Attachment 6 - Traffic Circulation Letter14736-03 Traffic Circulation
May 17, 2022 (Revised: May 22, 2023)
Mr. Rafael Cobian
City of Anaheim
200 S. Anaheim Blvd.
Anaheim, CA 92805
SCHOLARSHIP PREP SCHOOL (DEV2021-00218) TRAFFIC CIRCULATION
Mr. Rafael Cobian,
Urban Crossroads, Inc. is pleased to provide the following Traffic Circulation for the Scholarship
Prep School development (Project) located at 2780 E. Wagner Avenue in the City of Anaheim.
This Traffic Circulation was developed to ensure that the proposed site plan can accommodate
adequate on-site circulation for vehicles accessing the site.
PROJECT OVERVIEW
•It is our understanding that the project is to consist of improvements and additions to an
existing building site to allow for the development of a not-for-profit, public charter
school charted by the Orange County Department of Education, pursuant to California
Education Code (EC) Section 47601. The public charter school will host students from
transitional kindergarten through eighth grades. The maximum student enrollment will
include a total of 480 students on site.
•As stated in California legislature (EC Section 47605[e][2]), Charter Schools must admit
any student wishing to attend their school. Therefore, Scholarship Prep Public Charter
School does not have any criteria required for admission.
•The proposed staff for the school includes 40 people per shift and will operate from
Monday to Friday 6:00 AM – 6:00 PM.
•The remodeling of an existing 8,923 sf 2-story building for 10 classrooms, administration
offices, and restrooms.
•The addition of a new 5,633 sf 2-story building containing 6 classrooms, restrooms, and
an elevator to match the existing 2-story building in height.
•Remodel of an existing 5,439 sf 1-story building with basement for 3 classrooms,
restrooms, and a new lift.
•Parking lot improvements and pick-up/drop off areas.
•For an initial 24-month period, the existing church sanctuary will operate Sundays, with
the use of (1) classroom after 5:00 PM and (1) office during the week, once per week.
Religious assembly use of the site will cease following the 24-month duration.
The proposed Project site plan is shown on Attachment A.
ATTACHMENT NO. 6
Mr. Rafael Cobian
City of Anaheim
May 22, 2023
Page 2 of 3
14736-03 Traffic Circulation
PICKUP/DROP OFF CIRCULATION
The proposed Scholarship Prep School preliminary site plan prepared on March 9, 2023 by Studio
W Architects as shown in Attachment A. The pickup/drop-off loading area has been overlaid on
the site plan as shown in Attachment B. The site plan indicates that the on-site stacking area will
provide storage capacity for approximately 31 vehicles. Additional vehicles may queue on-site
before spilling out onto the public roadway. On-site staff will be available to direct vehicles to
efficient pickup/drop-off operations.
TRASH TRUCK ACCESS
A trash truck turning template has been overlaid on the site plan at the Project driveway and
drive aisles in order to determine appropriate curb radii and to verify that trash trucks will have
sufficient space to execute turning maneuvers (see Attachment C). As directed by City staff, the
site plan shall accommodate a 37’ turning radius to accommodate a truck length of 35’. As shown
in Attachment C, the path of the trash truck has been overlaid on the site plan. The proposed
site plan and recommended path is anticipated to accommodate a front-loading trash truck.
FIRE TRUCK ACCESS
A fire truck turning template has been overlaid on the site plan at the Project driveway and drive
aisles in order to determine appropriate curb radii and to verify that fire trucks will have sufficient
space to execute turning maneuvers (see Attachment D). Per the 2019 California Fire Code
§503.1.1, approved fire apparatus access roads shall be provided for every facility, building or
portion of a building hereafter constructed or moved into or within the jurisdiction. The fire
apparatus access road shall comply with the requirements of this section and shall extend to
within 150 feet of all portions of the facility and all portions of the building as measured by an
approved route around the exterior of the building or facility. The proposed Project shall comply
with all fire access road provisions:
• 78,000 lbs rated
• 20’ minimum width
• 14’ height clearance
The Project driveway and drive aisle will need to accommodate a width of 20’. As shown in
Attachment D, the drive aisle adjacent to the existing and proposed buildings meets the fire
access road requirements. The turning template utilizes the larger fire engine with a ladder since
the proposed Project includes buildings with more than one story.
CONCLUSIONS
Traffic circulation for pick/drop-off vehicles, trash truck access, fire truck access have been
prepared for the proposed Scholarship Prep School. The preliminary site plan provides adequate
circulation for passenger vehicles, trash trucks, and fire trucks.
Mr. Rafael Cobian
City of Anaheim
May 22, 2023
Page 3 of 3
14736-03 Traffic Circulation
If you have any questions, please contact me directly at rvu@urbanxroads.com.
Respectfully submitted,
URBAN CROSSROADS, INC.
Jose Alire, P.E. Robert Vu, P.E.
Senior Traffic Engineer Transportation Engineer
ATTACHMENT A
PRELIMINARY SITE PLAN
ATTACHMENT B
PICKUP/DROP-OFF LOADING AREA
EXHIBIT 4: ON-SITE PASSENGER VEHICLE STACKINGURBANCROSSROADSTELEPHONE # 949-660-1994WWW.URBANXROADS.COMPROJ. DWY.WAGNER AV.RIO VISTA ST.1516171819202122232425262714131211109876543212829303180604010200SCALE: 1" = 20' (ON 24" x 36" SHEET)
ATTACHMENT C
TRASH TRUCK ACCESS
80604010200SCALE: 1" = 20' (ON 24" x 36" SHEET)URBANCROSSROADSTELEPHONE # 949-660-1994WWW.URBANXROADS.COMWAGNER AV.RIO VISTA ST. EXHIBIT 3: GARBAGE TRUCK ACCESS
ATTACHMENT D
FIRE TRUCK ACCESS
EXHIBIT 2: EMERGENCY VEHICLE ACCESSURBANCROSSROADSTELEPHONE # 949-660-1994WWW.URBANXROADS.COMWAGNER AV.RIO VISTA ST.80604010200SCALE: 1" = 20' (ON 24" x 36" SHEET)