILDING 7BUILDING 8BUILDING 9BUILDING 10 A A A AAA AA A 7'70.5'TYPTYPTYPTYP TYP TYP TYP TYP2.5'2.5'24'4'2.5'24'4'DOG PARK COMMUNITY GARDEN8'9'9'10.5' 24'4'4'4'5'5'5'5'5'4'4'4'UNIT #UNIT NUMBER BUILDING NUMBER # ACCESSIBLE UNIT AC CONDENSER UNIT BACKFLOW PREVENTER BUILDING # A OPEN PARKING STALL DECORATIVE STAMPED ASPHALT CONCRETE R/W DEDICATIONPROPOSEDSETBACK20'TOT LOT 5'FFFF F F E E 4' E E NOTE: ** ** ** ****************NOTE ON TITLE SHEET. AND EGRESS RIGHTS TO THE CITY OF ANAHEIM. SEE EASEMENT AND SOLID WASTE COLLECTION SERVICES INCLUDING INGRESS TO BE DEDICATED PUBLIC EASEMENTS FOR EMERGENCY ACCESS WHERE SHOWN IN PLAN THIS SHEET: 5'8'51'43'54'10'WIDENING IMPROVEMENTSLIMIT OF STREETWIDENING IMPROVEMENTSLIMIT OF STREETWIDENING IMPROVEMENTSLIMIT OF STREETCL TO EX CURBCL TO NEW CURB3'11'LOT 1 AND ELECTRICAL PANEL SEWER LIFT STATION EVXER TLRX X X X MHX EV X X X X X X EV XSVAR XEVXERTLRV XTPB X TLRXEVX EVX XTPB XTPBUVXWX TLRX EVX XTPBEVX WX XTPB EV X X XT P B UVXT X UV X XT PB E V X EVXAC AC AC AC AC AC ACAC ACACACACACACACAC AC AC AC AC AC AC AC AC AC AC AC ACAC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC EVX XTPB EVX TLRX X XTPB 191 192 193R/WR /W R/WBOUNDARY PROJECT BOUNDARY PROJECT SWALE @ 0.4% SWALE @ 0.4%TO REMAINEXISTING CURB & GUTTERNEW CURB & GUTTERTO BE RELOCATED FIRE HYDRANT STRUCTURE TO REMAIN EXIST AT&T CEV R IGH T OF WAY SEE DETAIL THIS SHEET NEW CURB RAMP. EXIST R/W EXIST C&G NEW C&G PROPOSED R/W CONTROLLER CABINET TO REMAIN. EXISTING TRAFFIC SIGNAL RELOCATE TYPE 1-A SIGNAL POLE. RELOCATE TYPE 1-A SIGNAL POLE. EXIST R/W P R OP OSE D R/W(SHADED AREA) 25'x25' LINE OF SIGHT CLEAR ZONE TO REMAIN. EXIST CURB & GUTTER TO REMAIN. FIRE HYDRANT POLE TO REMAIN. EXIST TYPE 26A-3-100 SIGNAL EXISTING FIRE HYDRANT TO REMAIN. EXISTING TYPE 26A-3-100 SIGNAL POLE TO REMAIN. EXIST EASEMENT (MWD) EXIST EASEMENT (CITY)SAWCUT LINESAWCUT LINENEW C&G 0 GRAPHIC SCALE 1" = 30' 1530 30 60 90 5SUNKIST STREETE . L INCO LN AV ENU E 103'90'24'24'18'5'53'50'45' 45'10'11'11'11'12'11'11'13'4'7'2'13' 13'32'32' 191.20 FL 191.70 TC 193.24 FL 193.74 TC 0 . 5% (191.71) EG (192.01) EG (192.23) EG (191.74) EG (191.85) EG (191.85) EG (191.79) EG (190.50) EG (193.57) EG(194.48) EG(194.32) EG(194.07) EG(193.84) EG(193.73) EG(193.69) EG(193.44) EG(193.06) EG(192.97) EG(192.65) EG(192.51) EG(192.06) EGFS190.70195 .00 FF 194 .2 5 G F F1%FS-4"194.70E . L INCO LN AV ENU E 0" CF 194.26 TC 0" CF 193.53 TC 193 .75 G FF2%194 .80 FF 0" CF 193.53 TC 0" CF 194.13 TC 0" CF 194.83 TC 195 .7 0 FF 1%194 .90 G FF FS192.50FS-4"195.40194 .4 0 G F F1%195 .2 0 FF 0" CF 194.23 TCFS191.93FS-4"194.90FS191.20FS-6"194.30193 .7 5 G F F2%1 94 .80 F FFS-6"194.30FS191.301 9 4 .25 G FF1%1 9 5 .0 0 FF FS-4"194.70FS191.83FS190.75FS190.82FS190.95FS191.11FS191.34FS191.52FS191.56FS191.74FS192.33193.98 FL 194.48 TC 194.88 FS 195.38 TC 194.30 FL 194.80 TCFS192.20FS192.15194 .2 5 G FF 1 9 4 .2 5 G FF 1 9 4 .2 5 G F F 193 .75 G FF 1 93 .75 G F F 193 .7 5 G FF 194 .2 5 G FF 194 .2 5 G FF 194 .2 5 G FF 194 .90 G FF 194 .90 G FF 1 9 4 .9 0 G FF 194 .90 G FFFS-6"194.30FS-6"194.302%1 9 4 .80 FF 2%194 .80 FF 1%195 .00 F FFS-4"194.70FS-4"194.70FS-4"194.701%1 95 .0 0 FF 1%195 .0 0 F F FS-4"194.70FS192.02FS-4"195.40FS-4"195.40FS-4"195.40FS-4"195.401 9 5 .7 0 FF 1%195 .70 F F 1%195 .7 0 F F 1%1 9 5 .70 FF 1%FS-6"194.30195.30GFF1% 196.10 FF 195.10 FF 1%194.80GFF195.60 FF195.20GFF1%195.10GFF1% 195.60 FF195.00GFF1% 195.60 FF 194.90GFF1% 195.60 FF195.30GFF1%194.80GFF1%195.30GFF1%194.80GFF2% 195.45 FF 195.70 FF 195.05GFF194.95GFF195.20GFF1%195.10GFF1%195.00GFF1% 1%194.50GFF195.30 FF 193.60GFF2% 194.80 FF 193.00GFF1%193.20GFF1%193.30GFF1%193.40GFF1%193.50GFF1%194.50GFF1%194.30GFF1%193.50GFF1% 2%193.50GFF1%193.40GFF1%193.30GFF1%193.20GFF2%193.00GFF193.90GFF2% 194.80 FF 194.80 FF 193.80 FF 193.80 FF 193.80GFF1%193.70GFF1%193.60GFF1%193.40GFF1% 193.80 FF 194.80 FF 194.80 FF 193.90GFF2%194.30GFF1% 1%1% 1%1% 1% 2%193.80GFF1% 1%194.20GFF193.80GFF194.10GFF194.00GFF193.40GFF193.70GFF193.60GFF194.30GFF1%194.20GFF1%194.10GFF1%194.00GFF1%193.80GFF194.70GFF1% 1% 1% 1%194.60GFF194.50GFF194.40GFF194.20GFF194.60GFF195.00GFF194.90GFF1%194.80GFF1%194.60GFF1%194.50GFF1%194.40GFF1%194.20GFF1% 193.86 FL 194.36 TCFS-4"194.70FS-4"194.70195 .0 0 FF 1%195 .0 0 FF 1%1 95 .00 FF 1%194 .8 0 F F 2%24'0.5%0.5%0.5%0.5%0.5%193.57 FL 194.07 TC 194.10 FS 194.51 TC 1.0%194.55 FS 195.13 FL 195.20GFF195.70 FF 195.70 FF 195.70 FF 195.70 FF 1% 1% 1% 194.50 FL 194.83 TC FS-4"195.80FS-4"195.30FS-4"194.80FS-4"195.30FS-4"195.30FS-4"195.30191.25 FL 