1515 S HARBOR BLVD (364)r-- Permit Types
BLD ELE MEC PLM
X
Permit Number: BLD2016-01998
Issued: 05/16/2016
INSPECTION REQUEST LINE:
(714) 765 - 4626
Quarter Section: 76
Site Address:. 1515 S HARBOR BLVD 304 HYPERION THEATRE
Legal Description:
C
(714) 765 - 5153
EIM
Project Description: DCA - Hollywood - Hyperian Theatre BLD304 - Storage Racks: Phase 1; 30 In.ft, 10' high temporary
storage racks. Phase 2: 44 linear ft. X 16 ft. high storage rack for new storage room. REF:BLD2016-01942
Valuation:
$8,520.00
Construcion Types:
N/A, ,
Fire Sprinklered?
Yes
Cool Roof
No
Total Fees paid for Permit:
687.05
People Associated with Project:
Engineer KENNETH E AGEE SE3340 3452 E FOOTHILL 626-432-5850 PASADENA CA 91107
Engineer AMY M BRAUN 148 E FOOTHILL BLVD STE 101 ARCADIA CA 91006
Owner WALT DISNEY WORLD CO %WALT DISNEY CO TAX DEPT P O BOX 4741 GLENDALE CA 91
Permit Applicant MARK HOLLINGWORTH
Type Electrical Fixtures Qty Type
Plumbing Fixtures Qty Type Mechanical Fixtures Qty
The permit shall expire by limitation and become null and void if the building or work has not passed final inspection 365 days from the date of
permit issuance. A new permit is required to commence or continue work. fbid_permit combo
City of Anaheim
Building Division
Do not occupy this building until the final inspections have been made.
INSPECTION I DATE INSPECTOR
Do not pour concrete until the following applicable items have been signed:
Plumbing (Ground/Underfloor Drain Waste)
Electrical Ground Electrode/Ufer
Setback/Forms/Trenches (Footings)
Do not install subfloor or pour floor slab until the follwing applicable items have been
sioned7
Plumbing (Ground/Underfloor Water)
Underfloor Rough Gas
Mechanical (Groundwork)
Electrical (Underground Conduit)
Pre -slab (Compaction/Membrane ReinE)
Floor (Joist/Girders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been slanadb
1st Floor Shear
Firesprinkler (Rough) (Fire Dept.)
2nd Floor Shear
Roof (Sheathing/Diaphragm/Frame)
Masonry (ReinElBond Beam/Pre-Grout)
Rough Plumbing (Top Out)
Rough Duct (Mechanical)
Rough Mechanical
Rough Electrical
Rough COA/Mitagation Measures
Framing (Only after Plbg., Ele., Mee. & Fre)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed:
Drywall
Drywall Penetrations (Ele, Mac & Plbg)
Interior Lath
Exterior Lath
Electrical Service Meter -(Meter will be set within 2-3
business days after approval) Excludes New
Construction
Exterior Plaster (Brown Coat)
T -Bar (Struct., Ele., or Mec.)
Grease Interceptor
(Do not backfill unless sqanad offi
Sewer
Water Engineering Backflow (Testable Only)
Water Service
FINAL INSPECTIONS I DATE I INSPECTOR
All applicable Items below must be signed before utilities are released
Final Gas Test
Electrical Final
Plumbing Final
Mechanical Final
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-5126
Fire Sprinkler (ONLY) (714) 765-5041
Fire Dept. Final (714) 765-5041
Water Engineering (714) 765-4591
Sub List/Bus. Lic. (714) 765-5194 (Allow 10 business days)
COA/Migation Measures
Building Final (714 765-5153) �'
Last Inspection -Final Only After Above Completed C
PARTIAL INSPECTIONS
Building Inspections
Mechanical Inspections
Plumbing Inspections
Electrical Inspections