56R-3170
--
RESOLUTION NO. 3170
A RESOLUTION OF TH~ CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE COMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR,
SERVICES, MATERIALS AND EQUIPMENT AND ALL
UTILITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND WATER, AND PERFORMING ALL WORK NECES-
SARY TO CONSTRUCT AND COMPLETE THE FOLLOWING
PUBLIC IMPROVEMENT: The Creseent Avenue
street Improvement, from Manchester Avenue
to Brookhurst Avenue. Job No. 107
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general oirou1ation,
printed, published and ciroulated in the City of Anaheim, to wit:
The Anaheim Bulletin, on the 12th day and the 18th day of
Januarf ' 19 )6, a notice inviting sealed
proposals or furnishing the following:
All plant, labor, services, materials and equipment,
and all utilities and transportation, including
power, fuel and water, and performing all work
necessary to construct and complete in a good and
workmanlike manner, in strict aocordance with the
plans and specifications on file in the Office of
the City Clerk of the Oity of Anaheim, the follow-
ing: public improvement: The Crescent Avenue Street
Improvement, from Manchester Avenue to Brookhurst
Avenue, consisting of excavation, construction of
5-inch plant-mix surfacin~, adjusting existing
mannoles to grade, and appurtenant .'lork as indicated
on the plans, Job No. 107.
"....-
in accordance with the Qesigns, plans, profiles and specifications
prepared by George E. Holyoke, City Engineer
and the notice inviting sealed proposals, which said notice speci-
fied that sealed proposals as specified in said ~o~ice would be
reoeived up until 7:00 o'clock P.B. cf the 2 tn day of
January , 19 '6, and which said notice did state and de-
clare that, pursuant to the provisions of Section 1770 of the
Labor Code, the City Council of the City of Anaheim had ascertain-
ed the prevailing rate of wages for eaoh type of labor needed to
execute said contract and did set forth the prevailing hourly wage
scale so ascertained; and
on the
o'clock
hearing
to that
terials
oluding
WHEREAS, at a regular meeting of the City Council heli
24th day of January , 19 56, at the hour of 7: 00
P.M. cf said date, said City Council did hold a public
for the purpose of opening sealed proposals reoeived up
time, for furnishing of all plant, labor, services, ma-
and equipment, and all utilities and transportation, in-
power, fuel and water, and performing all work necessary
'--.....,
.r~"'-'
to construct ane.. complete, in a good and Horkmanlike manner, in
stric t accordance with tho, specifications, Dla:18 and dra1:rings
cJ:":cfor on file in tL'r'fice of the Ci t,y Clerk of the City of
i,c,aic'~im, of the public 'J,'.):'ovement hereinalJove more particularly
eeseL',bed and set for"i:L; cind
"HEREAS, th8 C:.ty Cou;:.cil did thereu.pon refer said bids
to the Oi ty Engineer for
uC8.m:.natlori-;-tabulatTO:;--:::1d re~1('Y'~~:':;o tne- City -CounCil, and said
City Engineer .. ..... did thereupon
eXB:mine an"d tabuTafe--safcl -seai'e-d'pr-l.)j:)osiiI's-and report the result
of his tabulation to the City Council; and
11HEREAS, the City Council did meet in
regular session on the 24th_day of,. JanuarX_.__.19 3b, at the hOur
of 7:00 orclnck P.fu. to consider the sealed proposals submitted
for furnISEing materials and performing the work hereinabove more
particularly described anu set forth, and the___Ciyy_~gg19&~~___
of the City of Anaheim did
thereupo-n- make his. report andsubmi i his tabulation of said
sealed proposals, and tho City Council did thereupon find and
determine that the sealed proposal submitted by R. J. Noble
Company, P. O. Box 620, Orange, California
for the construction, in stalla-t i on and completion of said
Crescent Avenue Street Improvement, Job No. 107
he-reYnabovementT6nedandcfe'S"C"r-ibed was the' lowest -resp6-nsibfe~pro_
posal submitted therefor, and thereupon accepted said bid and did
award a contract to said R. J. Noble Co~oany