191.75 TC 0.5% 0.5%1.0%0.5%0.5%0.5% 24'1.0%2.0%0 .5% 0 .5% 0 .5%0.5%1.0%1.0%1.0%193.08 FL 193.58 TC 193.72 FL 194.22 TC 191.90 FL 192.40 TC FS(190.70)FS(190.50)6.1%5.0% 192.10 FL 192.60 TC 193.30 FL 193.80 TC4.5%0.5%193.50 FL 194.00 TC 191.60 FL 1.0%1.0%0.5%194.26 FS 194.76 TC1.5% 191.96 FL 192.46 TC 0" CF 194.26 TC 0" CF 192.48 TC 0" CF 192.95 TC 192.68 FS 8" CF 193.27 TC 8" CF 193.09 TC 193.39 FL FL 193.80 2.0%193.80 FF 2.0%194.20 FF 194.20 FF 193.89 FL 2.0%194.60 FF 194.60 FF 1%2% 194.90 FF 194.90 FF 194.21 FL 194.54 TC 195.20 FF 195.00 FF 195.00 FF 195.20 FF 195.00 FF 2%1% 195.70 FF 191.05 FL FL 194.20 1 2 3 4 6 5 7 PAINT PARKING STALL STRIPING. CONSTRUCT 4" THICK PCC CONCRETE SIDEWALK (WIDTH PER PLAN). CONSTRUCT 6" CURB & GUTTER (TYPE A2-6) PER SPPWC STD 120-2 (W=1.5'). CONSTRUCT 6" PCC CURB (TYPE A1-6) PER SPPWC STD 120-2. CONSTRUCT 3' WIDE PCC RIBBON GUTTER PER SPPWC STD PLAN 122-2. CONSTRUCT 0" PCC CURB (TYPE A1-6) PER SPPWC STD 120-2. GRADING CONSTRUCTION NOTES GRADING CONSTRUCTION NOTES 6 6 3 3 12 4 4 4 4 6 4 4 2 4 6 4 5 4 3 3 3 3 3 4 4 4 4 2 :1 2 :1 FS192.594.9%194.22 FS 1.5%19419 4 1 9 3 19219 3 19419 2191 193 5.0%1 1 1 1 1 1 1 1 1 1 GRADING PLAN 1 3 3 3NEW DWYNEW DWY 8 8 8 8 194.44 FS 193.53 FS 193.09 FS 7 (TYP) 7 (TYP) 193.22 FL 193.72 TC 192.75 FL 193.25 TC 192.36 FL 192.86 TC 192.30 FL 192.80 TC191.62 FL 192.12 TC 192.77 FL 193.27 TC 193.49 FS 192.65 FL 193.15 TC 193.74 FL 194.24 TC 193.43 FS 190.90 FL 191.98 FL 192.48 TC 193.42 FL 193.92 TC 5 (193.37) TC (193.08) TC (192.80) TC (192.63) TC(192.31) TC(192.14) TC(191.93) TC(191.60) TC(191.16) TC(190.99) TC(190.63) TC(190.51) TC2 :1 2 6 9 9 8 9 GEOTECHNICAL ENGINEER'S RECOMMENDATIONS. CONSTRUCT 4" AC OVER 6" AB PAVEMENT STRUCTURAL SECTION PER SCORING PER LANDSCAPE ARCHITECT'S PLAN. SECTION PER GEOTECHNICAL ENGINEER'S RECOMMENDATIONS. COLOR & CONSTRUCT 6" THICK REINFORCED PCC CONCRETE PAVEMENT STRUCTURAL CONSTRUCT 4" ROLLED CURB. 10 CONSTRUCT PCC DRIVEWAY APPROACH PER CITY OF ANAHEIM STD PLAN 115-B. 10 10(190.82) TCDETAIL: CURB RETURN AREA (SW CORNER LINCOLN & SUNKIST) SCALE: 1"=10' 32'32'1941 9 4 194 194193192 1945 5 5 5 5 11 CONSTRUCT CONCRETE DITCH.43'43'43'51'10'10'10'54'10'54'3'2.0% CONSTRUCT 8" PCC CURB (TYPE A1-8) PER SPPWC STD 120-2.12 13 CONSTRUCT TRAFFIC SPEED BUMP. 13 1313 13 XS XS XS XSNO PARKINGNO PARKINGVPIV INIT.DATE DESCRIPTION APP'D DATE SHEET OF SITE ADDRESS: SCALE:DRAWN BY:CHECKED BY: PREPARED BY:OWNER OR DEVELOPER: SOILS ENGINEER: REVISIONS NO. CITY OF ANAHEIM STAT EOF CALIFORNIAREGISTEREDPROFESSIONAL E NGI NEERNo.46568 A R A BRY C OWNJGH JGH 02-NOV-2022 14:38 C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\ORN CorpStds 2005.dscript C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\19467_05_PrelimGrd.dgn J-19467 AS NOTED 7 DATE: PHONE: (949) 442-2442 CONTACT: IRVINE, CA 92614 17991 FITCH NMG GEOTECHNICAL, INC. PHONE: (858) 877-4262 CONTACT: JESSE KLEIST SAN DIEGO, CA 92131 9915 MIRA MESA BLVD, SUITE 100 KB HOME COASTAL 2420-2450 E. LINCOLN AVENUE, ANAHEIM, CA 92806 TENTATIVE TRACT MAP NO. 19237 DATE: 11/2/20223' EVXER TLREVXX X X X MHX EV X X X X X X XSVAR XEVXERTLRV XTPB X TLRXEVX EVX XTPB XTPBUVXWX TLRX EVX XTPBEVX WX XTPB EV X X XT P B UVXT X UVX XT PB E V X EVXAC AC AC AC AC AC ACAC ACACACACACACACAC AC AC AC AC AC AC AC AC AC AC AC ACAC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC EV X X XTPB XTLR UVXUVX XT P B T X X X E V X XT PB X EVX TLRX XTPB X TPB X X X EVX XTPB EVX XTPB TLRX TX XS X X X PROJECT BOUNDARYPROJECT BOUNDARYR IGH T OF WAY RIGHT OF WAY EX IST 8 " C IP WATE R EXIST GAS EX IST TELE PHON E EX IST ELE CTR ICEX IST 16 " D IP WATE R EXIST 16" CCP WATER EX IST 48 " STORM DRA IN EXIST 8" VCP SEWER AREA= 124 SF BIOINFILTRATION W/O UNDERDRAIN BMP #4 AREA= 89 SF BIOINFILTRATION W/O UNDERDRAIN BMP #3 85" WSP WATER TO BE RELOCATED FIRE HYDRANT OPT IC CABLE EX IST F IBER VENT TO BE RELOCATED (MWD) EXIST AIR RELEASE VALVE (MWD) TO REMAIN. STRUCTURE TO REMAIN EXIST AT&T CEV EX IST R IGH T OF WAY PROP R IGH T OF WAY PANEL CONTROL 0 GRAPHIC SCALE 1" = 30' 1530 30 60 90 6 1 2 4 22 4" WATER VALVE6 7 11 12 21 5 END CAP 23 3 4" DOMESTIC WATER MAIN AWWA C900 PVC PIPE 13 14 CLEAN-OUT 22 21 13 13 12 12 3 2 22 5 14 14 31 15 MANHOLE 15 15103'24'90'24'24' 23' 5' 24' 24' E . L INCO LN AV ENU E SUNKIST STREET32 33 34 CURB INLET CLEAN OUT 10'11'24'24'14 2 2 2 23'15'4'5'11'7'6' 5'11'11'6'7'12'7'23' 5' 11'5' 11'11' 12 12 12 12 12 0.5% 1.0%2.0%2.0%2.0%2.0%2.0%2.0%2.0%0.5 %15" SD 190.38 FL 18" SD 189.11 FL 18" SD 188.00 FL 18" SD 186.87 FL 18" SD 188.09 FL 12" SD 185.66 FL 1 .0% 0.5% 0.5% 0.5 %0.5%0 .5% 31 46 46 33 33 33 33 34 34 3 0.5%0.5%0.5%0.5%0.5%320.5% 0 .5% 0 .5% 0. 