1973-483
RESOLUTION NO.
73R-483
,.,...-.....
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE COMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR,
SERVICES, MATERIALS AND EQUIPMENT AND ALL
UTILITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND WATER, AND THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEMENT, TO WIT:
THE IMPROVEMENT OF THE NORTHWEST CORNER OF EUCLID
STREET AND LA PALMA AVENUE, IN THE CITY OF ANAHEIM,
WORK ORDER NO. 683-B.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
printed, published and circulated in the City of Anaheim, to
wit: The Anaheim Bulletin, on the 21st and 28th days of .
June , 19 73 ,a notice invit~ng sealed
proposals for furnishing the following:
All plant, labor, services, materials and equipment, and
all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct
and complete in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings
therefor on file in the Office of the City Engineer or
City Clerk of the City of Anaheim, the following public
improvement, to wit:
The improvement of the northwest corner of Euclid Street
and La Palma Avenue, in the City of Anaheim, consisting
of clearing and grubbing, excavation, construction of
P.C.C. curb and gutter, curb, sidewalk, drive approaches,
alley approach, asphalt concrete, aggregate base, relo-
cation of traffic signal, electric sign, highway sign;
adjustment of a manhole to grade and appurtenant work
as more particularly set forth on the plans and delineated
in the specifications on file in the Office of the City
Clerk or City Engineer, Work Order No. 683-B.
in accordance with the designs, plans, profiles and specifica-
tions prepared by the Public Works Departmen~
and the notice inviting sealed proposals, wh~ch said notice
specified that sealed proposals as specified in said notice would
be received up until 2: 00 0 I clock P.M. of the 5th day of
July , 19 73 , and which said notice did state and
declare that, pursuant to the provisions of Secti~n 1770 of the
Labor Code, the City Council of the City of Anahe~m had ascer-
,_ tained the prevailing rate of w~ges for each type of l~b~r needed
to execute said contract, and d~d state that the preva~l~ng hourly
wage scale so ascertained was on file in the Office of the City
Clerk; and
-1-
"-
WHEREAS, on July 5 , 19 73 ,;:it the hour of
"2:00 o'clock P.M. ,-lhe CIty Clerk ~nd the CIty Eng1neer of
the Cl ty of Anabei m did open sa1d sealed proposa Is rece";, ved Jp
to that tIme for t.he furnishing of all plant, labor, serVIces.
materials and equIpment, and all utlll ties and transportatlor.,
including power, fuel and water, and performing all work neces.-
sary to construct and complete, "In a good and workmanlike mann.er.
In strict accordance wIth the specl.flcation&, plans and drawings
therefor on file 1n the Office of the City Clerk of the Cltv of
Anaheim, the public l.mprovement herel,nabove more particular'~y
described and set forth, in public, in the Cl.ty CounCI! Chamber
.in the City Hall, Anaheim, Cal.ifornia, and the City Englneer old
tabulat.e the result of said sealed proposals and di d make a
report to the CIty Council at its next - - - - - - - regular
meeting; and
WHEREAS, the C1ty Council of the City of Anaheim did,
at its next - - - - - - - regular meetl.ng, held on the 10th
day of JU~y , 19/3 , at the hour of 1:30 0 clock
P.M., consider the sealed proposals submitted for furnishl.ng the
materials and performing the work hereinabove more particularly
described and set forth, and did thereupon find and determine that
the sealed proposal submitted by SILVERI and RUIZ CONSTRUCTION CO.,
2742 W. Orangethorpe - Suite Q, FUllerton, California 92633
for the construction, l.nstallation and completion of said improvement
of the Northwest corner of Euclid St. and La Palma Ave., in the City
of Ananel.m, worK order NO. b~3-B hereinabove mentloned
arid descrl.bed, was the lowest responsible proposal submitted
therefor, and thereupon accepted said bid and did award a contract
to said SILVERI and RUIZ CONSTRUCTION CO.
for furnishing all plant, labor,
servl.ces, materials and equipment and all utilities and transpor-
tation, including power, fuel and water, and performing all work
necessary to construct and complete, in a good and workmanlike
manner, in strIct accordance with the specifications, pl,ans and
drawings, the said public improvement as specified in said notIce
inviting sealed proposals, and did authorl.ze the Mayor and the
City Clerk of the city of Anaheim to execute a contract for and
on behalf of the City of Anaheim with SILVERI and RUIZ CONSTRUCTION
CO. which saId
contract was duly made and entered l.nto on the 12th day of
July , 19.:!..L-; and
WHEREAS, the said SILVERI and RUIZ I~NSTRUCTION CO.
