Permit Number: BLD2019-01854
Issued:07/09/2019
INSPECTION REQUEST LINE:
(714) 765 - 4626
Quarter Section: 112
Site Address: 100 S STATE COLLEGE BLVD
Legal Description:
CITY OF ANAHEIM
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(714) 765 - 5153
Project Description: Miscellaneous: (5) new light poles, restripe parking. REF: BLD2019-01852
Valuation:
$1,000.00
Construcion Types:
VB,
Occupancy Groups:
Fire Sprinklered?
No
Cool Roof
No
Total Fees paid for Permit:
325.50
People Associated with Project
Owner
WILLIAM REGO TR
9330 BALBOA AVE SAN DIEGO CA 92123-1516
Engineer
MARK A KAISER
12001 N CENTRAL EXPRESSWAY STE 300 DALLAS TX 75243
Engineer
DENNIS HEATH
1115 ATLANTIC AVE. ALAMEDA CA 94501
Engineer
WILLIAM D BEST
5880 SAWMILL RD STE200 DUBLIN OH 43017
Engineer
ROBERT L KOEPER
5880 SAWMILL RD STE 200 DUBLIN OH 43017
Contractor
T MORRISSEY CORPORATION
3740 OCEANIC WAY SUITE 301 OCEANSIDE CA 92056 0000
Permit Applicant
ERIC RAMOS
3740 OCEANIC WAY STE 301 OCEANSIDE CA 92056
Type Electrical Fixtures Qty Type Plumbing Fixtures Qty Type Mechanical Fixtures Qty
Pole Light (with one fixture) 5
The permit shall expire by limitation and become null and void if the building or work has not passed final inspection 365 days from the date of
permit issuance. A new permit is required to commence or continue work. L...., ,,._..
��pHEtM ��`
City of Anaheim O4 io
Building DIVISIOn F i
u i
,OVNOED 1157
Do not occupy this buildina until the final inspections have been made.
FINAL INSPECTIONS
DATE
INSPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
Electrical Final PERMIT
EXPIRE-74P
Plumbing Final
Mechanical Final
Cross Connection Control (714) 76
Engineering Final (714) 7655126
INSPECTION
I DATE
I INSPECTOR
Fire Sprinkler (ONLY) (714) 765- E:
I bill
Do not pour concrete until the following applicable items have been signed.
Fire Dept. Final (714) 765-5041
Plumbing (Ground/Underfloor Drain Waste)
Water Engineering (714) 765-4591
Electrical Ground Electrode/Ufer
Sub Llst/Bus. Lic. (714) 7654194 (Allow 10 business days)
Setback/Forms/Trenches (Footings)
COA/Mlgatlon Measures
Do not install subfloor or pour floor slab until the follwing applicable items have been
Building Final (714 7655153)
Last Inspection -Final Only After Above Completed
Plumbing (Ground/Underfloor Water)
Underfloor Rough Gas
PARTIAL INSPECTIONS
Building Inspections
Mechanical (Groundwork)
Electrical (Underground Conduit)
Pre -slab (Compaction/Membrane Reinf.)
Floor (JoisVGlyders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been sinned
1st Floor Shear
Flresprinkler (Rough) (Fire Dept.)
Mechanical Inspections
2nd Floor Shear
Roof (Sheathing/Diaphragm/Frame)
Masonry (Reinf./Bond Beam/Pre-Grout)
Rough Plumbing (Top Out)
Rough Duct (Mechanical)
Rough Mechanical
Rough Electrical
Rough COA/Mitagatlon Measures
Plumbing Inspections
Framing (Only after Plbg., Ele., Mec. & Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signs
Drywall
Drywall Penetrations (Ele, Mec & Pibg)
Interior Lath
Exterior Lath
Electrical Inspections
Electrical Service Meter -(Meter will be set within 2-3
business days after approval) Excludes New
Exterior Plaster (Brown Coat)
T-Bar (Struct., Ele., or Mec.)
Grease Interceptor
Sewer
Water Engineering Backflow (Testable Only)