63-0135RESOLUTION NO. 63R135
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ANAHEIM FINALLY ACCEPTING THE COMPLETION AND
THE FURNISHING OF ALL PLANT, LABOR, SERVICES,
MATERIALS AND EQUIPMENT AND ALL UTILITIES AND
TRANSPORTATION INCLUDING POWER, FUEL AND WATER,
AND PERFORMING ALL WORK NECESSARY TO CONSTRUCT
AND COMPLETE THE FOLLOWING PUBLIC IMPROVEMENT,
TO WIT: A STEEL RESERVOIR TANK, NEAR THE OLIVE
HILLS RESERVOIR, IN THE CITY OF ANAHEIM, WO RK
ORDER NO. 4083.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
printed, published and circulated in the City of Anaheim, to wit:
The Anaheim Bulletin, on August 30, and September 6
19 9
following:
All plant, labor, services, materials and equipment, and all
utilities and transportation, including power, fuel and water,
and performing all work necessary to construct and complete
in a good and workmanlike manner, in strict accordance with
the specifications, plans and drawings therefor on file in
the Office of the City Engineer or City Clerk of the City of
Anaheim, the following public improvement, to wit: The con-
struction of a 750,000 gallon steel reservoir tank, near the
Olive Hills Reservoir, in the City of Anaheim, including ex-
cavation, concrete structures, pipe main and fittings, A.C.
pavement, and appurtenant work as more particularly set forth
in the plans and specifications on file in the Office of the
City Clerk or City Engineer, Work Order No. 4083,
in accordance with
tions prepared by
and the notice inv
specified that sea
be received up unt
of September
state and declare
of the Labor Code,
ascertained the pr
needed to execute
hourly wage scale
the designs, plans, profi.es and specifica-
Bovle Engineering
sting sealed proposals, which said notice Y
led proposals as specified in said notice would
11 2:00 oVclock Po M. of the 13th day
9 19 62 and which said notice did
that, pursuant to the provisions of Section 1770
the City Council of the City of Anaheim had
evailing rate of wages for each type of labor
said contract and did set forth the prevailing
so ascertained; and
WHEREAS, on September 13 19 at the hour
of 2:00 ooclock P. M., the City Clerk and City Engineer of
-1-
the City of Anaheim did open said sealed proposals received up
to that time for the furnishing of all plant, labor, services,
materials and equipment, and all utilities and transportation,
including power, fuel and water, and performing all work neces-
sary to construct and complete, in a good and workmanlike
manner, in strict accordance with the specifications plans and
drawings therefor on file in the Office of the City Clerk of the
City of Anaheim, the public improvement hereinabove more
cularly described and set forth in unciti
e l
public in City Council
Chamber in the City Hall, Anaheim, California, .and the City
Engineer did tabulate the result of said sealed proposals and
did make a report to the City Council at its next
regular meeting; and
WHEREAS, the City Council of tie City of Anaheim did,
at its next regular meeting, held on the 18th
day of September 1962
ooclock F, Ma, consider the sealed proposais for fur-
nishing the materials and performing the work hereinabove more
particularly described and set forth, and did thereupon find and
determine that the sealed proposal submitted by WEST AND WIGGS,
INC.,
for the construction, installation and completion of said
reservoir tank, near the Olive Hills Reservoir, Work Order No e1 4083,
hereinabove mentioned and described, was the lowest responsible
proposal submitted therefor, and thereupon accepted said bid and
did award a contract to said WEST AND WIGGS IN
2425 Gundry Avenue, Lon Beach, a i ornia
for furnishing all plant, labor, service materials and equip-
ment and all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct and
complete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings, the said public
improvement as specified in said notice inviting sealed proposals,
and did authorize the Mayor and the City Clerk of the City of
Anaheim to execute a contract for and on behalf of the City of
Anaheim with WEST AND WIGGS, INC.,
which said contract was duly made and entered into on the 24th
day of Spptemher 1962
any
WHEREAS, the said WEST AND WIGGS INC
has furnished all plant, labor, ser-
vices, materials and equipment and all utilities and transportation,
and performed all work necessary for the construction and completion,
in a good and workmanlike manner, in strict accordance with the
specifications, plans, drawings of said public improvement as
specified in the notice inviting sealed proposals anri in the
detailed designs, plans, drawings, and specil'.cations prepared
by Boyle Engineering 9 and the contract made and
entered into with it by the City of Anaheim; and
WHEREAS, the Director of Public Works has duly
certified to the .construction and completion of said public im-
provement hereinabove mentioned and described, in accordance with
the plans and specifications and the contract documents duly made
and entered into with said WEST AND WIGGS, INC.
and
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particularly
described in accordance with the provisions of the contract and the
contract documents, and that notice of completion should be filed
and payment of the balance due said contractor authorized in accord with the contract documents,
m2®
NOW THEREFORE BE IT RESOLVED by the City Council of
the City of Anaheim that all plant labor services materials
and equipment and all utilities and transportation and the per-
formance of all work necessary to construct install and complete
in a good and workmanlike manner in strict accordance with the
specifications plans and drawings therefor on file in the Office
of the City Clerk of the City of Anaheim together with the
appurtenances thereto said public improvement hereinabove more
particularly described and set forth in the City of Anaheim by
said contractor be and the same are hereby accepted subject
nevertheless to all the terms conditions and provisions of the
contract documents and that the balance due said contractor for
said work be paid to it thirty -five (35) days from and after
final acceptance of said work as evidenced by the adoption of this
resolution but not sooner than thirty (30) days after the date of
the filing of notice of completion excepting only such sum or sums
as may lawfully be withheld in accordance with the provisions of
said contract and contract documents, That acceptance by the con-
tractor of said payments made in accordance with said final estimate
shall operate and shall be a release to the City of Anaheim its
officers agents and employees from all claims and liabilities due
the contractor for anything done or furnished or withheld or for
anything relating to the work or any act or neglect of the City its
officers agents and employees excepting only claims against the
City for any amounts withheld by the City at the time of such payment
AND BE IT FURTHER RESOLVED that the Mayor and the City Cler]
of the City of Anaheim be and they are hereby authorize :d to execute
and file a notice of completion of said work as required by lax,
THE FOREGOING RESOLUTION is approved and signed by me this
19th day of Februar ,3
STATE OF CALIFORNIA
COUNTY OF ORANGE ss,
CITY OF ANAHEIM
DENE M. of Anaheim do hereby certify that the fo Gresolutionewasty
introduced and adopted at a regular meeting pro-
vided by law of the City Council of the City of Anaheim held on the
19th day of February 19 63 by the following vote:
AYES: COUNCILMEN: Dutton, Chandler, Schutte, Krein and Coons
NOES: COUNCILMEN:: None
ABSENT: COUNCILMEN: None
AND I FURTHER CERTIFY that the Mayor of the City of
Anaheim approved and signed said resolution on the 19th day of
February 1963
IN WITNESS WHEREOF I have hereunto set my hand and
affixed the official seal of the City of Anaheim this 19th day
of February 19
(SEAL)
-3-
YOR OF THE CITY OF ANAHEIM