DLFWorkshopEYTPLANNING COMMISSION
DISNEYLANDFORWARD
PUBLIC CEQA WORKSHOP
OCTOBER 9, 2023
1
City Team / CEQA Lead Agency
City Staff
Elaine Thienprasiddhi, Senior Planner
Heather Allen, Principal Planner
Ted White, Planning & Building
Director
2
•Public Works, Traffic Engineering
•Public Works, Development Services
•Public Utilities, Water
•Public Utilities, Electrical
•Fire & Rescue
•Police
Dudek, Inc.
Alexandra Martini, Project Manager
Notice of Preparation/Initial Study
Oct. 21, 2021 to Nov. 29, 2021
NOP Scoping Public Meeting
November 4, 2021
Prepare Draft SEIR
Release Draft SEIR for 45-day Agency and Public Review
Sep. 14, 2023 to Oct. 30, 2023
3
Prepare Final SEIR including
Response to Comments
Public Hearings
Anticipated Spring 2024
Issue Notice ofDetermination
DisneylandForward Environmental Review
Public Workshop
Staff presentation on environmental review of the Project
Project Applicant presentation
Public comments on environmental review
Not a public hearing to make a decision on the Project nor a forum to
debate the merits of the Project
4
Using the Environmental Analysis
Section 1.0 – Executive Summary
Section 2.0 – Introduction
Section 3.0 – Project Description
Section 4.0 – Environmental Setting
Section 5.0 – Impact Analysis
Section 6.0 – Alternatives to the Proposed Project
Section 7.0 – Other CEQA Considerations
Section 8.0 – List of Preparers and Persons Consulted
5
Draft SEIR Availability
City Hall:
Anaheim Planning and Building Department
200 South Anaheim Boulevard, Planning Counter
Anaheim, California 92805
6
Public Libraries:
Anaheim Central Library
500 W. Broadway
Anaheim, California 92805
Euclid Branch Library
1340 S. Euclid Street
Anaheim, California 92802
Ponderosa Joint Use Branch Library
240 E. Orangewood Avenue
Anaheim, CA 92802
Online:
www.Anaheim.net/876/Environmental-Documents
7DSEIR Section 3.0
8DSEIR Section 3.0 Disneyland DriveWalnut StreetHarbor BoulevardKatella Avenue
Ball Road
Haster StreetDisneylandForward
DisneylandForward Project Overview
Provide flexibility as to location for permitted uses within DRSP & ARSP
No additional square footage of Theme Park or Retail
No additional Hotel Rooms
Increase of 4,376 Theme Park-related parking spaces in the ARSP
Provide administrative review of future projects by City of Anaheim
Incorporate properties acquired by Disney since original approvals
9DSEIR Section 3.0
Project Objectives
To support the continued reimagination of The Disneyland Resort to meet and
exceed evolving guest expectations for immersive entertainment and
technological advances in theme park and other resort experiences.
To continue to fulfill the following vision of Walt Disney: “Disneyland will never
be completed… It will continue to grow as long as there is imagination left in
the world.”
To allow the expansion of theme park and parking uses to Disney ARSP
Properties to support the continued success and vitality of The Anaheim
Resort, including The Disneyland Resort.
10DSEIR Section 3.0
Discretionary Applications
General Plan Amendment
Specific Plan Amendment
Zoning Code Amendment
Height Map Amendment
The Anaheim Resort Public Realm Landscape Program Amendment
The Anaheim Resort Identity Program Amendment
Abandonment of Public Right-of-Way
Encroachment Agreements
Development Agreement Amendment
11DSEIR Section 3.0
General Plan and Specific Plan Amendments
12DSEIR Section 3.0
13Disneyland DriveWalnut StreetHarbor BoulevardDSEIR Section 3.0
DRSP Theme Park District:
6,850,000 square feet of Theme Park uses
DRSP Hotel District:
5,600 Hotel rooms
DRSP Parking District, West Parking Area:
16,700 parking spaces
ARSP C -R District:
564 Hotel rooms
Katella Avenue
Ball Road
Theme Park District
Hotel
District
Parking
District
ARSP
Current Districts and
Allowed Uses
14Disneyland DriveWalnut StreetHarbor BoulevardKatella Avenue
Ball Road
DSEIR Section 3.0
DRSP Theme Park District:
6,850,000 square feet of Theme Park uses
5,600 Hotel rooms
DRSP Parking District, West Parking Area:
16,700 parking spaces
ARSP Theme Park Overlay West:
80,000 square feet of Theme Park uses
564 Hotel rooms
Proposed Districts and
Allowed Uses
Parking
District
Theme Park
District
Theme Park
District