5 %0.5%12" SD 187.10 FL 32 32 32 32 32 14 46 46 46 43 45 8 WATER AIR RELEASE VALVE 43 35 2424 BROOKS BOX 35 35 35 35 36 6.25'x18.5' MC-3500 STORM TECH 37 36 37 (SUNTREE TECHNOLOGIES MODEL NO: NSBB-HVT-2-4) PRETREATMENT NUTRIENT SEPARATING BAFFLE BOX (SUNTREE TECHNOLOGIES MODEL NO: NSBB-HVT-3-6) PRETREATMENT NUTRIENT SEPARATING BAFFLE BOX38 39 INSTALLED INSIDE GRATE INLET. TRASH CAPTURE DEVICE (BIO CLEAN HYDRA CP- U-3.7) 39 196.10 FF 195.60 FF 195.70 FF 195.70 FF 195.70 FF 195.20 FF 195.70 FF 195.10 FF 195.60 FF 195.60 FF 195.60 FF195.70 FF 195.70 FF 195.70 FF 195.20 FF 195.70 FF 195.00 FF 195.00 FF 194.60 FF 194.60 FF 194.20 FF 194.20 FF 194.80 FF 194.80 FF 193.80 FF 193.80 FF 194.80 FF 194.80 FF 193.80 FF 193.80 FF 195.30 FF 194.80 FF 1 95 .0 0 FF 195 .00 F F 195 .00 F F 195 .00 FF 1 9 4 .80 FF 1 94 .8 0 FF 1 94 .80 FF 1 94 .8 0 F F 1 9 4 .8 0 F F 1 9 5 .0 0 FF 195 .0 0 FF 195 .0 0 FF 1 95 .00 FF 195 .2 0 FF 1 9 5 .7 0 FF 195 .70 F F 195 .7 0 F F 1 9 5 .70 FF 195 .7 0 FF 12" PVC STORM DRAIN PIPE 16 4 7'11'6' 33 UTILITY PLAN SEWER NOTES (PRIVATE) STORM DRAIN NOTES (PRIVATE) WATER NOTES (PRIVATE) 21 10 16 23 23 23 38 POST INDICATOR VALVE (186.41) IE (193.82) RIM EX SEW MH 188.41 IE SEW CO 11 TYP1 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 1 TYP 11 TYP 15" SD 188.25 FL 12" SD 186.60 FL EXIST INLET CONNECT TO 186.90 FL 12" SD 190.56 FL 12" SD 190.72 FL 191.83 FL 194.50 TG 191.59 FL 194.50 TG 186.85 FL 190.82 TG 188.48 FL 192.62 TG 189.04 FL 192.36 TG 180.40 IE 194.29 RIM SEW MH 185.64 IE 191.99 RIM SEW MH 181.04 IE 193.99 RIM SEW MH 183.75 IE 194.78 RIM SEW MH 183.11 IE 195.10 FS SEW CO 184.45 IE 194.49 FS SEW CO185.33 IE 194.08 FS SEW CO 186.18 IE 193.68 FS SEW CO 187.40 IE 193.34 FS SEW CO 187.69 FL 35 189.81 FL 193.40 TG (OUT) 182.10 FL 185.30 FL 192.40 TG 35 186.66 IE SEW CO 16 35 189.22 FL 192.70 TG 0 .5% 0 .5%32 35 191.80 FL 194.50 TG 4 4' 8 13 1.5" BACKFLOW PREVENTER 11'4'4'4' 18" SD 185.56 FL WATER BLOW-OFF ASSEMBLY 2" COPPER WATER MAIN 1" COPPER WATER SERVICE LATERAL AND 1" METER TO A SINGLE 4" WATER MAIN. 2-2" SERVICE LATERAL & METER MANIFOLDED17 WATER NOTES (PUBLIC) 20 6" FIRE SERVICE LATERAL. 20 20 17 17 3 1.5" IRRIGATION LATERAL AND METER.9 4" BACKFLOW PREVENTER 4" SEWER HOUSE LATERAL 6" FIRE SERVICE MAIN AWWA C900 PVC PIPE 6" DCDA BACKFLOW PREVENTER FIRE HYDRANT (PRIVATE) 21 3 3 14 14 14 2 2 2 2 2 2 12 14 23 21 15 15 12 12 12 14 24 RELOCATE MANHOLE VENT (METROPOLITION WATER DISTRICT) 24 1 .0% 14 188.05 IE SEW CO 2 2 9 10 15.8'x70.8' MC-3500 STORM TECH 40 TRENCH DRAIN 40 40 41 4" PVC STORM DRAIN PIPE 418'11'7'42 42 SC-310 STORM TECH (24 CHAMBERS). UNDERGROUND DETENTION SYSTEM. 34 15" PVC STORM DRAIN PIPE43 4315" SD 189.00 FL 44 44 INVERT OF PLATE OPENING TO MATCH INVERT OF 15' OUTLET. INSTALL PLATE ON 15" OUTLET WITH 14.5" DIAMETER OPENING. 7 45 OUTLET PIPE TO CONNECT TO CURB INLET STRUCTURE. 6" PVC STORM DRAIN PIPE. DETENTION SYSTEM UNDERDRAIN 15" SD 189.00 FL 6" SD 188.50 FL 6" SD 188.20 FL 46 18" PVC STORM DRAIN PIPE 32 32 32 32 43 46 18" SD 188.96 FL 18" SD 188.55 FL 18" SD 189.35 FL 35 190.84 FL 194.45 TG 35 189.83 FL 193.52 TG35 189.44 FL 193.13 TG 35 189.03 FL 192.72 TG 195.70 FF 195.45 FF 195.00 FF 195.20 FF 194.90 FF 194.90 FF 16 SEWER LIFT STATION 1.0% 1.0% 177.40 BOT 180.00 IE (IN) 194.60 RIM SEWER LIFT STATION 6" SEWER MAIN 8" SEWER MAIN XS XS XS XS VPIV INIT.DATE DESCRIPTION APP'D DATE SHEET OF SITE ADDRESS: SCALE:DRAWN BY:CHECKED BY: PREPARED BY:OWNER OR DEVELOPER: SOILS ENGINEER: REVISIONS NO. CITY OF ANAHEIM STAT EOF CALIFORNIAREGISTEREDPROFESSIONAL E NGI NEERNo.46568 A R A BRY C OWNJGH JGH 02-NOV-2022 14:38 C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\ORN CorpStds 2005.dscript C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\19467_06_PrelimUtl.dgn J-19467 AS NOTED 7 DATE: PHONE: (949) 442-2442 CONTACT: IRVINE, CA 92614 17991 FITCH NMG GEOTECHNICAL, INC. PHONE: (858) 877-4262 CONTACT: JESSE KLEIST SAN DIEGO, CA 92131 9915 MIRA MESA BLVD, SUITE 100 KB HOME COASTAL 2420-2450 E. LINCOLN AVENUE, ANAHEIM, CA 92806 TENTATIVE TRACT MAP NO. 19237 DATE: 11/2/2022 X X X X MHX EV X X X X X X EV XSVAR XEVXERTLRV XTPB X TLRXEVX EVX XTPB XTPBUVXWX TLRX EVX XTPBEVX XTPB EV X X XT P B UVXT X UV X XT PB E V X EVXEVXER TLRAC AC AC AC AC AC ACAC ACACACACACACACAC AC AC AC AC AC AC AC AC AC AC AC ACAC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC AC 191 192 193PROJECT