71R-508
. ,j.....,
RESOLUTION NO. 71R-508
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE COMPLETION
A1~D THE FURNISHING OF ALL PLANT, LABOR,
SERVICES, MATERIALS AND EQUIPMENT AND ALL
UTILITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND WATER, AND THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEMENT, TO WIT:
THE ANAHEIM STADIUM AND CONVENTION CENTER
PARKING LOT AND ROADWAY RES UlU'ACING , IN THE
CITY OF ANAHEIM, WORK ORDER ~OS. 777 AND 778.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
printed, published and circulated in the City of Anaheim, to
wit: The Anaheim Bulletin, on the 2nd and the 9th days of
Seotember , 19 71 , a notJ.ce J.nv1tJ.ng sealed
proposals for furnishing the following:
All plant, labor, services, materials and equipment, and
all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct
and complete in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings
therefor on file in the Office of the City Engineer or
City Clerk of the City of Anaheim, the following public
tmprovement, to wit:
The Anaheim Stadium and Convention Center parkinq lot and
roadway resurfacing, in the City of Anaheim, consisting
of the furnishing and application of seal coat on parking
lots and roadways of the Anaheim Stadium and Convention
Center; and appurtenant work as more particularly set forth
in the plans and specifications on file in the Office of
the City Clerk or City Engineer, Work order Nos. 777 and 778.
in accordance with the desiqns, plans, profiles and specifica-
tions prepared by the Department of Public Works
and the notice inviting sealed proposals, which said notice
speci~i~d that sea~ed proposals as spe"cified in said notice would
be rece1ved up unt11 2:00 o'clock P.M. of the l6th day of
September , 19 71 , and which said notice did state and
declare that, pursuant to the provisions of Section 1770 of the
Labor Code, the City Council of the City of Anaheim had ascer-
tained the prevailing rate of wages for each type of labor needed
to execute said contract, and did state that the prevailing hourly
wage scale so ascertained was on file in the Office of the City
Clerk; and
,
-1-
......
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particu-
larly described in accordance with the provisions of the contract
and the contract documents, and that notice of completion should
be filed and payment of the balance due said contractor authorized
in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the
perfo~ance of all work necessary to construct, install and com-
plete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together
with the appurtenances thereto, said public improvement herei~-
above more particularly described and set forth, in the City of
Anaheim, by said contractor, be, and the same are hereby accepted,
subject, nevertheless, to all the terms, conditions and provisions
of the contract documents, and that the balance due said con-
tractor for said work be paid to it thirty-five (35) days
from and after final acceptance of said work as evidenced by the
adoption of this resolution, but not sooner than thirty (30) days
after the date of the filing of notice of completion, excepting
only such sum or sums as may lawfully be withheld in. accordance
with the provisions of said contract and contract documents.
That acceptance by the contractor of said payments made in accord-
ance with said final estimate shall operate and shall be a release
to the City of Anaheim, its officers, agents and employees from
all claims and liabilities due the contractor for anything done
or furnished or withheld or for anything relating to the work or
any act or neglect of the City, its officers, agents and em-
ployees, excepting only claims against the City for amounts with-
held by the City at the time of such payment.
AND BE IT FURTHER RESOLVED t~at the Mayor and the City
Clerk of the city of Anaheim be, and they are hereby authorized
to execute and file a notice of completion of said work as
required by law.
this
THE FOREGOING RESOLUTION is approved and signed by ~e
16th day of November , 19 71.
('
ATTEST:
,1l~ ~. f)~~~r-
CITY CLERK OF THE CITY OF ANAHEIM
..,...
-3-
--,
.-.,.,
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particu-
larly described in accordance with the provisions of the contract
and the contract documents, and that notice of completion should
be filed and payment of the balance due said contractor authorized
in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the
performance of all work necessary to construct, install and com-
plete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together
with the appurtenances thereto, said public improvement herei~-
above more particularly described and set forth, in the City of
Anaheim, by said contractor, be, and the same are hereby accepted,
subject, nevertheless, to all the terms, conditions and provisions
of the contract documents, and that the balance due said con-
tractor for said work be paid to it thirty-five (35) days
from and after final acceptance of said work as evidenced by the
adoption of this resolution, but not sooner than thirty (30) days
after the date of the filing of notice of completion, excepting
only such sum or sums as may lawfully be withheld in. accordance
with the provisions of said contract and contract documents.
That acceptance by the contractor of said payments made in accord-
ance with said final estimate shall operate and shall be a release
to the City of Anaheim, its officers, agents and employees from
all claims and liabilities due the contractor for anything done
or furnished or withheld or for anything relating to the work or
any act or neglect of the City, its officers, agents and em-
ployees, excepting only claims against the City for amounts with-
held by the City at the time of such payment.
AND BE IT FURTHER RESOLVED t.ilat the l.iayor.' and the City
Clerk of the city of Anaheim be, and they are hereby authorized
to execute and file a notice of completion of said work as
required by law.
THE FOREGOING RESOLUTION is approved and signed by me
16th day of November , 19 71.
this
ATTEST:
f)~ M. [)~t~~ r-
CITY CLERK OF THE CITY OF ANAHEIM
""..
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS .
CITY OF ANAHEIM )
; -...
I, DENE M. DAOUST, City Clerk of the City of
Anaheim, do hereby certify that the foregoing Resolution No.
71R-S08 was passed and adopted at a ----- regular meetinq
of the City Council held on the 16th day of November , 19 71 ,
by the following vote of the members thereof: ---
AYES:
COUNClId(EN: Roth, Pebley, Thom and Stephenson
NOES:
COUNCILMEN: None
ABSENT:
COUNCILMEN: Dutton
Pro-Tem
AND I FURTHER CERTIFY that the Mayor/of the City of
Anaheim approved and signed said resolution on the 16th day
of November, 19-Z.L. --
IN WITNESS WHEREOF, I have hereunto set my hand and
affixed the seal of the City of Anaheim this 16th day of
November , 19 71
Ll~ h. i2~~
CITY C ERR OF THE CITY OF ANAHEIM
(SEAL)
I, DENE M. DAOUST, City Clerk of the City of Anaheim, do hereby
certify that the foregoing is the original of Resolution No. 71R-S08 duly
passed and adopted by the Anaheim City Council on November 16, 1971.
Mew 'hr 12~A4L-~