15
Concept Rendering of Theme Park District
Disneyland
Hotel
DSEIR Section 3.0
Paradise Pier
Hotel
California
Adventure
16
Current Districts and
Allowed Uses
Harbor BoulevardKatella Avenue
Orangewood Avenue Haster StreetDRSP Future Expansion District:
5,100 parking spaces
ARSP C -R District:
3,348 Hotel rooms
Theme Park Parking by CUP
Future Expansion District
ARSP C -R District
17
Proposed Districts and
Allowed Uses
Harbor BoulevardKatella Avenue
Orangewood Avenue Haster StreetDRSP Southeast District:
390,000 square feet of Theme Park uses
1,852 Hotel rooms
ARSP Theme Park East Overlay:
840,000 square feet of Theme Park uses
3,348 Hotel rooms
Southeast District
ARSP
Theme Park
East Overlay
18
Concept Rendering of Southeast District/
Theme Park East Overlay
DSEIR Section 3.0
19
Current Districts and
Allowed Uses
ARSP C -R District:
534 Hotel rooms
Parking by CUP
Ball Road
Disney WayHarbor BoulevardClementine StreetARSP C -R District:
1,116 Hotel rooms
Parking by Temporary Parking Permit
Parking District, East Parking Area:
17,600 parking spaces
20
Proposed Districts and
Allowed Uses
ARSP Parking Overlay:
534 Hotel rooms
5,700 parking spaces (increase of 4,376 spaces)
Ball Road
Disney WayHarbor BoulevardARSP Parking Overlay:
1,116 Hotel Rooms
A portion of the parking from the Parking District
Parking District, East Parking Area:
17,600 parking spaces
21
Concept Rendering of Parking District East Parking Area
(as viewed from Disney Way)
General Plan Circulation Element Amendment
22DSEIR Section 3.0
Transportation –
Intersection
Improvements
23DSEIR Section 3.0 Disneyland DriveHarbor BoulevardHaster StreetKatella Avenue
Orangewood AvenueClementine Street
Transportation –
Traffic Signal
Control
24DSEIR Section 3.0 Disneyland DriveHarbor BoulevardHaster StreetKatella Avenue
Orangewood AvenueClementine StreetMagic WayWalnut Street
Transportation –
Lane
Configuration
Changes
25DSEIR Section 3.0 Disneyland DriveHarbor BoulevardHaster StreetKatella Avenue
Orangewood AvenueClementine StreetConvention Way Gene
Autry Way
26
Transportation –
Operational
Improvements
Funding
Harbor BoulevardKatella Avenue Anaheim BoulevardBall Road
Orangewood Avenue
Circulation Element and
Bike Master Plan
Amendments – Walnut
Street
27
Walnut Street Proposed Cross Section
Proposed Bike Facility Change
Modify Planned Class II Bike Lanes to
Class I Shared Bike/Ped Path on east side Walnut StreeetDisneyland DriveBall Road
Katella Avenue
DSEIR Section 3.0
Circulation Element and
Bike Master Plan
Amendments – Disney
Way
28
Disney Way Proposed Cross Section
Remove Planned Class I Bike Path
Add Class I Shared Bike/Ped Path
Modify Planned Class I Bike Path to Class I
Shared Bike/Ped PathHarbor BoulevardDisney Way
Clementine StreetAnaheim BoulevardProposed Bike Facility Changes
DSEIR Section 3.0
Height Map
29DSEIR Section 3.0
Existing Proposed
Anaheim Resort Identity and Landscape Programs
30DSEIR Section 3.0
31
Right-of-Way Abandonments
DSEIR Section 3.0 Harbor BoulevardDisneyland DriveMagic Way
Katella Avenue
Disney Way
Hotel Way
Clementine StreetAnaheim Boulevard
Encroachment
Agreements for Bridges
32
Disneyland Drive Bridge/Crossing Examples
Harbor BoulevardDisneyland DriveBall Road
Katella Avenue
DSEIR Section 3.0
33
Harbor Boulevard Bridge Examples
Harbor BoulevardDisneyland DriveBall Road
Katella Avenue
DSEIR Section 3.0
Encroachment
Agreements for Bridges
Harbor Boulevard Bridge Features
34
Harbor Boulevard Bridge ExamplesPublic access from Harbor will be
provided
Abutments will meet existing setbacks
Vertical clearances will meet emergency
vehicle requirements
Will include safety screening
Will have an open design
Will not be more than 50 feet wide
DRSP Section 4.6.2
Environmental Analysis
Applies to discretionary actions undertaken by agency
Evaluates and discloses potential project impacts on the environment to
the public and decision makers
35
Follows regulations established by the California
Environmental Quality Act (CEQA)
Determines level of impact, if any, for each
environmental topic
Prior EIRs
36
Disneyland Resort
Specific Plan (DRSP)
1993 - EIR No. 311 Certified
1994 - Master EIR No. 313
Certified
2012 - Supplemental EIR No.
