1977-083RESOLUTION NO. 77R -83
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE COMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR, SER-
VICES, MATERIALS AND EQUIPMENT AND ALL UTILI-
TIES AND TRANSPORTATION INCLUDING POWER, FUEL
AND WATER, AND THE PERFORMANCE OF ALL WORK
NECESSARY TO CONSTRUCT AND COMPLETE THE FOLLOW-
ING PUBLIC IMPROVEMENT, TO WIT:
MANZANITA PARK FLOODLIGHTING IMPROVEMENTS,
IN THE CITY OF ANAHEIM, WORK ORDER NO. 794.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
printed, published and circulated in the City of Anaheim, to
wit: The Anaheim Bulletin, on the 26th day of August and 2nd
day of September 19 76 a notice inviting sealed
proposals for furnishing the fo lowing:
All plant, labor, services, materials and equipment, and
all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct
and complete in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings
therefor on file in the Office of the City Engineer or
City Clerk of the City of Anaheim, the following public
improvement, to wit:
Manzanita Park floodlighting improvements, in the City
of Anaheim, consisting of the furnishing and installation
of a floodlighting system complete, including labor,
material, and all appurtenant work in accordance with the
plans and specifications on file in the Office of the
City Engineer, Work Order No. 794,
in accordance with the designs, plans, profiles and specifica-
tions prepared by the Public Works Department
and the notice inviting sealed proposals, which said notice
-1-
specified that sealed proposals as specified in said notice
would be received up until 2:00 o'clock. P.M. of the 9th
day of September 19 76 and which said notice did
state and declare that, pursuant to the provisions of Section
1770 of the Labor Code, the City Council of the City of Anaheim
had ascertained the prevailing rate of wages for each type of
labor needed to execute said contract, and did state that the
prevailing hourly wage scale so ascertained was on file in the
Office of the City Clerk; and
WHEREAS, on September 9 1976 at the hour
of 2:00 o'clock P.M., the City Clerk and the City Engineer
of the City of Anaheim did open said sealed proposals received
up to that time for the furnishing of all plant, labor, services,
materials and equipment, and all utilities and transportation,
including power, fuel and water, and performing all work necessary
to construct and complete, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings
therefor on file in the Office of the City Clerk of the City of
Anaheim, the public improvement hereinabove more particularly
described and set forth, in public, in the City Council Chamber
in the City Hall, Anaheim, California, and the City Engineer did
tabulate the result of said sealed proposals and did make a report
to the City Council at its next regular meeting; and
WHEREAS, the City Council of the City of Anaheim did,
at its next regular meeting, held on the 14th day
of September 19 76 at the hour of 1:30 o'clock P.M.,
consider the sealed proposals submitted for furnishing the
materials and performing the work hereinabove more particularly
described and set forth, and did thereupon find and determine
that the sealed proposal submitted by HELD ELECTRIC, INC., 8995
State Street, South Gate, California 90280
for the construction, installation and completion of said
Manzanita Park floodlighting improvements, in the City of Anaheim,
Work Order No. 794
hereinabove mentioned and
described, was the lowest responsible proposal submitted there-
for, and thereupon accepted said bid and did award a contract
to said contractor for furnishing all plant, labor, services,
materials and equipment and all utilities and transportation,
including power, fuel and water, and performing all work neces-
sary to construct and complete, in a good and workmanlike man-
ner, in strict accordance with the specifications, plans and
drawings, the said public improvement as specified in said
notice inviting sealed proposals, and did authorize the Mayor
and the City Clerk of the City of Anaheim to execute a contract
for and on behalf of the City of Anaheim with said contractor,
which said contract was duly made and entered into on the 23rd
day of September 19 76 and
WHEREAS, the said contractor has furnished all plant,
labor, services, materials and equipment and all utilities and
transportation, and performed all work necessary for the con-
struction and completion, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings
of said public improvement as specified in the notice inviting
sealed proposals and in the detailed designs, plans, drawings
and specifications prepared by the Public Works Department
and the contract made and
entered into with said contractor by the City of Anaheim; and
WHEREAS, the Director of Public Works
has duly certified to the construction and completion of said
public improvement hereinabove mentioned and described, in
accordance with the plans and specifications and the contract
documents duly made and entered into with said contractor; and
WHEREAS, the City Council finds that said contractor
has completed said public improvement hereinabove more particu-
larly described in accordance with the provisions of the con-
tract and the contract documents, and that notice of completion
should be filed and payment of the balance due said contractor
authorized in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the per-
formance of all work necessary to construct, install and com-
plete in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together
with the appurtenances thereto, said public improvement herein
above more particularly described and set forth, in the City of
Anaheim, by said contractor, he, and the same are hereby accepted,
subject, nevertheless, to all the terms, conditions and provi-
sions of the contract documents, and that the balance due said
contractor for said work be paid to said contractor thirty -five
(35) days from and after final acceptance of said work as evi-
dence by the adoption of this resolution, but not sooner than
thirty (30) days after the date of the filing of notice of com-
pletion, excepting only such sum or sums as may lawfully be
withheld in accordance with the provisions of said contract
and contract documents. That acceptance by the contractor of
said payments made in accordance with said final estimate shall
operate and shall be a release to the City of Anaheim, its offi-
cers, agents and employees from all claims and liabilities due
the contractor for anything done or furnished or withheld or
for anything relating to the work or any act or neglect of the
City, its officers, agents and employees, excepting only claims
against the City for amounts withheld by the City at the time
of such payment.
AND BE IT FURTHER RESOLVED that the Mayor and the
City Clerk of the City of Anaheim be, and they are hereby
authorized to execute and file a notice of completion of said
work as required by law.
THE FOREGOING RESOLUTION is approved and signed by rye
this 8th day of February 19 77__
ATTEST:
CITY CLERK OF THE CITY OF ANAHEIM
/fm
MAY 1' TfE CIT OF ANAHEL%M
STATE OF CALIFORNIA
COUNTY OF ORANGE ss.
CITY OF ANAHEIM
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify
that the foregoing Resolution No. 77R -83 was introduced and adopted at a
regular meeting provided by law, of the City Council of the City of
Anaheim held on the 8th day of February, 1977, by the following vote of
the members thereof:
AYES: COUNCIL MEMBERS: Kaywood, Seymour, Kott, Roth and Thom
NOES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEMBERS: None
AND I FURTHER CERTIFY that the Mayor of the City of Anaheim approved and
signed said Resolution No. 77R -83 on the 8th day of February, 1977.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of
the City of Anaheim this 8th day of February, 1977.
(SEAL)
CITY CL RK OF THE CITY OF ANAHEIM
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify
that the foregoing is the original of Resolution No. 77R -83 duly passed
and adopted by the Anaheim City Council on February 8, 1977.