1985-094RESOLUTION NO. 85R-94
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ANAHEIM FINALLY ACCEPTING THE COMPLETION AND
THE FURNISHING OF ALL PLANT, LABOR, SERVICES,
MATERIALS AND EQUIPMENT AND ALL UTILITIES AND
TRANSPORTATION INCLUDING POWER, FUEL AND WATER,
AND THE PERFORMANCE OF ALL WORK NECESSARY TO
CONSTRUCT AND COMPLETE THE FOLLOWING PUBLIC
IMPROVEMENT, TO WIT:
BARRIER FREE ANAHEIM 9A - LA REINA STREET AT
SHADOW LANE; GREENLEAF AVENUE AT NANCITA
STREET; MAGNOLIA AVENUE 229 FEET SOUTH OF
GREENLEAF AVENUE, STONYBROOK DRIVE-DALE AVENUE
TO BADEN POWELL SCHOOL; BRONWYN DRIVE-ORANGE
AVENUE TO STONYBROOK DRIVE, IN THE CITY OF
ANAHEIM, ACCOUNT NOS. 24-793-6325-E3830 AND
24-793-6325-E3870.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation,
published and circulated in the City of Anaheim, to wit: The
Anaheim Bulletin, on the 16th and 23rd days of August, 1984,
inviting sealed proposals for furnishing the following:
All plant, labor, services, materials and equipment, and
all utilities and transportation, including power, fuel
and water, and performing all work necessary to construct
and complete in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings
therefor on file in the Office of the City Engineer or
City Clerk of the City of Anaheim, the following public
improvement, to wit:
Barrier Free Anaheim 9A - La Reina Street at Shadow Lane;
Greenleaf Avenue at Nancita Street; Magnolia Avenue, 229
feet south of Greenleaf Avenue; Stonybrook Drive-Dale
Avenue to Baden Powell School; Bronwyn Drive-Orange
Avenue to Stonybrook Drive, in the City of Anaheim,
consisting of clearing and grubbing; construction of 4"
and 8" P.C.C.; construction of curb and gutter;
construction of asphalt concrete; and all appurtenant
work as shown on the plans and delineated in the
specifications on file in the Office of the City
Engineer, Account Nos. 24-793-6325-E3830 and
24-793-6325-E3870,
in accordance with the designs, plans, profiles and specifications
prepared by the Public Works Department, and the notice inviting
sealed proposals, which said notice specified that sealed
proposals as specified in said notice would be received up until
2:00 o'clock P.M. on the 6th day of September, 1984, and which
said notice did state and declare that, pursuant to the provisions
of Section 1770 of the Labor Code, the City Council of the City of
Anaheim had ascertained the prevailing rate of wages for each type
of labor needed to execute said contract, and did state that the
prevailing hourly wage scale so ascertained was on file in the
Office of the City Clerk; and
WHEREAS, on the 6th day of September, 1984, at the hour
of 2:00 o'clock P.M., the City Clerk and the City Engineer of the
City of Anaheim did open said sealed proposals received up to that
time for the furnishing of all plant, labor, services, materials
and equipment, and all utilities and transportation, including
power, fuel and water, and performing all work necessary to
construct and complete, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings
therefor on file in the Office of the City Clerk of the City of
Anaheim, the public improvement hereinabove more particularly
described and set forth, in public, in the City Council Chamber in
the City Hall, Anaheim, California, and the City Engineer did
tabulate the result of said sealed proposals and did make a report
to the City Council at a meeting held no later than thirty (30)
days after the bids were opened; and
WHEREAS, the City Council of the City of Anaheim did, at
a subsequent regular or adjourned regular meeting, held on the 2nd
day of October, 1984, at the hour of 10:00 o'clock A.M., consider
the sealed proposals submitted for furnishing the materials and
performing the work hereinabove more particularly described and
set forth, and did thereupon find and determine that the sealed
proposal submitted by HARPER CONSTRUCTION COD4PANY, 2340 Secret
Drive, Running Springs, CA 92382 for the construction,
installation and completion of said Barrier Free Anaheim 9A - La
Reina Street at shadow Lane; Greenleaf Avenue at Nancita Street;
Magnolia Avenue, 229 feet south of Greenleaf Avenue; Stonybrook
Drive-Dale Avenue to Baden Powell School; Bronwyn Drive-Orange
Avenue to Stonybrook Drive, in the City of Anaheim, Account Nos.
