71R-458
RESOLUTION NO. 7lR- 458
...-..-,.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE COMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR,
SERVICES, MATERIALS AND EQUIPMENT AND ALL
UTILITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND WATER, AND THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEMENT, TO WIT:
THE MAGNOLIA AVENUE STREET IMPROVEMENT FROM
SANTA ANA FREEWAY TO LA PALMA AVENUE, IN THE
CITY OF ANAHEIM, WORK ORDER NO. 5056.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
printed, published and circulated in the city of Anahe~, to
wit: The Anaheim Bulletin, on June lOth and June 17th
, 19 71 , a not1ce inv1t1nq sealed
proposals for furnishing the following:
All plant, labor, services, materials and equipment, and
all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct
and complete in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings
therefor on file in the Office of the City Engineer or
City Clerk of the city of Anaheim, the .following public
improvement, to wit:
The Magnolia Avenue Street improvement from Santa Ana Free-
way to La Palma Avenue, in the City of Anaheim, consisting
of clearing and grubbing; construction of p.e.c. curb and
gutter, cross gutter and spandrel, drive approaches and
sidewalk; construction of asphalt concrete pavement over
aggregate base, variable thickness asphalt concrete and
asphalt concrete berm; relocation of signs, fencing, sprinklers
and traffic signals; adjustment to grade of gas and water valve
boxes, survey monuments and curb face drain; installation of
magnetometer sensor units; construction of concrete irrigation
line and standpipes; modification of drainage structure; and
appurtenant work as more particularly set forth in the plans
and specifications on file in the Office of the City Clerk or
City Engineer, Work Order No. 5056.
in accordance with the designs, plans, profiles and specifica-
tions prepared by the Department of Public Works
and the notice inviting sealed proposals, which said notice
specified that sealed proposals as specified in said notice would
be received up until 2:00 o'clock P.M. of the 24th day of
June , 19 71 , and which said notice did state and
declare that, pursuant to the provisions of Section 1770 of the
Labor Code, the City Council of the City of Anaheim had ascer-
tained the prevailing rate of wages for each type of labor needed
to execute said contract, and did state that the prevailing hourly
wage scale so ascertained was on file in the Office of the City
Clerk; and
,
-l-
--,~.._.
WHEREAS, on June 24 , 19 71 , at the hour of
2:00 o'clock P.M., the City Clerk-and the-City Engineer of
the City of Anaheim did open said sealed proposals received up
to that time for the furnishing of all plant, labor, services,
materials and equipment, and all utilities and transportation,
including power, fuel and water, and performing all work neces-
sary to construct and complete, in a good and workmanlike manner,
in strict accordance with the specifications, plans and drawings
therefor on file in the Office of the City Clerk of the city of
Anaheim, the public improvement hereinabove more particularly
described and set forth, in public, in the City Council Chamber
in the City Hall, Anaheim, California, and the city Engineer did
tabulate the result of said sealed proposals and did make a
report to the City Council at its next ------ regular
meeting; and --------.--
WHEREAS, the city Council of the City of Anaheim did,
at its next ----- regular meeting, held on the 29th
day of June , 19 71 , at the hour of 1:30 o'croc~
P.M., consider the sealed proposals submitted for-furnishing the
materials and performing the work hereinabove more particularly
described and set forth, and did thereupon find and determine that
the sealed proposal submitted by R. J. NOBLE COMPANY,
P.O. Box 620, Oran~e, CaliforDra 92666
for the construct1on, 1nstalration and completion oC-sa1a---------
Magnolia Avenue from San'ta Ana Preeway 'to L~~!~ Avenue:--
Work Order No. 5056 here1nabove mentioned
ana-described, was the 10west~sponsrbIe proposal submitted
therefor, and thereupon accepted said bid and did award a contract
to said R. J. Noble compan1
or furnfshing air plant, labor,
services, materials and eijUrpment and all utilities and transpor-
tation, including power, fuel and water, and perfo~ing all work
necessary to construct and complete, in a good and workmanlike
manner, in strict accordance with the specifications, plans and
drawings, the said public improvement as specified in said notice
inviting sealed proposals, and did authorize the Mayor and the
City Clerk of the City of Anaheim to execute a contract for and
on behalf of the City of Anaheim with Q~. U^h'.~V.