BOUNDARYPROJECT BOUNDARYRIGHT OF WAY EXIST SCREEN WALLEXIST SCREEN WALLTO BE RELOCATED FIRE HYDRANT EXIST 16" CCP WATER 85" WSP WATER TO REMAIN EXISTING FH EX IST 16 " D IP WATE R EX IST 8 " C IP WATE R R IGH T OF WAY EX IST R IGH T OF WAY 6" DCDA PROPOSED 6" DCDA PROPOSED EXIST RIGHT OF WAY TO REMAIN. FIRE HYDRANT INIT.DATE DESCRIPTION APP'D DATE SHEET OF SITE ADDRESS: SCALE:DRAWN BY:CHECKED BY: PREPARED BY:OWNER OR DEVELOPER: SOILS ENGINEER: REVISIONS NO. CITY OF ANAHEIM STAT EOF CALIFORNIAREGISTEREDPROFESSIONAL E NGI NEERNo.46568 A R A BRY C OWNJGH JGH 02-NOV-2022 14:38 C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\ORN CorpStds 2005.dscript C:\RICK\Projects\C19000\19467_KB-Lincoln\Civil\PlanSets\Entitlement Plans\19467_07_Fire.dgn J-19467 AS NOTED 7 DATE: PHONE: (949) 442-2442 CONTACT: IRVINE, CA 92614 17991 FITCH NMG GEOTECHNICAL, INC. PHONE: (858) 877-4262 CONTACT: JESSE KLEIST SAN DIEGO, CA 92131 9915 MIRA MESA BLVD, SUITE 100 KB HOME COASTAL 2420-2450 E. LINCOLN AVENUE, ANAHEIM, CA 92806 TENTATIVE TRACT MAP NO. 19237 DATE: 11/2/2022XS XS XS XSNO PARKINGNO PARKINGVPIV 7 E . L INCO LN AV ENU E SUNKIST STREET103'24'18'90'24'11'24' 24' 24'24'1+00 2+00 3+ 00 4+ 00 5+00 6+00 7+ 00 1+002+003+0010'24'18'10'24'18'10'21.5'1 5' 15' 20'10.39'103'50'53'16'34'8'53'50'34'8'4'55'45' 45' 13'32' 32'13' 20'20'20' 24' UN IT 1 UN IT 2 UN IT 3 UN IT 4 UN IT 5 UN IT 6 UN IT 7 UN IT 8 UN IT 9 UN IT 10 UN IT 11 UN IT 12 UN IT 13 UN IT 14 UN IT 15 UN IT 16 UN IT 17 UN IT 18 UN IT 19 UNIT 20 UNIT 21 UNIT 22 UNIT 23 UNIT 24 UNIT 25 UNIT 26 UNIT 27 UNIT 28 UNIT 29 UNIT 30UNIT 31 UNIT 32 UNIT 33 UNIT 34 UNIT 35 UNIT 39 UNIT 36 UNIT 37 UNIT 38 UNIT 40 UNIT 41 UNIT 42 UNIT 43UNIT 44 UNIT 45 UNIT 46 UNIT 47UNIT 50 UNIT 51 UNIT 52 UNIT 53UNIT 54 UNIT 55 UNIT 56 UNIT 57 UNIT 58UNIT 59 UNIT 60 UNIT 61 UNIT 62 UNIT 63UNIT 64 UNIT 65 UNIT 66 UNIT 67 UNIT 68UNIT 69 UNIT 70 UNIT 71 UNIT 72 UNIT 73 UNIT 74 UNIT 75 UNIT 76 UNIT 77 UNIT 78UNIT 79 UNIT 80 UNIT 81 UNIT 82 UNIT 83 15 '11.5'10'UNIT 48UNIT 49 20'21.4' MIN 35.3' MIN 28.5' MIN 20' MIN 28.5' MIN 20' MIN 36.5' MIN 28' MIN 23.5' MIN 30.2' MIN 30.4'37.7'TRACT BOUNDARY UNIT #UNIT NUMBER LEGEND FIRE TRUCK TURNING MOVEMENT BUILDING NUMBER R=20' R=40'NEW DWY24'NEW DWY 24 ' FIRE PLAN11'PROPOSED FIRE HYDRANTS EXISTING FIRE HYDRANTS DESIGNATED FIRE LANE FIRE SERVICE LINE POST INDICATOR VALVE FS FIRELANE 24'0 GRAPHIC SCALE 1" = 30' 1530 30 60 90 BU ILD ING 1 BU ILD ING 2 BU ILD ING 3 BUILDING 4BUILDING 5 BUILDING 6BUILDING 7BUILDING 8BUILDING 9BUILDING 10 BUILDING # AA PIV 2) BUILDINGS 1-4 FIRE SPRINKLER SYSTEM PER NFPA 13D. 3) BUILDINGS 5-10 FIRE SPRINKLER SYSTEM PER NFPA 13. 4) ON-SITE FIRE LINE AND APPURTENANCES ARE PRIVATE AND PER NFPA 24.15'5' NEW SDWKSETBACKR/W DEDICATIONPROPOSEDFIRE LANEFIRE LANEFIRE LANEFIRE LANE55' SETBACKFIRE LANE FIRE LANE FIRE LANEFIRE LANE LOAD OF 78,000 LBS AND SURFACED TO PROVIDE ALL-WEATHER ACCESS. 5) ALL ON-SITE DESIGNATED FIRE LANES WILL BE DESIGNED TO SUPPORT A FIRE NOTES SPRINKLER SYSTEMS. 1) ALL BUILDINGS ARE 3-STORY MULTI-FAMILY RESIDENTIAL WITH AUTOMATIC TRAVEL PATH FROM FIRE HYDRANT DISTANCE 300' 110' 250' 300' 300' 300' 300' 260' 250'10'5'5'33'270' 300' LINCOLN A V E .S. SUNKIST STREET1 2 3 456789 10 A A A A A A A A A 40'31'PROPOSED PLANT PALETTE STREET & PARKING TREES BOTANICAL NAMESYMBOL COMMON NAME PODOCARPUS GRACILIOR KOELREUTERIA PANICULATA PISTACIA CHINENSIS PINUS CANARIENSIS MAGNOLIA SPP. FERN PINE GOLDENRAIN TREE CHINESE PISTACHE 4 CANARY ISLAND PINE 13 MAGNOLIA JACARANDA SPP. OLEA 'WILSONII' MAGNOLIA G. 'RUSSET' MULTI TRUNK TREES (36" - 48" BOX JACARANDA SPP. 8 OLIVE SPP. RUSSET MAGNOLIA THEME / SCREEN TREES (15 GAL - 24" BOX) MONDEL PINE BOTTLE TREE BRISBANE BOX 25 PINUS ELDARICA BRACHYCHITON POPULNEUS LOPHOSTEMON CONFERTUS ACCENT TREES (24" - 36" BOX) ARBUTUS HYBRID PALO VERDE 13 AFRICAN SUMAC ORNAMENTAL PEAR FLOWERING PLUM 31 ARBUTUS 'MARINA' CERCIDIUM ‘DESERT MUSEUM’ RHUS LANCEA PYRUS C. 'CHANTICLEER' PRUNUS C. 'KRAUTER VESUVIUS' PALM TREES (24" - 36" BOX) QUEEN PALM 21 DATE PALM SYAGRUS ROMANZOFFIANUM PHOENIX DACTYLIFERA VERTICAL ACCENT TREES (15 GAL - 24" BOX) JUNIPER SPP. CYPRESS SPP. 5 LONG LEAFED YELLOWWOOD JUNIPERUS SPP. CUPRESSUS SPP. PODOCARPUS 'HENKELII' (COLUMNAR) RHAPHIOLEPIS I. 'MAJESTIC BEAUTY' PHOTINIA FRASERI PRUNUS C. 'BRIGHT N TIGHT' PATIO ACCENT TREES (100% - 15 GAL) INDIAN HAWTHORN 25 N.C.N. FLOWERING PLUM VAR. 26 CANARY ISLAND PINE (7) CALIFORNIA PEPPER (1) SUNKIST STREET TREES (2) EXISTING TREES (TO REMAIN IF POSSIBLE) QTY. TURF - MARATHON IIe SOD AGAVE SPP. ARBUTUS UNEDO 'COMPACTA' BOUGAINVILLEA SPP. BUXUS SPP. CALLISTEMON 'LITTLE JOHN' DIANELLA DIETES SPP. DIOSMA PULCHRUM DODONEA V. 