1973-555
RESOLUTION NO.
73R-555
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIH FINALLY ACCEPTING THE COMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR,
SERVICES, MATERIALS AND EQUIPMENT AND ALL
UTILITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND '\lATER, AND THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEMENT, TO WIT:'
THE LA PALMA AVENUE STREET IMPROVEMENT FROM
WHITTIER STREET TO APPROXIMATELY 724 FEET
EAST OF STATE COLLEGE BOULEVARD, IN THE
CITY OF ANAHEIM, WORK ORDER NO. 648-A.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
printed, published and circulated in the City of Anaheim, to
wit: The Anaheim Bulletin, on 9th and 16th days of
August , 19 73 , a notice inviting sealed
proposals for furnishing the following:
All plant, labor, services, materials and equipment, and
all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct
and complete in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings
therefor on file in the Office of the City Engineer or
City Clerk of the City of Anaheim, the following public
improvement, to wit:
The La Palma Avenue street improvement from Whittier
Street to approximately 724 feet east of State College
Boulevard, in the City of Anaheim, consisting of clear-
ing and grubbing; excavation; construction of P.C.C.
curb and gutter, curb, cross gutter and spandrel, side-
walk and driveway approach; construction of asphalt
concrete over aggregate base and variable thickness
asphalt concrete; and appurtenant work as shown on the
plans and delineated in the specifications on file in
the Office of the City Clerk or City Engineer, Work
Order No. 648-A.
in accordance with the designs, plans, profiles and specifica-
tions prepared by the Public Works Dep'arT-m~t
and the notice inviting sealed proposals, W 1ch said not~ce
specified that sealed proposals as specified in said not1ce would
be received up until 2:00 o'clock P.M. o~ the. 23rd day of
August , 1973 , and which said not1ce d1d state and
declare that, pursuant to the provisi~ns of Secti~n 1770 of t~e
Labor Code the City Council of the C1ty of Anahe1m had ascer
tained the' prevailing rate of wages for each type of l~b9r needef
-- to execute said contract, and did state that the preva1l1ng ~our y
wage scale so ascertained was on file in the Office of the C1ty
Clerk; and
-1-
-
WHEREAS, on August 23 , 1973 ,,:it the hour of
_ 2:00_ o'clock P.M, ,-the CIty Clerk and t.he CIty EngIneer of
the C1 ty of Anahei m dl,d open sal.d sealed proposa is rece 1. ved J.p
to that tIme for t"he furnishing of all plant, labor, serV,l ces.
materials and equIpment, and all utILIties and transportat 1 or, ,
~ncluding power, fuel and water, and performing all work neces.-
sary to construct and complete, .1n a good and workmanlike manner.
In strict accordance wIth the SpeC1.flcations, plans and draw:i.ngs
therefor on fl.le 1n the Office of the City Clerk of the Clt,y of
Anaheim, the publ.ic ~mprovement herei"nabove more particuVu'.<y
described and set fOIth, in public, in the City CouncIl Chamber
in the City Hall, Anaheim, California, and the City Engl.neer dld
tabulate the result of said sealed proposals and dId make a
report to the City Council at its next - - - - - - - regular
meetlng; and
WHEREAS, the C~ty Councl.l of the City of Anaheim did,
at its next - - - - - - - regular meetl.ng, held on the 28th
day of August , 19~, at the hour of 1:30 0 clock
P.M., consider the sealed proposals submitted for furnishing the
materials and performing the work hereinabove more particularly
described and set forth, and did thereupon find and determIne that
the sealed proposal submitted by McGREW CONSTRUCTION COMPANY, INC.,
P. O. Box 10941, Santa Ana, Call.forn1a 92711
for the construction, l.nstallation and completion of said La Palma
Ave. Street improvement from Whittier St. to a~prox. 724 ft. E. of
s:t. COl.lege BlVd., Anahel.m, W. O. NO.648-Aherel.nabove mentIoned
arid described, was the lowest responsible proposal submitted
therefor, and thereupon accepted said bid and did award a contract
to said McGREW CONSTRUCTION COMPANY, INC.
