515 N CITRON ST (2)Permit Types
BLD I ELE I MEC 1 PLM
X
Permit Number: BLD2021-04094
Issued: 09/16/2021
INSPECTION REQUEST LINE:
(714) 765 - 4626
Quarter Section: 62
Site Address: 515 N CITRON ST B (Second Unit)
Legal Description: N TR 1119 LOT 32
CITY OF ANAHEIM
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(714) 765 - 5153
Project Description: Reroof: Install (5) squares of composition shingles over existing first layer on to accessory dwelling unit.
Valuation: $2,500.00
Construcion Types: N/A, ,
Total Fees paid for Permit: 340.50
People Associated with Project:
Owner KARL SCHISLER 515 N CITRON ST ANAHEIM CA 92805-2415
Type Electrical Fixtures Qty Type Plumbing Fixtures Qty Type Mechanical Fixtures Qty
The permit shall expire by limitation and become null and void if the building or work has not passed final inspection 365 days from the date of
permit issuance. A new permit is required to commence or continue work. - - 11170
PNpNEIM cq<
City of Anaheim pk io
Building Division
�I a
0vNOEo gay^/
Do not occupy this building until the final inspections have been made.
FINAL INSPECTIONS
DATE
I INSPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
Electrical Final
Plumbing Final
Mechanical Final
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-5126
INSPECTION
DATE
INSPECTOR
Fire Sprinkler (ONLY) (714) 765-5041
Do not pour concrete until the following applicable items have been signed:
Fire Dept. Final (714) 765-5041
Plumbing (Ground/Underfloor Drain Waste)
Water Engineering (714) 765-4591
Electrical Ground Electrode/Ufer
Sub List/Bus. Lie. (714) 765-5194 (Allow 10 business days)
Setback/Formslrrenches (Footings)
COA/Migation Measures
Do not install subfloor or pour floor slab until the follwing applicable items have been
sinned
Building Final (714 765.5153)
Last Inspection -Final Only After Above Completed
y
/
Plumbing (GroundlUnderfloor Water)
Underfloor Rough Gas
PARTIAL INSPECTIONS
Building Inspections
Mechanical (Groundwork)
Electrical (Underground Conduit)
Pre -slab (Compaction/Membrane Saint.)
Floor (Joist(Girders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been sinned
1st Floor Shear
Firesprinkler (Rough) (Fire Dept.)
Mechanical Inspections
2nd Floor Shear
Ill Sheat ' laphragm/Frame)
_
Masonry (Reinf./Bond Beam/Pre-Grout)
Rough Plumbing (Top Out)
Rough Duct (Mechanical)
Rough Mechanical
Rough Electrical
Rough COA/Mitagation Measures
Plumbing Inspections
Framing (Only after Plbg., Ele., Mec. 8 Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed:
Drywall
Drywall Penetrations (Ele, Mae & Plbg)
Interior Lath
Exterior Lath
Electrical Inspections
Electrical Service Meter -(Meter will be set within 2-3
business days after approval) Excludes New
Construction
Exterior Plaster (Brown Coat)
T-Bar (Struct., Ele., or Mac.)
Grease Interceptor
Sewer
Water Engineering Backflow (Testable Only)
Water Service