'PURPUREA' ELAEAGNUS P. VARIEGATA GAZANIA SPP. GELSEMIUM SEMPERVIRENS GREVILLEA LANIGERA GREWIA OCCIDENTALIS HEMEROCALLIS SPP. HESPERALOE PARVIFLORA JUNIPERUS SPP. LANTANA 'YELLOW' LEONOTIS LEONORUS LIGUSTRUM J. 'TEXANUM' PHORMIUM SPP. PITTOSPORUM SPP. RAPHIOLEPIS SPP. ROSA ICE BERG SPP. ROSMARINUS SPP. SALVIA SPP. SEDUM SPP. SENECIUM MANDRALISCAE TRACHELOSPERMUM JASMINOIDES COMMON H.O.A. AREA SHRUBS / VINES / GROUNDCOVER (40% 5 gal, 60% 1 gal. min, with flatted groundcover) such as: AGAVE DWARF STRAWBERRY TREE BOUGAINVILLEA - N.C.N. BOXWOOD SPP. BOTTLE BRUSH SPP. FLAX LILY FORTNIGHT LILY BREATH OF HEAVEN HOPSEED BUSH N.C.N. GAZANIA - N.C.N. CAROLINA JESSAMINE GREVILLEA - N.C.N. LAVENDER STARFLOWER DAYLILY SPP. YUCCA JUNIPERUS SPP. NEW GOLD LANTANA LION'S TAIL JAPANESE PRIVET NEW ZEALAND FLAX SPP. PITTOSPORUM SPP. RAPHIOLEPIS - N.C.N. FLORIBUNDA ROSE ROSEMARY SPP. SAGE SPP. STONECROP BLUE CHALKSTICKS STAR JASMINE A A AA 0 SCALE - 1" = 30'-0" 15' 30' 60' 90'NORTH COMMUNITY GARDEN SEE SEPARATE ENLARGEMENT PLAN COMMUNITY DOG PARK SEE SEPARATE ENLARGEMENT PLANEXISTING PUBLIC UTILITY EASEMENT EXISTING MASONRY WALL ON WEST P.L. TO REMAIN HANDICAPPED PARKING STALL - TYP. TOT-LOT & FITNESS AREA COMMUNITY OPEN SPACE AREA SEE ENLARGEMENT SHEET DRIVE LANE W/ ENHANCED PAVING - TYP. ENHANCED ENTRY PAVING - TYP. (STAMPED ASPHALT BY STREET PRINT) 15' - 20' SETBACK LINEA 5256 S. Mission Road, Ste 404 Bonsall, CA 92003 760.724.1198ARCHITECTURE FEBRUARY 11, 2022KB HOME 9915 MIRA MESA BLVD., STE 100 SAN DIEGO, CA 92131 858.877.4256 ANAHEIM, CA LINCOLN & SUNKIST TOWNHOMES 28924 OLD TOWN FRONT STREET, SUITE 202 TEMECULA, CA 92590 P (844) WEILAND, XT 701 F (619) 675-3426 EMAIL - KLONIGRO@W-D-G.COM CORPORATE OFFICE 291 SIERRA WAVE SWALL MEADOWS, CA 93514 OVERALL LANDSCAPE CONCEPT PLAN LC-01 3' HEIGHT VINYL FENCE AT PRIVATE FRONT YARDS - TYP. (BLDG.'S 1, 2, 3 AND 5) STREET TREES - TYP. ACCENT/ THEME TREES - TYP. 3' HT. VINYL FENCE HANDICAPPED PARKING STALL - TYP. ENHANCED ENTRY PAVING - TYP. (STAMPED ASPHALT BY STREET PRINT) ENHANCED ASPHALT PAVING - TYP. (STAMPED ASPHALT BY STREET PRINT) EXISTING AND PROPOSED R.O.W. -TYP. EXISTING AND PROPOSED R.O.W. -TYP. EXISTING AND PROPOSED R.O.W. -TYP. EXISTING AND PROPOSED R.O.W. -TYP. ACCESSIBLE PATH OF TRAVEL FROM THE PUBLIC R.O.W. THROUGHOUT THE SITE (SEE ARCH. PLANS SHT. A-3) ENHANCED 'STREET PRINT' PATH OF TRAVEL - TYP. PROPOSED MAILBOX AND PARCEL BOX LOCATIONS SEE ENLARGEMENT SHEET 15' - 20' SETBACK LINE 7'x50' L.O.S. (CITY DET. 115-B) CLEAR ZONE LANDSCAPING SHALL NOT EXCEED THE 24" MAX. HEIGHT LIMITATION (BOTH ENTRIES) 25'x25' L.O.S. CLEAR ZONE AT INTERSECTION FROM ULTIMATE ROW. LANDSCAPING SHALL NOT EXCEED THE 24" HEIGHT LIMITATION ENHANCED METAL VINE TRELLIS (PAINTED DARK BROWN) WITH 5 GAL. VINE - TYP. (SEE ARCHITECTURE PLANS) ENHANCED METAL VINE TRELLIS (PAINTED DARK BROWN) WITH 5 GAL. VINE - TYP. (SEE ARCHITECTURE PLANS) PROPOSED RETAINING WALL AT PARKING EDGE - TYP. UNDERGROUND STORM DRAIN FILTRATION TANKS PER CIVIL PLANS EXISTING AT&T CABINET AND CONCRETE PAD TO REMAIN PER CIVIL PLANS 7'x50' L.O.S. (CITY DET. 115-B) CLEAR ZONE LANDSCAPING SHALL NOT EXCEED THE 24" MAX. HEIGHT LIMITATION (BOTH ENTRIES) ADA UNIT - 9 TOTAL PROPOSED CONCRETE OVERFLOW SWALE PER CIVIL PLANS PROPOSED CONCRETE OVERFLOW SWALE PER CIVIL PLANS WATER QUALITY BASIN - TYP. OVERFLOW WATER QUALITY TANKS PER CIVIL PLANS PROPOSED 1.5" IRRIGATION SERVICE LINE, WATER METER & BACKFLOW PREVENTER - SEE CIVIL UTILITY PLAN NUMBER 9 & 10 31' TO EXISTING CANARY ISLAND PINE UTILITY SCREENING EXHIBIT SCALE: 1" = 10'-0" WATER AIR RELEASE VALVE - TYP. SCREEN W/ LANDSCAPE A/C SCREEN - 3' VINYL LATTICE SCREEN ADJACENT TO HARDSCAPE - TYP. MEDIUM HT. SHRUB LANDSCAPE SCREENING - TYP. (A/C UNITS & ADDITIONAL ABOVE-GROUND UTILITIES - COORD. W/ CIVIL) W/ LANDSCAPE SCREENING 40' TREE CLEARANCE PER CITY STD. 530-A Rev. 8/18/22, 9/13/22 EXISTING MASONRY WALL ON SOUTH P.L. TO REMAIN COMMUNITY DOG PARK COMMUNITY GARDEN COMMUNITY OPEN-SPACE AREA BENCH SEATING & TRASH RECEPTACLES - TYP. RAISED GARDEN BOXES - TYP. MULCH BINS - TYP. CONCRETE WALK ARTIFICIAL TURF TUBULAR STEEL FENCE WITH GATE DOGGY BAG PEDESTAL BENCH SEATING & TRASH RECEPTACLES - TYP. OPEN-SPACE LAWN COMMUNITY SEATING AREA W/ LOUNGING FURNITURE OVER SYNTHETIC TURN. COMMUNITY OPEN-SPACE AREA WITH GAS/ PROPANE BBQ AND SHADE STRUCTURE WITH TABLE AND CHAIRS