66-182
--
RESOLUTION NO. 66R-182
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE COMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR,
SERVICES, MATERIALS AND EQUIPMENT AND ALL
UTILITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND WATER 9 AND THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEMENT, TO WIT ~
THE IMPROVEMENT or HARBOR, BOULEVARD FROM
APPROXIMATELY 5.50 FEET NORTH or ROmYA DRIVE
fiR ti~OXDfAtE&y ~l 5 lDLSfTH or.R~
DR! IN-mE In (jr ANAHEIM JOB NO ~
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
printed, published and circulated in the City of Anaheim, to
wit: The Anaheim Bu11etin~ on the 14th and 21st days of
October , 19 65 ,a notice inviting sealed pro-
posals for furnishing the following:
All plant, labor, services, materials and equipment, and all
utilities and'transportation, including power, fuel and water,
and performing all work necessary to construct and complete
in a good and workmanlike manner, in strict accordance with
the specifications, plans and drawi~s therefor on file in
the Office of the.City Engineer or City Clerk of the City of
Anaheim, the following pu61ic improvement, to wit: The
Improvement of Harbor Boulevard, from approximately 550 feet
north of Romneya Drive to approximately 41.5 feet south of
Romneya Drive, in the City of Anaheim, consisting of
excavation, including compacted embankment, hau1away and
disposal; construction of asphalt concrete pavement,
aggregate base, P.C.C. drive, P.C.C. curb, and curb and
gutter, P.C.C. sidewalk; relocation of miscellaneous poles,
signs and traffic signals; removal of existing highway
facilities; adjustment of water.va1ve'box to grade, and
appurtenant work as more particu1arl! set forth in the plans
and specifications on file in the Office of the City Clerk or
City Engineer, Job No. 941.
-
in accordance with the designs, plans, .profi1es and specifica-
tions prepared by the Public Works De2artment ,
and the notice inviting sealed proposals, which said notice
specified that sealed proposals as specified in said notice would
be received up until 2:00 o'clock P.M. of the 28th day of
October ,19 65 ,and which said notice did state and
declare that, pursuant to the provisions of Section 1770 of the
Labor Code, the City Council of the City of Anaheim had ascer-
tained the prevailing rate of wages for each type of labor needed
to execute said contract, and did state that the prevailing hourly
wage scale so ascertained was on file in the Office of the City
Clerk; and
WHEREAS, on October 28 , 19 65 ,at the hour of
0'c10ck P.M., the City Clerk and the City Engineer of
2:00
-1-
.-.
the City of Anaheim did'open said sealed proposals received.up
to that time for the furnishing of all plant, labor, services,
materials and equipmen~, and all utilities and transportation,
including power, fuel a~d' water, an4," performing all work neces-
sary to construct an.d complete, in:~" good and workmanlike manner,
in strict accordance with the specifications, plan.s and drawings
therefor on file in the Office of the City Clerk of the City of
Anaheim, the public improvement hereinabove more particularly de-
scribed and set forth, in public, in the, City.: Council Chamber in
the City Hall, Anaheim, California, and the City Engineer did
tabulate the result of said sealed proposals and did make a re-
port to the City Council at its next -- regular meeting;
and . .
-
WHEREAS, the City Council of the".City of, Anaheim did, at
its next -- , regular meeting, held on the 2nd day of
November ,19 65 , at the hour of "'2:'OO.ovclock P.M., con-
sider the sealed proposals submitted for furnishing the materials
'and performing the work hereinabove more pa~ticular1y described
and set forth, and did thereupon find and. determine that the sealed
proposal submitted by SULLY-MILLER CONTRACTING COMPANY. P. O.
Box 432tl Or~etl Ca11forniatl, for the construc-
tion!, ins.tal ation ,and com..pletion of said improvement of Harbor
BouJ.evard, in the Cit of m Job No. 9liI . .
