1801 KATELLA AVE (5)Permit Types
BLD ELE MEC PLM
X X
Permit Number: BLD2023-00895
Issued: 02/24/2023
www.anaheim.neUbuilding
(714)7654626
Quarter Section: 107
CITY OF ANAHEIM
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(7141765.5153
Site Address:.1801 E KATELLA AVE 1037, Anaheim, CA 92805
Legal Description: N TR 16618 BLK LOT 1 UN 1037 TRACT 16618, LOT 1 OF
APNc93028553
Project Description: Electrical to upgrade electrical in kitchen
L'(4%
/
4\y
Living Area: Number of Stories: 1 Valuation: 0.00
Garage Area: Construction Types: NIA
Carport Area: Occupancy Groups:
Balcony I Deck Area: Fire Sprinldered: No
Cool Roof: Total Fees paid for Permit: 613.50
People Associated with Project:
Contractor ROY BARGIL 1470 MARIA LANE SUITE 200 WALNUT, CA 92780
Permit Applicant ROY ORBARGIL 7290 EDINGER AVE APT 3011 HUNTINGTON BEACH, CA 92647
Owner REYES KEVIN AUSTIN 2327 OCANA AVE
Type Electrical Fixtures Oty Type Plumbing Fixtures Qty Mechanical Fixtures Qty
Receptacle, switches, lights 21
The permit shall expire by limitation and become null and void K the building or work has not passed final inspection 365 days from the
date of permit Issuance. A new permit is required to commence or continue work.
P�pHEIM �q<
Cityof Anaheim O� �o
Building Division F y
u a
' DGNDED `gy
Do not occupy this building until the final inspections have been made.
FINAL INSPECTIONS
DATE
INSPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
c rical Final
Plum mal
Mechanical Final
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-5126
INSPECTION DATE I INSPECTOR
Fire Sprinkler (ONLY) (714) 765-5041
Do not pour concrete until the following applicable items have been signed:
Fire Dept. Final (714) 765-5041
Plumbing (Ground/Underfloor Drain Waste)
Water Engineering (714) 765-4591
Electrical Ground Electrode/Ufer
Sub ListlBus. Lic. (714) 765-5194 (Allow 10 business days)
Setback/Forms/Trenches (Footings)
COA/Mi oat on Measures
Do not install subfloor or pour floor slab until the follwing applicable items have been
signed:
Building Final 4765-5163)
Final Only After Above Completed
Plumbing (Ground/Underfloor Water)
Underfloor Rough Gas
PARTIAL INSPECTIONS
Building Inspections
Mechanical (Groundwork)
Electrical (Underground Conduit)
Pre-slab (Compaction/Membrane Reinf.)
Floor (Joist/Girders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been sionede
1st Floor Shear
Firesprinkler (Rough) (Fire Dept.)
Mechanical Inspections
2nd Floor Shear
Roof (Sheathing/Diaphragm/Frame)
Masonry (Reinf./Bond Beam/Pre-Grout)
Rough Plumbing (Top Out)
Rough Duct (Mechanical)
Rough Mechanical
rough Electrical oc
Rough COA/Mitagation Measures
Plumbing Inspections
Framing (Only after Plbg., Ele., Mec. & Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed:
Drywall
Drywall Penetrations (Ele, Mec & Plbg)
Interior Lath
Exterior Lath
Electrical Inspections
Electrical Service Meter-(Meter will be set within 2-3
business days after approval) Excludes New
Constructea
Exterior Plaster (Brown Coat)
T-Bar (Struct., Ele., or Mec.)
Grease Interceptor
Sewer
Water Engineering Backflow (Testable Only)
Water Service