340 Certified
Anaheim Resort
Specific Plan (ARSP)
DSEIR Section 2.0
DisneylandForward Project CEQA Review – SEIR No. 352
Analyzes changes to The Disneyland Resort Project and
the Anaheim Resort Specific Plan Project proposed by
DisneylandForward
Looks for potential new or substantially more severe
significant impacts than those analyzed in the prior EIRs
Includes mitigation measures from the prior EIRs in
addition to new mitigation measures applicable to
DisneylandForward
37DSEIR Section 2.0
38
DisneylandForward Environmental Review
Included in Draft SEIR:
•Aesthetics
•Air Quality
•Biological Resources
•Cultural Resources
•Energy
•Geology/Soils
•Greenhouse Gas Emissions
•Hazards/Hazardous Materials
•Hydrology/Water Quality
•Land Use/Planning
•Noise
•Population/Housing
•Public Services/Recreation
•Transportation
•Tribal Cultural Resources
•Utilities/Service Systems
No further review required:
•Agricultural/Forestry Resources
•Mineral Resources
•Wildfire
DSEIR Sections 1.0 and 5.0
Less than Significant with Mitigation Impacts
•Aesthetics
•Biological Resources
•Energy
•Geology/Soils
•Hazards/Hazardous
Materials
•Land Use/Planning
•Noise (Operations and
Vibration)
•Public
Services/Recreation
•Transportation
•Tribal Cultural Resources
•Utilities/Service Systems
39
•Hydrology/Water Quality
•Population/HousingConsistent
New or
Substantially
More Severe
DSEIR Section 5.0
40
Aesthetics
DSEIR Section 5.1
Operational Noise - Fireworks
41
Aerial fireworks limited to existing Disneyland and California
Adventure Theme Parks
No aerial fireworks, only low-level fireworks west of Disneyland
Drive or south of Katella Avenue
DSEIR Section 5.0
Operational Noise – Setbacks from Residential Uses
42
Indoor Thrill or Family Attraction:
Outdoor Family Attraction:
200-feet minimum
400-feet minimum
+ building or noise barrier
DSEIR Section 5.11
Operational Noise – Setbacks from Residential Uses
43
Outdoor Thrill Attractions / Parades and Large Shows:
550-feet minimum
+ building or noise barrier
Mitigation Measure for noise monitoring requires:
•Ongoing: Semi-annually
•During the first five years of operation: Quarterly
•Noise Complaint: Immediately
DSEIR Section 5.11
Public Services
44DSEIR Section 5.13
Utilities and Service Systems
45
Katella Avenue Harbor BoulevardNinth StreetDisneyland DriveClementine StreetWalnut StreetDSEIR Section 5.16
Significant and Unavoidable Impacts
•Cultural Resources
46
•Air Quality (Construction and Operations)Consistent
New or
Substantially
More Severe
•Greenhouse Gas Emissions
•Noise (Construction)
DSEIR Section 5.0
Consistent
and New or
Substantially
More Severe
Air Quality - Construction and Operation
47
•Impact consistent with EIR
Nos. 311 and 340
•Mitigation Measures
DSEIR Section 5.2
Greenhouse Gas Emissions
48
•CEQA did not require analysis for
EIR No. 311
•Consistent with EIR No. 340
•Mitigation Measures
DSEIR Section 5.7
Noise - Construction
49
•New Impact compared to EIR No.
311
•Consistent with EIR No. 340
•Mitigation Measures
DSEIR Section 5.11
Cultural (Historic) Resources
50
•New Impact
•Mitigation Measures
DSEIR Section 5.4
Notice of Preparation/Initial Study
Oct. 21, 2021 to Nov. 29, 2021
NOP Scoping Public Meeting
November 4, 2021
Prepare Draft SEIR
Release Draft SEIR for 45-day Agency and Public Review
Sep. 14, 2023 to Oct. 30, 2023
51
Prepare Final SEIR including
Response to Comments
Public Hearings
Anticipated Spring 2024
Issue Notice ofDetermination
DisneylandForward Environmental Review Next Steps
Project Webpage
52
https://www.anaheim.net/DisneylandForward
Draft SEIR Availability
City Hall:
Anaheim Planning and Building Department
200 South Anaheim Boulevard, Planning Counter
Anaheim, California 92805
53
Public Libraries:
Anaheim Central Library
500 W. Broadway
Anaheim, California 92805
Euclid Branch Library
1340 S. Euclid Street
Anaheim, California 92802
Ponderosa Joint Use Branch Library
240 E. Orangewood Avenue
Anaheim, CA 92802
Online:
www.Anaheim.net/876/Environmental-Documents
Comment Letters Received
54
“No Comment” Letters from Agencies - 2
Comment Letters on the environmental analysis - 0
Letters from the community - 48
Public Review Period: September 14, 2023 through October 30, 2023 (45 days)
Public Workshop: The public may provide verbal or written comments today.
The public may provide written comments by mail, email or hand delivery to:
Elaine Thienprasiddhi, Senior Planner
Anaheim Planning and Building Department
200 South Anaheim Boulevard, MS 162
Anaheim, California 92805
Email: Ethien@Anaheim.net
55
Thank You for Your Participation!