24-793-6325-E3830 and 24-793-6325-E3870 hereinabove mentioned and
described, was the lowest responsible proposal submitted therefor,
and thereupon accepted said bid and did award a contract to said
contractor for furnishing all plant, labor, services, materials
and equipment and all utilities and transportation, including
power, fuel and water, and performing all work necessary to
construct and complete, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings, the
said public improvement as specified in said notice inviting
sealed proposals, and did authorize the Mayor and the City Clerk
of the City of Anaheim to execute a contract for and on behalf of
the City of Anaheim with said contractor, which said contract was
duly made and entered into on the 2nd day of January, 1985; and
-2-
WHEREAS, the said contractor has furnished all plant,
labor, services, materials and equipment and all utilities and
transportation, and performed all work necessary for the
construction and completion, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings of
said public improvement as specified in the notice inviting sealed
proposals and in the detailed designs, plans, drawings and
specifications prepared by the Public Works Department, and the
contract made and entered into with said contractor by the City of
Anaheim; and
WHEREAS, the City Engineer has duly certified to the
construction and completion of said public improvement hereinabove
mentioned and described, in accordance with the plans and
specifications and the contract documents duly made and entered
into with said contractor; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinabove more particularly
described in accordance with the provisions of the contract and
the contract documents, and that notice of completion should be
filed and payment of the balance due said contractor authorized in
accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Anaheim that all plant, labor, services, materials and
equipment and all utilities and transportation, and the
performance of all work necessary to construct, install and
complete in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings therefor on file in
the Office of the City Clerk of the City of Anaheim, together with
the appurtenances thereto, said public improvement hereinabove
more particularly described and set forth, in the City of Anaheim,
by said contractor, be, and the same are hereby, accepted subject,
nevertheless, to all the terms, conditions and provisions of the
contract documents, and that the balance due said contractor for
said work be paid to said contractor thirty-five (35) days from
and after final acceptance of said work as evidenced by the
adoption of this resolution, but not sooner than thirty (30) days
after the date of the filing of notice of completion, excepting
only such sum or sums as may lawfully be withheld in accordance
with the provisions of said contract and contract documents. That
acceptance by the contractor of said payments made in accordance
with said final estimate shall operate and shall be a release to
the City of Anaheim, its officers, agents and employees from all
claims and liabilities due the contractor for anything done or
furnished or withheld or for anything relating to the work or any
act or neglect of the City, its officers, agents and employees,
excepting only claims against the City for amounts withheld by the
City at the time of such payment.
AND BE IT FURTHER RESOLVED that the Mayor be, and he is
hereby, authorized to execute and file a notice of completion of
said work as required by law.
-3-
THE FOREGOING RESOLUTION is approved and adopted by the
City Council of the City of Anaheim this 26th day of February,
1985.
MAYOR OF THE CITY OF ANA EIM
ATTEST:
CITY CLERK OF THE CITY OF ANAHEIM
.,
-4-
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF ANAHEIM )
I, LEONORA N. SOHL, City Clerk of the City of Anaheim, do hereby certify that
the foregoing Resolution No. 85R-94 was introduced and adopted at a regular ,-~,,,,,~
meeting provided by law, of the City Council of the City of Anaheim held on
the 26th day of February, 1985, by the following vote of the members thereof:
AYES: COUNCIL MEMBERS: Kaywood, Bay, Pickler, Overholt and Roth
NOES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEMBERS: None
AND I FURTHER certify that the Mayor of the City of Anaheim signed said
Resolution No. 85R-94 on the 26th day of February, 1985.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of the
City of Anaheim this 26th day of February, 1985.
CITY CLERK OF HE CITY OF ANAHEIM
(SEAL)
I, LEONORA N. SOHL, City Clerk of the City of Anaheim, do hereby certify that
the foregoing is the original of Resolution No. 85R-94 duly passed and adopted
by the Anaheim City Council on February 26, 1985.
CI Y CLE
'"~'"~,