227 N DALE AVEPermit Types
BLD ELE MEC PLM
X
Permit Number: BLD2024-05939
Issued: 11/08/2024
www.anaheim.net/building
(714)765-4626
Quarter Section: 12
Site Address: 227 N DALE AVE, Anaheim, CA 92801
Legal Description: N TR 3099 BLK LOT 35
APN: 07055107
CITY OF ANAHEIM
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(7141 765 -5153
Project Description: Reroof: To remove and install (25) squares of composition shingles over partial area of house and attached garage
Living Area: Number of Stories: 0 Valuation:
Garage Area: Construction Types:
Carpon Area: Occupancy Groups:
Balcony I Deck Area: Fire Sprinklered:
Cool Roof: Total Fees paid for Permit:
People Associated with Project:
Contractor SMILE ROOFING 6320 TOPANGA BLVD STE 1630-705 WOODLAND HILLS, CA
Permit Applicant JOSE MONTALVO 320 N PARK VISTA SPC 100 ANAHEIM, CA 92806
Owner LOPEZ, JAVIER OCHOA 227 N DALE AVE
5.000.00
VS
359.65
Type Electrical Fixtures Qty Type Plumbing Fixtures Qty Mechanical Fixtures Qty
The permit shall expire by limitation and become null and void U the building or work has not passed final inspection 365 days from the
date of permit issuance. A new permit is required to commence or continue work.
Pvipm C.
pity of Anaheim
Building Division F i
u >
OVNDED �Bh�
Do not occupy this building until the final inspections have been made.
FINAL INSPECTIONS I
DATE
I INSPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
Electrical Final
Plumbing Final
Mechanical Final
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-5126
INSPECTION I
DATE I
INSPECTOR
Fire Sprinkler (ONLY) (714) 765-5041
Do not pour concrete until the following applicable items have been signed:
Fire Dept. Final (714) 765-5041
Plumbing (Ground/Underfloor Drain Waste)
Water Engineering (714) 765-4591
Electrical Ground Electrode/Ufer
Sub List/Bus. Lic. (714) 7654194 (Allow 10 business days)
Setback/ForrnslTrenches (Footings)
COA/Migation Measures
Do not install subfloor or pour floor slab until the follwing applicable items have been
Building Final (714765-5153)
Last Inspection -Final Only After Above Completed
Plumbing (Ground/Undernoor Water)
Underfloor Rough Gas
PARTIAL INSPECTIONS
Building Inspections
Mechanical (Groundwork)
Electrical (Underground Conduit)
Pre -slab (Compaction/Membrane Reinf.)
Floor (JoistlGirders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been sioned
1st Floor Shear
Firesprinkler (Rough) (Fire Dept.)
Mechanical Inspections
2nd Floor Shear
Roof(Sheathing/Diaphragm/Frame)
it�l2 L"l
Masonry (Reinf./Bond BeamlPre-Grout)
Rough Plumbing (Top Out)
Rough Duct (Mechanical)
Rough Mechanical
Rough Electrical
Rough COA/Mitagation Measures
Plumbing Inspections
Framing (Only after Plbg., Ele., Mec. & Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed.
Drywall
Drywall Penetrations (Ele, Mec & Plbg)
Interior Lath
Exterior Lath
Electrical Inspections
Electrical Service Meter -(Meter will be set within 2-3
business days after approval) Excludes New
Construction
Exterior Plaster (Brown Coat)
T-Bar (Struct., Ele., or Mec.)
Grease Interceptor
Min not backfill unless sinned off)
Sewer
Water Engineering Backflow (Testable Only)
Water Service