SEATING TOT-LOT & FITNESS AREA WITH BENCH SEATING 5256 S. Mission Road, Ste 404 Bonsall, CA 92003 760.724.1198ARCHITECTURE FEBRUARY 11, 2022KB HOME 9915 MIRA MESA BLVD., STE 100 SAN DIEGO, CA 92131 858.877.4256 ANAHEIM, CA LINCOLN & SUNKIST TOWNHOMES 28924 OLD TOWN FRONT STREET, SUITE 202 TEMECULA, CA 92590 P (844) WEILAND, XT 701 F (619) 675-3426EMAIL - KLONIGRO@W-D-G.COM CORPORATE OFFICE 291 SIERRA WAVE SWALL MEADOWS, CA 93514 ENHANCED STAMPED ASPHALT PAVING AT COMMON AREAS - TYP. CONCRETE MOW CURB - TYP. ENLARGEMENT CONCEPT PLAN LC-02 0 5' 10' 20' 30' SCALE - 1" = 10'-0" NORTH CONCRETE WALK THROUGH COMMON AREA - TYP.CONCRETE WALK THROUGH COMMON AREA - TYP. COMMUNITY MAILBOX AREA (2'X21' CONCRETE PAD) WITH 20 MIN. GREEN CARRIER & RESIDENCE PARKING - TYP.WALL-MOUNTED VINE TRELLIS - TYP. (FINAL LOCATIONS PER ELEVATIONS) ENTRY WALK WITH ADA RAMP ENTRY WALK WITH ADA RAMP ENHANCED STAMPED ASPHALT PAVING AT COMMON AREAS - TYP. MULTI-TRUNK SPECIMEN TREES - TYP. SPECIMEN PALM TREES - TYP. CURVED SEAT WALLS - TYP. OVERFLOW WATER QUALITY TANKS PER CIVIL PLANS Rev. 8/18/22, 9/13/22 CANOPY TREE VERTICAL PALM VERTICAL TREES ACCENT TREE ACCENT SHRUBS GROUNDCOVERS HEDGE SHRUBS LOW - MEDIUM SHRUBS VINES 5256 S. Mission Road, Ste 404 Bonsall, CA 92003 760.724.1198ARCHITECTURE FEBRUARY 11, 2022KB HOME 9915 MIRA MESA BLVD., STE 100 SAN DIEGO, CA 92131 858.877.4256 ANAHEIM, CA LINCOLN & SUNKIST TOWNHOMES 28924 OLD TOWN FRONT STREET, SUITE 202TEMECULA, CA 92590 P (844) WEILAND, XT 701 F (619) 675-3426 EMAIL - KLONIGRO@W-D-G.COM CORPORATE OFFICE 291 SIERRA WAVE SWALL MEADOWS, CA 93514 PLANT PALETTE LC-03 Rev. 8/18/22, 9/13/22 Luminaire ScheduleTypeSymbolQtyLabelArrangementLLFDescriptionLum. LumensLum. WattsTotal WattsA110ANP EQ111 T3 (Post Top Light)Single0.920LIGHT: EQ111-1-E030LD-T3-30K-HSS150-1-FM3-72POLE: BD3STLS12-7-BDC-72340330300A22ANP EQ111 T5 (Post Top Light)Single0.920LIGHT: EQ111-1-E030LD-T5-30K-HSS150-1-FM3-72POLE: BD3STLS12-7-BDC-7232763060B111ANP EQ BL0121 (Bollard)Single0.920BL0121-CL-A018LD4-T2-30K-72165818198T14Teron Chaparral (Trellis Light)Single0.920CHL-L5.3-120/277-MFL-BZ-30K4835.321.2W1133Typical Building LightSingle0.920MAXIM 65753 (Placeholder)39181064Calculation SummaryLabelCalcTypeUnitsAvgMaxMinAvg/MinVEHICLE HARDSCAPEIlluminanceFc0.562.40.15.60COMMON SPACEIlluminanceFc3.9525.20.139.50LINCOLN & SUNKIST LIGHTING CONCEPTUAL PLAN Feb 07, 202201of 05SUMMARIES AND SCHEDULESSHEET INDEX1 SUMMARIES & SCHEDULES2 LIGHTING PLAN3 SPECIFICATION: SITE LIGHT4 SPECIFICATION: BOLLARD LIGHT5 SPECIFICATION: TRELLIS LIGHTSITE LOCATIONANAHEIM, CAKEy MAPNʒTʒSʒLINCOLN AVES SUNKIST STREETSHEET 2MAKE: TERON LIGHTINGMODEL: CHAPARRAL BULLET LIGHT ˫ ɾʖ AʒFʒGʒXTy: 4wATTAGE: 5ʒ3SPEC: SHEET 05MAKE: ANP LIGHTINGMODEL: BL0121 BOLLARD ˫ 3ʒ5ʖ AʒFʒGʒXTy: 11wATTAGE: 1ɾ ˫ 3000KSPEC: SHEET 04MAKE: ANP LIGHTINGMODEL: EX111 POST TOP ˫ 14ʖ AʒFʒGʒXTy: 12wATTAGE: 30 ˫ 3000KSPEC: SHEET 03 0.43.51.50.30.74.40.40.21.810.915.13.00.30.21.712.517.63.00.51.62.07.611.33.00.50.54.725.210.00.8 0.3 2.514.413.32.20.41.47.812.03.20.50.32.614.912.72.00.30.86.519.45.90.80.40.10.40.40.30.50.60.10.30.20.20.20.20.20.20.55.91.40.30.20.31.10.86.63.40.60.10.11.04.05.94.32.63.11.21.83.13.31.07.92.34.18.20.4 1.0 1.8 1.2 1.8 1.2 0.61.2 1.8 1.2 1.9 1.20.3 0.3 0.6 1.4 1.7 1.4 1.7 0.8 0.3 0.20.2 0.4 1.1 1.8 1.2 1.8 1.1 0.5 0.30.2 0.2 0.5 1.3 1.8 1.2 1.8 1.0 0.40.3 0.7 1.3 1.3 1.4 0.9 0.50.9 1.4 1.4 1.4 0.90.3 0.3 0.5 1.0 1.4 1.4 1.2 0.6 0.3 0.10.2 0.3 0.8 1.3 1.4 1.3 0.8 0.4 0.30.2 0.2 0.4 0.9 1.4 1.4 1.3 0.7 0.40.2 0.2 0.3 0.4 0.6 0.60.60.4 0.3 0.3 0.4 0.6 0.7 0.6 0.5 0.6 1.1 1.2 1.0 1.2 0.7 0.3 0.2 0.3 0.5 0.6 0.6 0.5 0.3 0.2 0.1 0.1 0.1 0.2 0.4 0.6 0.6 0.6 0.4 0.3 0.2 0.4 0.8 1.2 0.9 1.2 0.8 0.4 0.2 0.2 0.3 0.4 0.6 0.6 0.6 0.4 0.3 0.3 0.7 1.5 1.6 1.6 1.40.4 0.4 0.3 0.3 0.3 0.2 0.2 0.2 0.2 0.2 0.2 0.3 0.3 0.3 0.3 0.4 0.8 1.1 1.2 0.9 0.6 0.3 0.2 0.2 0.2 0.3 0.3 0.3 0.2 0.2 0.1 0.1 0.1 0.2 0.3 0.3 0.3 0.3 0.2 0.2 0.2 0.3 0.7 1.0 1.1 1.0 0.6 0.3 0.2 0.1 0.1 0.2 0.3 0.3 0.3 0.2 0.2 0.3 0.5 0.9 1.1 1.1 0.81.1 0.8 0.4 0.2 0.2 0.1 0.10.2 0.2 0.41.0 0.6 0.60.5 0.3 0.30.5 0.3 0.30.7 0.7 0.5 0.4 0.50.5 0.3 0.31.8 1.3 0.6 0.3 0.20.2 0.3 0.71.5 0.5 0.82.1 0.4 0.62.4 0.5 0.50.4 0.3 0.3 0.81.4 0.4 0.51.2 1.3 0.6 0.30.4 0.3 0.81.0 0.5 0.71.1 0.5 0.61.1 0.5 0.50.2 0.3 0.81.0 0.4 0.41.8 1.3 0.6 0.40.6 0.4 0.91.1 0.5 0.71.3 0.5 0.71.4 0.5 0.60.20.3 0.81.1 0.4 0.61.1 0.8 0.4 0.30.7 0.4 0.60.6 0.4 0.50.7 0.4 0.50.8 0.4 0.40.1 0.2 0.50.6 0.3 0.40.5 0.4 0.3 0.30.8 0.4 0.60.8 0.3 0.50.9 0.4 0.51.3 0.4 0.40.1 0.2 0.50.8 