1982-301RESOLUTION NO. 82R -301
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE CQMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR, SER-
VICES, MATERIALS AND EQUIPMENT AND ALL UTIL-
ITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND WATER, A14D THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEMENT, TO WIT:
CERRITOS AVENUE STORM DRAIN IMPROVEMENT, 1048'
E/O ANAHEIM BOULEVARD TO ANAHEIM BOULEVARD AND
SUNKIST STREET TO 595' W/O SUNKIST STREET, IN
THE CITY OF ANAHEIM, ACCOUNT NOS.•13- 791 -6325-
E1180 AND 24 -791- 6325- E1150.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation
printed, published and circulated in the City of Anaheim, to wit:
The Anaheim Bulletin, on the 15th and 22nd days of October
19 81 , a notice inviting sealed
proposals for furnishing the following:
All plant, labor, services, materials and equipment,
and all utilities and transportation, including power,
fuel and water, and performing all work necessary to
construct and complete in a good and workmanlike man-
ner, in strict accordance with the specifications,
plans and drawings therefor on file in the Office of
the City Engineer or City Clerk of the City of Anaheim,
the following public improvement, to wit:
Cerritos Avenue storm drain improvement, 1048' E/o Anaheim
Boulevard to Anaheim Boulevard and Sunkist Street to 595'
W/o Sunkist Street, in the City of Anaheim, consisting of
the construction of 51 ", 42" and 18" RCP, 8" V.C.P.; P.C.C.
manholes, junction structures, collars, encasement, catch
basins, concrete removal; chain link fence removal and
replacement, compacted fill including import borrow, con-
crete removal and all other appurtenant work as shown on
the plans and delineated in the specifications on file in
the office of the City Engineer, Account Nos. 13- 791 -6325-
E1180 and _?-4 -791- 6325- Ell50,
in accordance with the designs, plans, profiles and specifica-
tions prepared by the Public Works Department
and the notice inviting sealed proposals, which said notice
Arr -40 -1-
specified that s, led proposals as specifies in said notice would
be received up until 2:00 o'clock P.M. of the 5th . day of
November , 19 , and which said notice state
declare that, pursuant to the provisions of Section 1770 of the
Labor Code, the City Council of the City of Anaheim had ascertained
the prevailing rate of wages for each type of labor needed to exe-
cute said contract, and did state that the prevailing hourly wage
scale so ascertained was on file in the Office of the City Clerkf
and
WHEREAS, on the 5 th day of November 19 , at
the hour of 2:00 o'clock P.M., the City Clerk and the City Engineer
of the City of Anaheim did open said sealed proposals received up
to that time for the furnishing of all plant, labor, services,
materials and equipment, and all utilities and transportation, in-
cluding power, .fuel and water, and performing all work necessary to
construct and complete, in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings therefor on
file in the Office of the City Clerk of the City of Anaheim, the
public improvement hereinabove more particularly described and set
forth, in public, in the City Council Chamber in the City Hall,
Anaheim, California, and the City Engineer did tabulate the result
of said sealed proposals and did make a report to the City Council
at its third subsequent regular or adjourned regular meeting;
and
WHEREAS, the City Council of the City of Anaheim did, at
its third subsequent regular or adjourned regular meeting, held
on the 24th day of November 2 19 , at the hour of 1:30
o'clock
.M., , consider the sealed proposals submitted for furnish-
ing the materials and performing the work hereinabove more particu-
larly described and set forth, and did thereupon find and determine
that the sealed proposal submitted by FIVE STATES PLUMBING, INC. &
JAMES I. LANGFORD PLUMBING, 677 Hariton St., Orange, Calit. 9269
for the construction, installation and completion of said
Cerritos Avenue storm drain improvement, e/o Anaheim Blvd. an un.cisE
., to w/o Sunkist St., in the City of Anaheim, Account Nos.
/91-632b- an - -E
hereinabove mentioned and
described, was the lowest responsible proposal submitted therefor,
and thereupon accepted said bid and did award a contract to said*
contractor for furnishing all plant, labor, services, materials and
equipment and all utilities and transportation, including power,
fuel and water, and performing all work necessary to construct and
complete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings, the said public im-
provement as specified in said notice inviting sealed proposals,
and did authorize the Mayor and the City Clerk of the City of
Anaheim to execute a contract for and on behalf of the City of
Anaheim with said contractor, which said contract was duly made and
entered into on the 22nd day of December , 19 81 ; and
WHEREAS, the said contractor has furnished all plant,
labor, services, materials and equipment and all utilities and
transportation, and performed all work necessary for the construc-
tion and completion, in a good and workmanlike manner, in strict
INIZ
accordance with the specifications, plans and drawings of said
public improvement as specified in the notice inviting sealed
proposals and in the detailed designs, plans, drawings and speci-
fications prepared by the Public Works Department, and the con-
tract made and entered into with said contractor by the City of
Anaheim; and
WHEREAS, the Public Works Executive Director has duly
certified to the construction and completion of said public im-
provement hereinabove mentioned and described, in accordance with
the plans and specifications and the contract documents duly made
and entered into with said contractor; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinabove more particularly
described in accordance with the provisions of the contract and
the contract documents, and that notice of completion should be
filed and payment of the balance due said contractor authorized
in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the per-
formance of all work necessary to construct, install and complete
in a good and workmanlike manner, in strict accordance with the
specifications, plans and drawings therefor on file in the Office
of the City Clerk of the City of Anaheim, together with the appur-
tenances thereto, said public improvement hereinabove more parti-
cularly described and set forth, in the City of Anaheim, by said
contractor, be, and the same are hereby, accepted subject, never-
theless, to all the terms, conditions and provisions of the contract
documents, and that the balance due said contractor for said work
be paid to said contractor thirty -five (35) days from and after
final acceptance of said work as evidenced by the adoption of this
resolution, but not sooner than thirty (30) days after the date of
the filing of notice of completion, excepting only such sum or sums
as may lawfully be withheld in accordance with the provisions of
said contract and contract documents. That acceptance by the con-
tractor of said payments made in accordance with said final estimate
shall operate and shall be a release to the City of Anaheim, its
officers, agents and employees from all claims and liabilities due
the contractor for anything done or furnished or withheld or for
anything relating to the work or any act or ne of the City,
its officers, agents and employees, excepting only claims against
the City for amounts withheld by the City at the time of such
payment.
AND BE IT FURTHER RESOLVED that the Mayor be, and he is
hereby, authorized to execute and file a notice of completion of
said work as required by law.
-3-
THE FOREGOING
by the City Council of
June Z982
RESOLUTION is approved and adopted
the City of Anaheim this 8th day of
ATTEST:
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.'
CITY OF ANAHEIM )
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify that
the foregoing Resolution No. 82R -301 was introduced and adopted at a regular
meeting provided by law, of the City Council of the City of Anaheim held on
the 8th day of June, 1982, by the following vote of tha members thereof:
AYES: COUNCIL MEMBERS: Overholt, Kaywood, Roth and Bay
NOES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEMBERS: None
VACANCY: COUNCIL WEMBERS: One
AND I FURTHER. CERTIFY that the Mayor of the City of Anaheim signed said
Resolution No. 82R -301 on the 8th day of June, 1982.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of the
City of Anaheim this 8th day of June, 1982.
C?e� '
CITY CLtRK OF THE CITY bF ANAHEIM
(SEAL)
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify that
the foregoing is the original of Resolution No. 82R -301 duly passed and
adopted by'the Anaheim City Council on June 8, 1982.
9 N WE - / 1 �0 I ffi�4111