RES-2026-011RESOLUTION NO.2 0 2 6 - 011
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ANAHEIM ESTABLISHING A PERFORMANCE TIME
SCHEDULE FOR THE COMMENCEMENT AND
COMPLETION OF CONSTRUCTION OF VACATION
OWNERSHIP RESORT NO. 1 AS SET FORTH IN THE SECOND
AMENDED AND RESTATED DEVELOPMENT AGREEMENT
NO. 99-01 BETWEEN THE CITY OF ANAHEIM AND
WESTGATE RESORTS ANAHEIM, LLC AND DETERMINE
THAT THE PREVIOUSLY APPROVED POINTE ANAHEIM
INITIAL STUDY AND MITIGATED NEGATIVE
DECLARATION (IS/MND), AND ASSOCIATED ADDENDA,
ARE THE APPROPRIATE ENVIRONMENTAL
DOCUMENTATION FOR THIS REQUEST
WHEREAS, Article 2.5 of Chapter 4 of Division 1 of Title 7 (commencing with Section
65864) of the Government Code of the State of California (herein referred to as the "Statute")
authorizes a city to enter into a contract, which is called a development agreement, in order to
establish with certainty what regulations will govern the construction of a development; and
WHEREAS, on November 23, 1982, the City Council of the City of Anaheim (herein
referred to as the "City Council") enacted Ordinance No. 4377 (the "Enabling Ordinance"), and
pursuant to subdivision (c) of Section 65865 of the Statute, adopted Resolution No. 82R-565
(herein referred to as the "Procedures Resolution"), establishing procedures and requirements for
consideration of development agreements upon receipt of an application by the City; and
WHEREAS, in accordance with the statute, the Enabling Ordinance and the Procedures
Resolution (herein referred to collectively as the "Development Agreement Law"), The City and
Anaheim GW, LLC, a Delaware limited liability company, (the "Original Developer") entered into
the Second Amended and Restated Development Agreement No. 99-01 dated as of April 11, 2006,
and recorded in the Official Records of Orange County California on June 2, 2006, as Instrument
No. 2006000373943 (the "Development Agreement") with respect to the real property depicted in
Exhibit A attached hereto and incorporated by this reference; and
WHEREAS, The Original Developer assigned the Development Agreement with respect
to the Parking Structure No. 1, Retail No. 1 and Vacation Ownership Resort No. 1 to Anaheim
GW II, LLC, a Delaware limited liability company ("Anaheim GW II") pursuant to the Partial
Assignment of Second Amended and Restated Development Agreement No. 99-01 dated as of
January 31, 2007, and recorded in the Official Records of Orange County California on February
7, 2007, as Instrument No. 2007000092571; and
WHEREAS, Anaheim GW II assigned the Development Agreement with respect to the
Timeshare Parcel and the Vacation Ownership Resort No. 1 to Westgate Resorts Anaheim, LLC
("Westgate Resorts" or "Developer") pursuant to that certain Partial Assignment of Second
Amended and Restated Development Agreement No. 99-01 dated as of February 29, 2008, and
recorded in the Official Records of Orange County California on March 6, 2008, as Instrument
No. 2008000105443; and
WHEREAS, the Development Agreement addresses, among other things, Developer's
construction of the Project in phases and requires Developer to commence construction of the
various Project Elements within certain time frames; and
WHEREAS, in 2010, Developer requested that the City amend the Development
Agreement to require Developer to commence construction of Vacation Ownership Resort No. 1
to occur on or before March 23, 2019. Accordingly, the Development Agreement was amended
by that certain Amendment No. 1 to Second Amended and Restated Development Agreement No.
99-01 dated as of March 1, 2010, and recorded in the Official Records of Orange County California
on July 19, 2010, as Instrument No. 2010000341657 ("Amendment No. 1"); and
WHEREAS, Developer thereafter requested that the City further amend the Development
Agreement and thereafter Amendment No. 5 to the Second Amended and Restated Development
Agreement No. 99-01 was recorded in the Official Records of Orange County on July 3, 2019, as
Instrument No. 2019000237347 ("Amendment No. 5"), to require the Developer to obtain building
permits for the construction of the Vacation Ownership Resort No. 1 on or before December 31,
2019, and Complete Construction and Open for Business no later than twenty-four (24) months
after Commencement of Construction of Vacation Ownership Resort No. 1; and
WHEREAS, the Development Agreement inclusive of Amendment No. 1, Amendment
No. 2, Amendment No. 3, Amendment No. 4 and Amendment No. 5 thereto shall hereinafter be
referred to as the "Development Agreement." Unless otherwise defined herein all capitalized terms
shall have the meanings ascribed to such terms in the Development Agreement, as amended.