_ .. ",' .'''~'', one an. ......escr e, was e
lowest responsible proposal' 's', -t!ted ther410r J' and thereupQ.n
accepted said ,bid and did award a ,contra~t to'said SULLY-~LLER
CONTRACTING COMPANY . for furnishing
all plant, labor, services, materials and equipment and all utili-
ties and transportation, including power, fuel and water, and per-
forming all work n.ecessary to construct and complete, in a good
and workmanlike manner, in strict accordance with the specifica-
tions, plans and.drawings, the said public ,improvement as specified
in said notice inviting sealed proposals, and did authorize the
Mayor and the City Clerk of the City of Anaheim to execute a con-
tract for and on behalf of the City of Anaheim with
SULLY-MILLER CON'l'BACTING COMPANY ' which said
contract was duly made and entered into on the 5th day of
November ,19 65 ; and ,
WHEREAS, the said SULLY-MILLER CONTRACTpm COMPANY
. has furnished all plant, ,abor" services,
materials and equipment and' all utilities and transportation, and
performing all work necessary for the construction and completion,
in ~ good and workmanlike manner, i~ strict accordance with the
specifications, plans and. drawings of said public improvement as
specified in the notice inviting sealed proposals and in the de-
tailed designs, plans, drawings, and specifications prepared by
the Public Works Department ' J and the contract
made and entered into with it by the City of Anaheim; and
WHEREAS, the Director of Public Works. has
duly certified to the construction and completion of said public
improvement hereinabove mentioned and described, in accordance
with the plans and specifications and the contract documents duly
made and entered in.to with said SULLY-MILLER CONTRACTING
COMPANY ; and
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particu-
larly described in accordance with the provisions of the contract
and the contract documents, and that notice of completion should
be filed and p.yment 'of the balance due said contractor authorized
in.accordance with the cont~act documents.
-2-
.-
NOW;l THEREFORE" BE IT RESOLVED by' the City Council of
the City of Anaheim that all plant, labor~ aervices, materials
and equipment and all utilities and tTansportation, and the per-
formance of all work necessary to construct, install and com-
plete, in a good and workmanlike manner, in strict accordance
with the specificat.ions, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together
with the appurtenances thereto, sAid public improvement herein-
above more parLicu1ar1y described and set forth, in the City of
Anaheim, by said contractor, be, and the same are hereby accepted,
subject, nevertheless, to all the terms, conditions and provisions
of the contr~~c documents, and that the balance due said contractor
for said work ',e paId to it thirty-five (35) days from and
after final acceptance of said ~ork as evidenced by the adoption
of this re~olution, but not sooner than thirty (30) days after the
date of the filing of notice of completion, excepting only s\1ch
s~m or sums as may lawfully be withheld in accordance with the
provisions of said contract and contract documents. That accept-
ance by the contractor of said payments made in accordance with
said final estimate shall operate and shall be a release to the
City of Anaheim, its officers., agents and employees from all
claims and liabilities due the contractor for anything done or
furnished or withheld or for anything relating to the work or
any act or neglect of the City, its officers, agents and e~ployees,
excepting only claims against the City for amounts withheld by the
City at the time of such payment.
AND BE IT FURTHER RESOLVED that. the Mayor and the City
Clerk of the City of Anaheim be, and they are hereby authorized
to execute and file a notice of completion of- said work as
required by 1a-w.
THE FOREGOING RESOLUTION is approved and signed by me
this 8th day of March , 19 66 . '
'ATTEST:
"/,"<,
.' ,
~. .0
~.. t ........... "-... ~
~rmfe~F~~
....-
-3-
-
-
STATE OF CAL~FORNIA )
COONTY OF ORANGE ) s s .
CITY OF ANAHEIM )
~.
I, DENE M. WILLIAMS, City Clerk of the City of Anaheim,
do hereby oertify that the foregoing Resolution No. 66R-182 was
introduced and adopted at a regular meeting provided by ]a w, of the
City Council of the City of Anaheim, held on the 8th day of March,
1966, by the following vote of the members thereof.
AYES. COONCILMEN. Dutton, Pebley, Schutte and Krein
NOES: COUNCILMEN. None
ABSENT: COUNCILMEN: Chandler
,
AND I FURTHER CERTIFY that the Mayor of the City of
Anaheim approved and signed said Resolution No. 66R-182 on the
8th day of March, 1966.
IN WITNESS WHEREOF, I have hereunto set my hand and
affixed the official seal of the City of Anaheim this 8th day
of ~archs 1966.
('. . r'.
i --, - '-+-"---'"
~,w. d./~'; ",~~
CIT . CLERK OF THE CITY OF ANAHEIM
(SEAL)
I, DENE M. WILLIAMS, City Clerk of the City of Anaheim,
do hereby certify that the foregoing is the original of Resolution
No. 66R-182. duly passed and adopted by the Anaheim City Council on
March 8, 1966.
r-"
i j
~ ~-,
, ~ /?t.
--- '-""::'--,----
~~.....-~~
CITY CLERK
.-....
to