131 S CONNIE CIR (2)Permit Types
BLD
ELE
MEC
:M::j
X
X
Permit Number: BLD2024-02901
Issued: 06/27/2024
www.anahel m. net/bu ilding
(714)765-4626
Quarter Section: 134
Site Address: 131 S CONNIE CIR, ANAHEIM, CA 92806
Legal Description: N TR 6784 BLK LOT 5
APN: 26802205
CITY OF ANAHEIM
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(714) 765. 5153
Project Description: Photovoltaic System with Micro -inverters: Install roof mounted solar with (22) modules, (22) micro -inverters and (1)
200amp Main Service
Living Area:
Number of Stories: 1 Valuation: 20,320.00
Garage Area:
Construction Types: VB
Carport Area:
Occupancy Groups:
Balcony I Deck Area:
Fire Sprinklered:
Cool Roof:
Total Fees paid for Permit: 1,408.64
People Associated with Project:
Contractor LGCY INSTALLATION SERVICES LLC DBA LG 3333 N. DIGITAL DRIVE STE 600 LEHI, UT
Permit Applicant Mary Hernandez
Owner TAPIA, CARLOS E
131 S CONNIE CIR
Type Electrical Fixtures
Oty Type Plumbing Fixtures Qty Mechanical Fixtures Qty
Meter/Disc Sw - Under 600 V, up to 200
1
amps
Microinverter
22
The permit shall expire by limitation and become null and void if the building or work has not passed final inspection 365 days from the
date of permit Issuance. A new permit is required to commence or continue work.
P�PNeIM �q<
Cityof Anaheim gk iO
Building Division F'- i
O >
D�NDeo tsy^
Do not occupy this building until the final inspections have been made.
FINAL INSPECTIONS
DATE
INSPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
Electrical Final
I111NI't
Plumbing Final
Mechanical Final
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-5126
INSPECTION I
DATE I
INSPECTOR
Fire Sprinkler (ONLY) (714) 765-5041
Do not pour concrete until the following applicable items have been signed:
Fire Dept. Final (714) 765.6041
Plumbing (Ground/Underfloor Drain Waste)
Water Engineering (714) 765-4591
Electrical Ground Electrode/Ufer
Sub List/Bus. Lic. (714) 765.5194 (Allow 10 business days)
Setback/FormslTrenches (Footings)
COA/Migation Measures
Do not install subfloor or pour floor slab until the follwing applicable items have been
stoned
Building Final (714 765-5153)
Last Inspection -Final Only After Above Completed
Plumbing (Ground/Underfloor Water)
Underfloor Rough Gas
PARTIAL INSPECTIONS
Building Inspections
Mechanical (Groundwork)
Electrical (Underground Conduit)
Pre -slab (Compaction/Membrane Reinf.)
Floor (JoistlGirders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable Items have
been sioned
1st Floor Shear
Firesprinkler (Rough) (Fire Dept.)
Mechanical Inspections
2nd Floor Shear
Roof (Sheathing/Diaphragm/Frame)
Masonry (Reinf./Bond Beam/Pre-Grout)
Rough Plumbing (Top Out)
Rough Duct (Mechanical)
Rough Mechanical
Rough Electrical
5
Rough COA/Mitagation Measures
Plumbing Inspections
Framing (Only after Plbg.. Ele., Mec. & Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed.
Drywall
Drywall Penetrations (Ele, Mec & Plbg)
Interior Lath
Exterior Lath
Electrical Inspections
Electrical Service Meter -(Meter will be set within 2-3
business days after approval) Excludes New
Construction
Exterior Plaster (Brown Coat)
T-Bar (Struct., Ele., or Mec.)
Grease Interceptor
(Do nnt backfill unless sinned off)
Sewer
Water Engineering Backflow (Testable Only)
Water Service