has furnished a plant, labor,
serVl.ces, materl.als and equipment and all utilities and trans-
portation, and performed all work necessary for the construction
and completion, in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings of said
public improvement as specified in the notice inviti.ng sealed
proposals and in the detailed designs, plans, drawings, and
specifications prepared by _the Public Work~
Departmp-nt ~ and the co~tract maQe and entered l.nto
w~th y the C~ty of Anahel.m; and
-
WHEREAS, the Director of Public Works
has duly certified to the construction and completion of sa~d
public improvement hereinabove mentioned and described, in accord-
ance with the plans and specifications and the contract documents
duly made and entered into with said SILVERI and RUIZ CONSTRgCTTON
CO. ; an
-2-
"'...-....
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particu'
larly described in accordance with the prov~sions of the contr~cL
and the contract documents, and that not~ce of completion should
be filed and payment of the balance due said contractor authorized
~n accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the C~ty Council of
the City of Anaheim that all plant, labor, services, materia l~'j
and equipment and all utilities and transportation, and the
performance of all work necessary to construct, install and com-
plete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together
with the appurtenances thereto, said public improvement herein-
above more particularly described and set forth, in the City of
Anaheim, by said contractor, be, and the same are hereby accepted,
subject, nevertheless, to all the terms, conditions and provisions
of the contract documents, and that the balance due said con-
tractor for said work be paid to it thirty-five (35) days
from and after final acceptance of said work as evidenced by the
adoption of this resolution, but not sooner than thirty (30) days
after the date of the filing of notice of completion, excepting
only such sum or sums as may lawfully be withheld in accordance
with the provisions of said contract and contract documents.
That acceptance by the contractor of said payments made in accord-.
ance with said final estimate shall opera.te and shall be a release
to the City of Anaheim, its officers, agents and employees from
all claims and liabilities due the contractor for anything done
or furnished or withheld or for anything relating to the work or
any act or neglect of the City, its officers, agents and em-
ployees, excepting only claims against the City for amounts V'~ t;tJ"
held by the City at the time of such payment.
AND BE IT FURTHER RESOLVED bnat the Mayor and the C~ty
Clerk of the City of Anaheim be, and they are hereby authorized
to execute and file a notice of completion of said work as
required by law.
THE FOREGOING RESOLUTION is approved and signed by me
16th day of October , 19 73 .
th1s
~ ~'
I
, 'l~ ~ ~Jil,e' .i ~
OR OF THE CITY OF AN~E~M
ATTEST:
DENE M. DAOUST, CITY CLERK
By C,z,a>--P,",OL- >7'1- ~'ai--U'7"-Y Deputy
CITY CLERK OF THE CITY OF ANAHEIM
-
-)-
-
-
-.
STATE OF CALIFORNIA }
COUNTY OF ORANGE ) SSe
CITY OF ANAHEIM )
I, DENE M. DAOUST, City Clerk of the City of Anaheim,
do hereby certify that the foregoing Resolution No. 73R-483 was
passed and adopted at a regular meeting of the City Council held
on the 16th day of October , 19 73 , by the following
vote of the members thereof: ---
AYES: COUNCILMEN: Stephenson, Sneegas, Pebley, Thom
and Dutton
NOES: COUNCILMEN: None
ABSENT: COUNCILMEN: None
AND I FURTHER CERTIFY that the Mayor of the City of
Anaheim approved and signed said Resolution on the 16th day of
October , 19 ~
IN WITNESS WHEREOF, I have hereunto set my hand and
affixed the seal of the City of Anaheim this 16th day of
October , 1973
DENE M. DAOUST, CITY CLERK
By ~J'V' m. ~~a/ Dppnty
CITY CLERK OF THE CITY OF ANAHEIM
(SEAL )
I, DENE M. DAOUST, City Clerk of the City of \naheim, do
hereby certify that the foregoing is the original of Resolution No.
73R-483 duly passed and adopted by the Anaheim City Council on
October 16, 1973.
DENE M. DAOUST, CITY CLERK
By ~.a.-' >n.~~
Deputy City Clerk
.....-...."