wnicb --sa1d
COntract was duly made and entered into on the-:-:1st day of
July ___' 19 -'Zl-i and
R. J L NPq~ ~~JP\Y
has furn1she a 1 plant, labor,
services, materials ana-equipment and all utilities and trans-
portation, and perfo~ed all work necessary for the construction
and completion, in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings of said
public improvement as specified in the notice inviting sealed
proposals and in the detailed designs, plans, drawings, and
specifications prepared by the DApAr~mAft~ n~ ~nhl;~ ~~p~a
, and the contract ma e an entere 1nto
with it. by ~he City of Anaheim; and
WHEREAS, the said
WHEREAS, the Direc'tQJ' of P~;Lic ~Tlig
has duly certified to the constructIon an comp et10n of sa1d
public improvement hereinabove mentioned and described, in accord-
ance with the plans and specifications and the contract documents
duly made and entered into with said R. J. HQPle CQRpAfta
...._---J an
-2-
................."Ao.... ~
. . '.............
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particu-
larly described in accordance with the provisions of the contract
and the contract documents, and that notice of completion should
be filed and payment of the balance due said contractor authorized
in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the
performance of all work necessary to construct, install and com-
plete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together
with the appurtenances thereto, said public improvement herei~-
above more particularly described and set forth, in the City of
Anaheim, by said contractor, be, and the same are hereby accepted,
subject, nevertheless, to all the terms, conditions and provisions
of the contract documents, and that the balance due said .con-
tractor for said work be paid to it thirty-five (35)-days
from and after final acceptance of said work as evidenced by the
adoption of this resolution, but not sooner than thirty (30) days
after the date of the filing of notice of completion", excepting
only such sum or sums as may lawfully be withheld in accordance
with the provisions of said contract and contract documents.
That acceptance by the contractor of said payments made in accord-
ance with said final estimate shall operate and shall be a release
to the City of Anaheim, its officers, agents and employees from
all claims and liabili ties due the contractor fo.r anythin9 done
or furnished or withheld or for anything relating to the work.or
any act or neglect of the City, its officers, agents and em-
ployees, excepting only claims against the City for amounts with-
held by the City at the time of such payment.
AND BE IT FURTHER RESOLVED -t"hat the !.1ayor and the City
Clerk of the city of Anaheim be, and they are hereby authorized
to execute and file a notice of completion of said work as
required by law.
THE FOREGOING RESOLUTION is approved and signed by me
12th day of October (=~ 19..2L.
A~
/7M:-,--
this
ATTEST:
fhr hrj)~
CIT CLERK OF THE CITY OF ANAHEIM
..........
-3-
--.,........... ... --
.....
STA'l'B OP CALIPORNIA )
COUH'l'Y Olr ORANGE ) SS .
CITY OP AHABBIM )
.-.-..."'
I. DENE M. DAOUST, City Clerk of the City of Anaheim,
do hereby certify that the foreqoinq Resolution No. 71R-458 was
passed and adopt:ed at: a ------- re9Ular Dleet.in9' of 'the Cit.y
Council held on the 12th day of October , 19 71, by the followinQ
vote of 'the members aiireof: - .
AYES:
COURClIdlBN: Roth, Pebley, Thom and Stephenson
NOES:
ABSENT:
COUNCILMEN: None
OOUHCI~: Dutton
Pro-Tem
AND I FURTHER CERTIFY that the Mayor/ of the City of Anaheim
approved and siCJned said resolution on the ~ day of October ,
19..1.L.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed
the seal of. the City of Anahei.m this 12th day of October , 19...1!...
() .H.j)~
~RK OP 'fIlE CITY OP ANAHEIM
(SEAL)
I, DENE M. DAOUST, City Clerk of the City of Anaheim, do hereby
certify that the foregoing is the original of Resolution No. 71R-458 duly
passed and adopted by the Anaheim City Council on October 12, 1971.
~ M. iJ~d-
City Clerk
........... '"'-
..............."