1313 S HARBOR BLVD (425)Permit Ty4.pes
„ BLD ELE: MEC PLM
X
Permit Number: BLD2022-05906
Issued: 12/14/2022
www.anaheim.neYbuilding
(714)765-4626
Quarter Section: 76
CITY OF ANAHEIM
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(7141765.5153
Site Address: 1313 S HARBOR BLVD 8600, Anaheim, CA 92802
Legal Description: S TWP 4 RGE 10 SEC 22 T 4 R 10 SEC 22 POR OF SEC A
APN:08219019
Project Description: Mechanical to support DLR - SW Launch Bay - Change of Use
Living Area: Number of Stories: 0 Valuation: 0.00
Garage Area: Construction Types: NIA
Carport Area: Occupancy Groups:
Balcony I Deck Area: Fire Spdnldered:
Cool Roof: Total Fees paid for Permit: 240.00
People Associated with Project:
Contractor P P C AIR CONDITIONING INC 5950 LAKESHORE DRIVEABCDE11155788 CYPRESS, CA 90630
Permit Applicant Tyler Truong
Owner WALT DISNEY WORLD CO PO BOX 5046
Type , Electrical Fixtures Oty Type Plumbing Fixtures Qty Mechanical Fixtures Qty
Commercial System per 1,000 sq. ft. 1
Ventilation Fan - <= 300 drn on single duct 2
Ventilation Fan - > 300 cfm on single duct 1
The permit shall expire by limitation and become null and void if the building or work has not passed final Inspection 365 days from the
date of permit Issuance. A new permit Is required to commence or continue work.
P�PtiEIM ��C
City of Anaheim D� �o
Building Division F i
u >
�DGNDED �$y^
Do not occupy this building until the final inspections have been made.
FINAL INSPECTIONS
DATE
INSPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
Electrical Final
Plumbing Final
Mechanical Final
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-5126
INSPECTION I DATE I INSPECTOR
Fire Sprinkler (ONLY) (714) 765-5041
Do not pour concrete until the following applicable items have been signed:
Fire Dept. Final (714) 765-5041
Plumbing (Ground/Underfloor Drain Waste)
Water Engineering (714) 765-4591
Electrical Ground Electrode/Ufer
Sub List/Bus. Lic. (714) 765-5194 (Allow 10 business days)
Setback/Forms/Trenches (Footings)
COA/Migation Measures
Do not install subfloor or pour floor slab until the follwing applicable items have been
signed:
Building Final (714 765-5153)
Last Inspection-Final Only After Above Completed
Plumbing (Ground/Underfloor Water)
Underfloor Rough Gas
PARTIAL INSPECTIONS
Building Inspections
Mechanical (Groundwork)
Electrical (Underground Conduit)
Pre-slab (Compaction/Membrane Reinf.)
Floor (Joist/Girders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been s' ed:
1st Floor Shear
Firesprinkler (Rough) (Fire Dept.)
Meobanical Ins ections
y q IL-49Roof
2nd Floor Shear
(Sheathing/Diaphragm/Frame)
Masonry (Reinf./Bond Beam/Pre-Grout)
Rough Plumbing (Top Out)
Rough Duct (Mechanical)
Rough Mechanical
Rough Electrical
Rough COA/Mitagation Measures
Plumbing Inspections
Framing (Only after Plbg., Ele., Mac. & Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed:
Drywall
Drywall Penetrations (Ele, Mac & Plbg)
Interior Lath
Exterior Lath
Electrical Inspections
Electrical Service Meter-(Meter will be set within 2-3
business days after approval) Excludes New
Construction
Exterior Plaster (Brown Coat)
T-Bar (Strutt., Ele., or Mec.)
Grease Interceptor
Sewer
Water Engineering Backflow (Testable Only)
Water Service
LOS ANGELES AIR BALANCE COMPANY INC.
• 1848 W. 11TH ST., SUITE #N, UPLAND, CA 91786
TEL# : 1-800-429-6880
HVAC TEST AND BALANCE ANALYSIS REPORT
PROJECT: Disneyland DCl' TL DVC Lounge
LOCATION: Anaheim, California
ARCHITECT: None Found
MECHANICAL ENGINEER: Salas O' Brien
HVAC CONTRACTOR: PPC Air Conditioning Inc.
REPORT CERTIFICATION#: 42258
REPORT DATE: March 15, 2023
AABC TBE: Eddie Alejandre, P.E.
Project: Disneyland DCP TL DVC Lounge, Anaheim
HVAC TEST AND BALANCE
SUMMARY
All components of the HVAC system(s) on this project were tested, adjusted and balanced to within the
tolerances set forth by AABC and the design documents, with the following exceptions:
No Exceptions
Setting the Industry Standard