104 W ORANGEWOOD AVE (2)Permit Types
BLD
I ELE
MEC
PLM
X
X
I X
I X
Permit Number: BLD2024-02578
Issued: 06/25/2024
www. anaheim. net/buiid ing
(714)765-0626
Quarter Section: 89
CITY OF ANAHEIM
Site Address: 104 W ORANGEWOOD AVE, Anaheim, CA 92802
Legal Description: N TR 1965 BLK LOT 1
APN: 23310110
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(714) 766 - 5153
Project Description: Residential Remodel: 450 sq. ft. to convert rumpus room into bedroom #4 and bathroom #3 with 200 amp panel
upgrade. Replace (12) windows, air conditioner, furnace. Upgrade mechanical and plumbing in bathrooms and kitchen.. REF:
INV2024-00109.
Living Area: Number of Stones: 0 Valuation:
Garage Area: Construction Types:
Carport Area: Occupancy Groups:
Balcony / Deck Area: Fire Spnnklered:
Cool Roof: Total Fees paid for Permit:
People Associated with Project:
Pennit Applicant Max Nguyen
Owner TNT REALTY U-C
Engineer - Civil Ly Phan 10821 Keenan PI Stanton, CA 90680
Type Electrical Fixtures City Type Plumbing Fixtures City
Meter/Disc Sw - Under 600 V, up to 200 1 Bath Tub 1
amps Gas System (outlets) 1
Receptacle, switches, lights 2
Lavatory 2
Repair/Drainage Alteration/Vent Piping 1
Sewer per 100 ft. 1
Shower
Water Closet
Water Heater
Water Main per 100 ft.
1
M
35,000.00
VB
3,69180
Mechanical Fixtures City
Condenser 1
Heating Appliances, including vent 1
Residential Registers (ducts) 6
Ventilation Fan - <= 300 cfm on single duct 1
The permit shall expire by limitation and become null and void if the building or work has not passed final inspection 365 days from the
date of permit issuance. A new permit is required to commence or continue work.
PNPHEIM �q<
Cityof Anaheim O� iO
Building Division f y
• �OVNDED t
Do not occupy this building until the final inspections have been made.
FINAL INSPECTIONS
DATE INSPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
Electrical Final
Plumbing Final
Mechanical Final
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-5126
INSPECTION I
DATE I
INSPECTOR
Fire Sprinkler (ONLY) (714) 7655041
Do not pour concrete until the following applicable items have been signed:
Fire Dept. Final (714) 765-5041
Plumbing (Ground/Underfloor Drain Waste)
_
Water Engineering (714) 765.4591
Electrical Ground Electrode/Ufer
Sub List/Bus. Lic. (714) 765.5194 (Allow 10 business days)
Setback/Forms/Trenches (Footings)
COA/Migation Measures
Do not install subfloor or pour floor slab until the follwing applicable items have b
stoned
Building Final (714 7655163)
Last Inspection -Final Only After Above completed
I /
Plumbing (Ground/Underfloor Water)
Underfloor Rough Gas
PARTIAL INSPECTIONS
Buildina Insclections
% ( %iL rA�k 4h,WS vis hGu �,rtf6rr VgAvs
Mechanical (Groundwork)
Electrical (Underground Conduit)
Prelab(Compaction/Membrane Reinf.)
Floor (JoisUGirders)
``
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been s;aned
list Floor Shear
Firesprinkler (Rough) (Fire Dept.)
Mechanical Inspections
2nd Floor Shear
Roof (Sheathing/Diaphragm/Frame)
Masonry (Reinf./Bond Beam/Pre-Grout)
Rough Plumbing (Top Out)
j7/
Rough Duct (Mechanical)Rough
Mechanical
Rough Electrical
Rough COA/Mitagation Measures
-Plumbinp Inspections
72
r Z 1 '{,.. Ls d*
Framing (Only after Plbg.. Ele- Mec. & Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed:
Drywall
Drywall Penetrations (Ele, Mec & Plbg)
Interior Lath
Exterior Lath
Electrical Inspections
Electrical Service Meter -(Meter will be set within 2-3
business days after approval) Excludes New
Construct on
Exterior Plaster (Brown Coat)
T-Bar (Struct., Ele., or Mee.)
Grease Interceptor
Sewer
-L
Water Engineering Backflow (Testable Only)
Water Service