0.3 0.60.2 0.2 0.2 0.20.5 0.3 0.50.6 0.3 0.40.7 0.4 0.40.7 0.4 0.40.1 0.2 0.40.6 0.3 0.40.2 0.2 0.2 0.20.7 0.4 0.70.9 0.4 0.61.1 0.4 0.61.7 0.5 0.50.1 0.2 0.70.9 0.4 0.50.3 0.2 0.2 0.30.5 0.4 0.71.0 0.4 0.61.1 0.4 0.61.6 0.5 0.60.1 0.2 0.70.9 0.4 0.40.6 0.5 0.3 0.30.9 0.4 0.60.8 0.4 0.60.9 0.4 0.50.9 0.4 0.50.1 0.2 0.60.7 0.4 0.51.4 1.0 0.5 0.40.8 0.4 0.71.0 0.4 0.61.2 0.5 0.71.4 0.5 0.40.2 0.1 0.2 0.71.0 0.4 0.41.8 1.4 0.7 0.40.7 0.4 0.60.7 0.3 0.50.8 0.4 0.61.0 0.4 0.20.2 0.1 0.2 0.2 0.50.7 0.3 0.51.3 1.4 0.7 0.40.8 0.3 0.60.7 0.3 0.40.8 0.3 0.52.3 0.4 0.20.1 0.2 0.3 0.2 0.2 0.2 0.3 0.3 0.4 0.60.7 0.3 0.51.8 1.2 0.6 0.40.6 0.3 0.30.4 0.2 0.2 0.2 0.2 0.2 0.3 0.3 0.5 0.4 1.10.2 0.50.9 0.6 0.4 0.30.1 0.1 0.1 0.2 0.2 0.2 0.3 0.3 0.3 0.5 0.50.3 0.3 0.2 0.21.9 0.2 0.2 0.2 0.2 0.2 0.2 0.4 0.3 0.7 0.60.2 0.2 0.1 0.10.1 0.1 0.1 0.1 0.1 0.2 0.2 0.2 0.4 0.4 0.70.2 0.1 0.1 0.10.1 0.1 0.1 0.1 0.2 0.2 0.3 0.3 0.5 0.4 0.90.3 0.2 0.2 0.1 0.10.1 0.1 0.1 0.1 0.1 0.2 0.2 0.3 0.3 0.5 0.50.7 0.5 0.3 0.2 0.1 0.10.1 0.1 0.1 0.1 0.1 0.2 0.2 0.3 0.4 0.5 0.71.6 1.1 0.5 0.2 0.1 0.1 0.1 0.2 0.2 0.2 0.3 0.4 0.51.6 1.4 0.60.3 0.30.30.4 0.5 0.61.5 1.4 0.6 0.3 0.51.6 1.2 0.5 0.2 0.10.7 0.6 0.4 0.2 0.10.4 0.4 0.3 0.3 0.20.3 0.6 0.6 0.5 0.31.5 1.0 0.41.6 1.3 0.61.4 1.3 0.6LINCOLN & SUNKIST LIGHTING CONCEPTUAL PLAN Feb 07, 202202of 05LIGHTING PLAN PRIVATE STREETLINCOLN AVENUES SUNKIST STREETANy CHANGE OR DEVIATION FROM THE LIGHTING SPECIFICATIONSON PLAN SHALL INVALIDATE THIS PHOTOMETRIC ANALySISʒNOTE:0(IN FEET)20 1020 401 INCH = 20 FEETPRIVATE STREETPROPERTY LINEMAKE: ANP LIGHTINGMODEL: BL0121 BOLLARD ˫ 3ʒ5ʖ AʒFʒGʒXTy: 11wATTAGE: 1ɾ ˫ 3000KSPEC: SHEET 04MAKE: TERON LIGHTINGMODEL: CHAPARRAL BULLET LIGHT ˫ ɾʖ AʒFʒGʒXTy: 4wATTAGE: 5ʒ3SPEC: SHEET 05MAKE: ANP LIGHTINGMODEL: EX111 POST TOP ˫ 14ʖ AʒFʒGʒXTy: 12wATTAGE: 30 ˫ 3000KSPEC: SHEET 03 LINCOLN & SUNKIST LIGHTING CONCEPTUAL PLAN Feb 07, 202203of 05SPECIFICATION: SITE LIGHTMAKE: ANP LIGHTINGMODEL: EX111 POST TOP ˫ 14ʖ AʒFʒGʒXTy: 12wATTAGE: 30 ˫ 3000KSPEC: SHEET 03 LINCOLN & SUNKIST LIGHTING CONCEPTUAL PLAN Feb 07, 202204of 05SPECIFICATION: BOLLARD LIGHTMAKE: ANP LIGHTINGMODEL: BL0121 BOLLARD ˫ 3ʒ5ʖ AʒFʒGʒXTy: 11wATTAGE: 1ɾ ˫ 3000KSPEC: SHEET 04 LINCOLN & SUNKIST LIGHTING CONCEPTUAL PLAN Feb 07, 202205of 05SPECIFICATION: TRELLIS LIGHTMAKE: TERON LIGHTINGMODEL: CHAPARRAL BULLET LIGHT ˫ ɾʖ AʒFʒGʒXTy: 4wATTAGE: 5ʒ3SPEC: SHEET 05 Summary of the community meetings: KB Home held a community meeting on Tuesday, October 18th from 6-8PM at Abraham Lincoln Elementary School. The meeting was open house style with several display boards set up on easels. Team members in attendance included representatives from KB Home, the architect, the civil engineer, and myself. Drinks and pastries were available for attendees. Mailers were sent to all addresses within a 2,000 foot radius of the project site. About a dozen people (12-15) attended the meeting, the majority of whom were from the neighborhoods north of Lincoln. Two people were from the residential neighborhood just south of the project site and one person was from a neighborhood further south on Sunkist. The comments we heard are summarized as follows: •Parking – Nearly every community member shared a concern about the existing parking situation on their neighborhood streets. Some people were satisfied that the project will satisfy the code-required parking, but some people were not convinced that enough parking would be provided and firmly believe that more people in the area will mean more cars parking on their streets. Most people were bothered by the impact of the existing apartments and renters overflowing into their streets for parking. We found that it was helpful to tell people that the project will provide nearly a 1:1 ratio of bedrooms (240) to parking spaces (237). One person was adamant that one parking space per bedroom will not be sufficient and firmly believes there will be several people living in each bedroom. •Just Looking – Second to parking, the majority of people were simply interested to see what was going to be built. They have been living near a vacant site for a few years and many just liked the idea of anything going in that would help make the site look better. People did not object to the three-story townhomes, although some people felt that it was “a lot of stairs”. We shared unit count, height, SF of homes, bed/bath/parking. Most people were happy with the housing product, even though some would not personally live in that type of product. All were