for furnishl.ng all plant, labor,
servl.ces, materials and equipment and all utilities and transpor-
tation, lncluding power, fuel and water, and performing all work
necessary to construct and complete, in a good and workmanlike
manner, in strIct accordance with the specifications, plans and
drawings, the said public improvement as specified in said notJ.ce
inviting sealed proposals, and did authorl.ze the Mayor and the
City Clerk of the City of Anaheim to execute a contract for and
on behalf of the City of Anaheim with McGREW CONSTRUCTION COMPANY,
INC. which sald
contract was duly made and entered l.nto on the 4th day of
September, 19~; and
WHE REAS, the said McgREW CON~T~UCTIO~ COMPANY1 INC.
as furnl.s ed al plant, abor,
serv~ces, materl.als and equipment and all utilities and trans-
portation, and performed all work necessary for the construction
and completion, in a.good and workmanlike manner, in strict
accordance with the specifications, plans and drawings of said
public improvement as specified in the notice inviting sealed
proposals and in the detailed designs, plans, drawings, and
specifications prepared by the Public Wo~k~
Dep~rtmEnt , and the contract made and entered ~nto
Wl.th it y the City of Anaheim; and
<..-....,.,
WHEREAS, the ni rpl'""i-nr Q-F 'Pl1hA i I'"" wnfln:: ,
has duly certified to the constructl.on an comp et~on of sa~d
public improvement hereinabove mentioned and described, in accord-
ance with the plans and specifications and the contract documents
duly made and entered into with said McGREW CONSTRUCTION COMEAMY,
INC. ; an~
-:2-
,,..,.-..
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particll ...
larly described in accordance with the prov1sions of the contr&cL
and the contract documents, and that not1ce of completion should
be filed and payment of the balance due said contractor author~zed
in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the C1ty Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the
performance of all work necessary to construct, install and com-
plete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together
with the appurtenances thereto, said public improvement herein-
above more particularly described and set forth, in the City of
Anaheim, by said contractor, be, and the same are hereby accepted,
subject, nevertheless, to all the terms, conditions and provisions
of the contract documents, and that the balance due said con-
tractor for said work be paid to it thirty-five (35) days
from and after final acceptance of said work. as evidenced by the
adoption of this resolution, but not sooner than thirty (30) days
after the date of the filing of notice of completion, excepting
only such sum or sums as may lawfully be withheld in accordance
with the provisions of said contract and contract documents.
That acceptance by the contractor of said payments made in accord"
ance with said final estimate shall operate and shall be a release
to the City of Anaheim, its officers, agents and employees from
all claims and liabilities due the contractor for anything done
or furnished or withheld or for anything relating to the work or
any act or neglect of the City, its officers, agents and em-
ployees, excepting only claims against the City for amounts ..,,~ tb,.
held by the City at the time of such payment.
AND BE IT FURTHER RESOLVED tmat the NayOr and the C1ty
Clerk of the City of Anaheim be, and they are hereby .authorized
to execute and file a notice of completion of said work as
required by law.
THE FOREGOING RESOLUTION is approved and signed by me
th1s 20th day of November, 1911--
ATTEST:
~~~
"RK OF THE CITY OF ANAHEIM
,...-.....
-3-
-
-
~,
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SSe
CITY OF ANAHEIM )
I, DENE M. DAOUST, City Clerk of the City of Anaheim,
do hereby certify that the foregoing Resolution No. 73R-555 was
passed and adopted at a regular meeting of the City Council held
on the 20th day of November , 1973 , by the following
vote of the members thereof: ---
AYES:
NOES:
COUNCILMEN: Stephenson, Sneegas, Pebley, Thom
And Dutton
COUNCILMEN: None
ABSENT: COUNCILMEN: None
AND I FURTHER CERTIFY that the Mayor of the City of
Anaheim approved and signed said Resolution on the 20th day of
November , 19~
IN WITNESS WHEREOF, I have hereunto set my hand and
affixed the seal of the City of Anaheim this 20th day of
November , 19--1.1.-.
~M~
CI Y CLERK OF THE CITY OF ANAHEIM
(SEAL)
I, DENE M. DAOUST, City Clerk of the City of Anaheim, do
hereby certify that the foregoing is the original of Resolution No.
73R-555 duly passed and adopted by the Anaheim City Council on
November 20, 1973.
L )n.~
CityClerk
~,'"