for furnishing all plant, labor, sel'vices,--materialei-arur equip-
ment and all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct and
complete, in a good and workmanlike manner, in strict accordance
with the specifications, plans, and drawings, the said public
improvement as specified in said notice inviting sealed proposals,
and did authorize the Mayor and the City Clerk of the City of
Anaheim to execute a contract for and on behalf of the City of
Anaheim with R. J. Noble C~~!.lL.__ .~__
,.hieh said contract was dUly made and entered into.-o.n-"tfie- 8th
---
day of _~uary ____, 19-..2.2.; and
WHEREAS, the said R. J. Noble COillpany
has furnished all plant, labor, services, materials and equip:---
ment and all utilities and transportation, and performed all work
necessary for the construction and completion, in a good and
workmanlike manner in strict accordance with the specifications,
plans and drawings, of said public improvement as specified in
the notice inviting scaled proposals and in the detail, design,
plans, prOfiles, drawings a~d s>>ecifications prepared by
George E. HOlyoke, Clty ~ngineer , and the contract
made and entered into \.,ftE'- ~---OythGCi ty of Anaheim; and
w"HEREAS, the ___C1t;\' Engineer~~_ __.__
~as dUly certified to the construction and completion of said
Dublic improvement hereinabove mentioned and described in
c'.ccordance with the plans and specif lca tions and the contract
documents duly made and entered into with said
__c____.
R. J. Noble Company ; and
-.-- ........---- --. '--------.
,-,-',"
dHEREAS, the City Council finds that said contractor
has completeQ said public improvement hereinabove more particu-
larly described in accordance with the provisions of the contract
and the contract documenta, and that notice of comuletion shOUld
be filed and payment of the balance due said contractor authorized
in accordance with the contract documents.
-2-
NOH, THEREFOli.I:, B:2~ IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
a~o equipmont and all utjlities and transyortation, and the per-
.~ ~Jrmance of all work necessary to construct, install and completo
\.11 a good and workmanllko manner, in strict accordance with the
specifications, plans and drawings therefor on file in the office
of the City Clerk of the City of Anaheim together with the ap-
purtenances thereto of said public improvement hereinabove more
particularly describoQ ~nd set forth, in the City of Anaheim, by
said contractor, be, and tho samo is hereby, accepted, subject,
nevertheless, to all the terms, ccnditions anc. provisions of the
contract documents, and that the balance due said contraotor for
said work be paid to it thirty-five (35) days from and after
final acceptance of said work as evidenced by the adoption of this
resOlution, but not sooner than thirty (30) days after the date
of the filing of notice of completion, excepting only such sum
or sums as may lallTfully be withheld in accordance with the pro-
visions of said contract and contract documents. That acceptance
by the contractor of said payments made in accordance with said
final estimate shall operate and shall be a release to the City of
Anaheim, its officers, agents and employees from all claims and
liabilities due the contractor for anything done or furnished or
withheld or for anything relating to the work or any act or neg-
lect of the City, its officers, agents and employees, excepting
only claims against the City for any amounts withheld by the City
at the time of such payment.
AND BE IT FURTHER RESOLVED that tho Mayor and the City
Clerk of the Oity of Anaheim be, and they arc hereby, authorized
to execute and file a notice of completion of said work as re-
quired by law.
TH~ FOREGOING RESOLUTION was signed and approved by me
this 6th day of Maroh ,19 56
ATTEST:
-
. ../)
" . ../ . / /
.. ./~ /;:"-~
'-~C~-~,,/ .~1;CA-/~
!vIA OR 6 T CITY 0 Kr~-----'--::::
.,
1/ C--- . '.
~ /?(,~~-~~-.../
~RK OF T1E-.CITY OF ANAHEnI
,.,-.
-3-