complementary of the aesthetics of the design and we did not hear anyone voice a direct concern about “how the community looked.” •Price – Several people inquired about home prices. They also voiced that they felt the project would increase/strengthen their property value. Those that asked about affordable housing were pleased that there would not be affordable housing within the community. They were also glad to hear the townhomes will be for sale and not rentals. •Timing – Many wanted to know the timing of when development/construction will begin. •Traffic – A few people shared concerns about traffic, mostly detailing how they deal/navigate traffic today. Most were pleased that the right turn lane on eastbound Lincoln will be lengthened. Many were pleased that the community will be right out only at the exits, which helps the northbound traffic on Sunkist approaching Lincoln. One person voiced frustration with traffic due to proximity to the 57 ramps, saying he’s tried to bring up his concerns with the city before only to hit a dead end once he gets referred to public works. •Amenities – A couple people asked about the amenities in the community and they seemed to like the dog park area on the south. A couple people wanted to know if the site was gated. •One person who owns a home that is immediately adjacent to the property inquired about the wall height on the southern boundary. •One person really enjoyed reviewing/studying the plans and asked questions as she went along from a range of topics including those listed above but also road width, circulation, and fencing. •One person mentioned recent issues with a homeless population congregating around the gas station at the southeast corner of Lincoln and Sunkist. They seemed encouraged that the project might help clear that up (as opposed to the current/vacant state of the site). ATTACHMENT NO. 6 I attended the District 5 Community Meeting on October 19th at the Anaheim United Methodist Church. Jason Perez with Neighborhood Services introduced me as the last item on the agenda and let attendees know that I would be available for questions after the meeting. I spoke with eight people and their comments were as follows: • Four people expressed concern about the existing left turn on green arrow from westbound Lincoln onto southbound Sunkist. They said it’s common to wait through a few light cycles to make the turn during rush hour. They expect this left turn on green arrow to become more impacted with the project. They asked if the left turn arrow will have a longer light cycle or if left turns will be allowed on green, not just on green arrow. • Most people asked about the on-site parking, but none expressed concern over the number of parking spaces proposed. They seemed satisfied with each unit being provided a two-car garage, plus additional surface parking. • One person was concerned that left turns out of the project site would be allowed and they were happy to hear that both driveways will be restricted to right turn in, right turn out. • A few people were relieved to hear it is a for-sale project instead of an apartment project. • One person asked about the setbacks along Lincoln and wanted to make sure landscaping would be provided along Lincoln. • One person asked about the open space provided on site and liked the idea of a community garden. • Two people asked if a traffic study was completed and they believe the site will have more traffic than the former EDD buildings. ATTACHMENT NO. 7 RM-4 BARKLEY APARTMENTS 161 DU RM-4 THE CORSICAN APARTMENTS 124 DU RM-4 HAMPSHIRE SQUARE II APARTMENTS 209 DU C-G CAR WASH RS-2 SINGLE FAMILY RESIDENCE RS-2 SINGLE FAMILY RESIDENCE RS-2 SINGLE FAMILY RESIDENCE RS-2 SINGLE FAMILY RESIDENCE RS-2 SINGLE FAMILY RESIDENCE RS-2 SINGLE FAMILY RESIDENCE C-GDEV2021-001 80STATE OF CALIFORNIA EMPLOYMENT DEVELO PMENT DEPARTMENT RS-2 SINGLE FAMILY RESIDENCE RS-2SINGLE FAMILY RESIDENCERS-2 SINGLE FAMILY RESIDENCE RS-2 SINGLE FAMILY RESIDENCERS-2 SINGLE FAMILY RESIDENCE RS-2 SINGLE FAMILY RESIDENCE C-G SERVICE STATION S SUNKIST STE LINCOLN AVE E PARAD ISE RD S PEREGRINE STS COLT STE WA RD TER E P OWHATA N AVE E WESTPORT DR E WESTPORT CIRS PARADISE LNE. LINCOLN AVE E. SOUTH ST S. SUNKIST STS. RIO VISTA STE. LA PALMA AVE E . B R O A D W A Y N. RIO VISTA ST57 FWY57 FWYPr o j e c t L o c a t i o n : 2 4 2 0 - 2 4 5 0 E a st L in c o ln Av e n u e D E V N o . 2 0 2 1 -0 0 1 8 0 Subject Property APN: 083-731-18 083-731-19 °0 50 100 Feet Aeria l Ph oto : Ma y 2 02 1