Copies of the Development Agreement are available as a public record in the Office of the City
Clerk located at 200 South Anaheim Boulevard, Anaheim, California; and
WHEREAS, Developer obtained building permits for Vacation Ownership Resort No. 1
consistent with the Development Agreement; and
WHEREAS, on December 20, 2022, Developer advised the City that construction of
Vacation Ownership Resort No. 1 was delayed by the pandemic and resulting government orders,
and thereafter the City Council approved Developer's request for an additional extension of twelve
(12) months, anticipating Completion of Construction no later than December 27, 2023; and
WHEREAS, as part of its 2023 review, the City Council determined that Developer was not in
compliance with the terms and conditions of the Development Agreement for the 2023 review
period and in accordance with the process set forth in Section 7 of the Procedures Resolution
directed staff to notify Developer of its intent to establish new development timeframes for
Vacation Ownership Resort No. 1 as an alternative to modification or termination of the
Development Agreement; and
WHEREAS, on March 26, 2024, the City Council established the performance timeline to
obtain building permits for the construction of Vacation Ownership Resort No. 1 to April 15, 2025
-2-
and the completion of construction of Vacation Ownership Resort No. 1 to no later than twenty-
four months after commencement of construction; and
WHEREAS, the deadline to obtain building permits for Vacation Ownership Resort No. 1
set forth in the Development Agreement has now passed and Developer has requested that the City
Council extend the performance milestones for Vacation Ownership Resort No. 1 to commence
construction by October 31, 2028 and complete construction by October 31, 2030; and
WHEREAS, on December 16, 2025, the City Council determined that Developer was not
in compliance with the terms and conditions of the Development Agreement for the 2025 review
period and in accordance with the process set forth in Section 7 of the Procedures Resolution
directed staff to notify Developer of its intent to establish new development timeframes for
Vacation Ownership Resort No. 1 as an alternative to modification or termination of the
Development Agreement; and
WHEREAS, pursuant to the Procedures Resolution, compliance with the performance
schedule established by City Council as an alternative to modification or termination of the
Development Agreement shall be subject to periodic review in the manner set forth in Sections 6
and 7 of the Procedures Resolution and lack of good faith compliance therewith shall be a basis
for termination or modification of the Development Agreement; and
WHEREAS, pursuant to the California Environmental Quality Act (Public Resource Code
Section 21000 et seq.; herein referred to as "CEQA") and the State of California Guidelines for
Implementation of the California Environmental Quality Act (commencing with Section 15000 of
Title 14 of the California Code of Regulations; herein referred to as the "CEQA Guidelines"), the
City is the "lead agency" for the preparation and consideration of environmental documents for
this resolution; and
WHEREAS, the City Council finds and determines that the previously approved Point
Anaheim Initial Study and Mitigated Negative Declaration (IS/MND), and associated Addenda,
are the appropriate environmental documentation for this request because since the adoption of the
Pointe Anaheim IS/MND and associated Addenda, neither the Project nor the circumstances under
which it will be undertaken have changed. Additionally, there is no new information of substantial
importance that the City, as Lead Agency, did not know and could not have known previously.
The establishment of new performance timelines will not increase the unit count, or otherwise
increase the intensity of the project. Therefore, additional environmental review is not required
pursuant to CEQA Guidelines Section 15162.
NOW, THEREFORE, BE IT RESOLVED that the Anaheim City Council, does hereby
establish the following performance timelines for Vacation Ownership Resort No. 1:
1. Developer shall commence construction of Vacation Ownership Resort
No. 1 on or before October 31, 2028.
2. Developer shall complete construction of Vacation Ownership Resort
No. 1 on or before October 31, 2030.
1911
NOW THEREFORE BE IT FURTHER RESOLVED that except as expressly
provided to the contrary herein, all provisions of the Development Agreement remain in full force
and effect.
THE FOREGOING RESOLUTION is approved and adopted by the City Council
of the City of Anaheim this 24 day of February , 2026, by the following roll
call vote:
AYES: Mayor Aitken and Council Members Leon, Balius,
Rubalcava, Kurtz, Maahs and Meeks
NOES: None
ABSENT: None
ABSTAIN: None
OF THE CITY OF ANAHEIM
CITY OF ANAHEIM
LIM
-4-
APN: 082-551-01
082-551-02
082-551-03
082-551-04
082-551-05
082-551-06
082-551-07
082-551-11
a o
v
EXHIBIT A
W DISNEY WAY
W KATELLA AVE
F-----�-
Source: Recorded Tract Maps andlor City GIS
Please note the accuracy is +!- two to five feet.
-5-
CLERK'S CERTIFICATE
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF ANAHEIM )
I, THERESA BASS, City Clerk of the City of Anaheim, do hereby certify that the foregoing is the
original Resolution No. 2026-011 adopted at a regular meeting provided by law, of the Anaheim
City Council held on the 24th day of February, 2026 by the following vote of the members thereof:
AYES: Mayor Aitken and Council Members Leon, Balius, Kurtz, Rubalcava
Maahs and Meeks
NOES: None
ABSTAIN: None
ABSENT: None
IN WITNESS WHEREOF, I have hereunto set my hand this 251h day of February, 2026.