1981-275RESOLUTION NU . 81R-275
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE CpMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR, SER-
VICES, MATERIALS AND EQUIPMENT AND ALL UTIL-
ITIES AND TRANSPORTATION INCLUDIIJG POWER,
FUEL AND WATER, AiJD THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEtdENT, TO WIT:
DOWNTOWN PROJECT ALPHA (PHASE I) STREF,T, SEWER,
WATER, STORM DRAIN AND ELECTRICAL IMPROVEMENTS,
IN THE CITY OF ANAHEIM, ACCOUNT NOS. 46-792-
6325-E2190, 82-366-6327-00957 AND•46-795-6325-
.E5210.
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of Qeneral circulation
printed, published and circulated in the City of Anaheim, to wit:
The Anaheim Bulletin, on the 29th day of March and 5th day of
April-- , 1979 , a notice inviting sealed
proposals for furnishing the following:
All plant, labor, services, materials and equipment,
and all utilities and transportation, including power,
fuel and water, and performing all work necessary to
construct and complete in a good and workmanlike man-
ner, in strict accordance with the specifications,
plans and drawings therefor on file in the Office of
the City Engineer or City Clerk of the City of Anaheim,
the following public improvement, to wit:
Downtown Project Alpha (Phase I) street, sewer, water, storm drain and
electrical improvements, Harbor Boulevard-Cypress Street to Broadway;
Lincoln Avenue-Olive Street to Harbor Boulevard; Anaheim Boulevard-
Cypress Street to Broadway; Clementine Street-Lincoln Avenue to Oak
Street; Broadway-Philadelphia Street to Anaheim Boulevard, in the City
of Anaheim, consisting of clearing and grubbing; excavation; removal
of A.C. and P.C.C. improvements; construction of P.C.C. alley gutter,
curb, gutter, sidewalk, driveways, planter walls, aprons and cross
gutter, construction of base material; construction of asphalt concrete
pavement; construction of asphalt concrete sidewalk and berm; construc-
tion of P.C.C. textured concrete; installation of metal beam guardrail;
installation of tree well grates; adjustment of valve covers and man-
holes to grade; construction of noise barrier walls; construction of
quarry the sidewalk; construction of RCP and RCB storm drain and man-
holes; construction of catch basins; sheeting, shoring and/or bracing;
construction of VCP sewer and manholes; construction of DI? water lines;
construction of irrigation service; installation of fire hydrants;
installation of landscaping; construction of irrigation system; construc-
tion of traffic signals and loops; modification of traffic signals;
installation of interconnect system; installation of street furniture;
placement of detour striping and construction signs; construction and
installation of street lighting and landscape lighting; installation of
electrical underground distribution system; and all appurtenant work as
shown on the plans and delineated in the specification on file in the
Office of the City Engineer, Account Nos. 46-792-6325-E2190, 82-366-
6327-00957 and 46-795-6325-E5210
in accordance with the designs, plans, profiles and specifica-
tions prepared by the Public Works Department
and the notice inviting sealed proposals, which said notice ~
Arr-ao -1-
specified that _aled proposals as specific., in said notice would
be received up until 2:00 o'clock P.M. of the 26th - day of
April ~, 1979 , and which said notice i state and
ec are t at, pursuant to the provisions of Section 1770 of the
Labor Code, the City Council of the City of Anaheim had ascertained
the prevailing rate of wages for each type of labor needed to exe-
cute said contract, and did state that the prevailing hourly wage
scale so ascertained was on file in the Office of the City Clerkf
and
WHEREAS, on the 26th day of April 1979 , at
the hour of-2:00 o'clock P.M., the City Clerk and the City Engineer
of the City of Anaheim did open said sealed proposals received up
to that time for the furnishing of all plant, labor, services,
materials and equipment, and all utilities and transportation, in-
cluding power, .fuel and water, and performing all work necessary to
construct and complete, in a good and workmanlike manner, in strict
accordance with the specifications, plans and drawings therefor on
file in the Office of the City Clerk oP the City of Anaheim, the
public improvement hereinabove more particularly described and set
forth, in public, in the City Council Chamber in the City Hall,
Anaheim, California, and the City Engineer did tabulate the result.
of said sealed proposals and did make a report to the City Council
at its fifth subsequent regular or adjourned regular meeting;
and __
WHEREAS, the City Council -of the City of Anaheim did, at
its fifth subsequent regular or adjourned regular meeting, held
on the 29th day of May , 1979 , at the hour of 1:30
o'clock~.M., consider the sealed proposals submitted for furnish-
ing the materials and performing the work hereinabove more particu-
larly described and set forth, and did thereupon find and determine
that the sealed proposal submitted by _SmEINY AND COMPANY- 7N_
4620 East La Palma Avenue Anaheim California 92807
for the construction, installation and completion of said
Downtown Project Alpha (Phase I) street, sewer, water, storm rc~ai~n and
electrical improvements, in the Citv of Anaheim Account Nos 46-792
6325-E2190, 82-366-6327-00957 and 46-795-6325-E5210,
hereinabove mentioned and
described, was the lowest responsible proposal submitted therefor,
and thereupon accepted said bid and did award a contract to said-
contractor for furnishing all plant, labor, services, materials and
.equipment and all utilities and transportation, including power,
fuel and water, and performing all work necessary to construct and
complete, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings, the said public im-
provement as specified in said notice inviting sealed proposals,
and did authorize the Mayor and the City Clerk of the City of
Anaheim to execute a contract for and on behalf of the City of
Anaheim with said contractor, which said contract was duly made and
entered into on the 4th day of June , 19 79; and
WHEREAS, the said contractor has furnished all plant,
labor, services, materials and equipment and all utilities and
transportation, and performed all work necessary for the construc-
tion and completion, in a good and workmanlike manner, in strict
-2-
accordance with the specifications, plans and drawings of said
public improvement as specified in the notice inviting sealed
proposals and in the detailed designs, plans, drawings and speci-
fications prepared by the Public Works Department, and the con-
tract made and entered into with said contractor by the City of
Anaheim; and
°°~ WHEREAS, the Public Works Executive Director has duly
certified to the construction and completion of said public im-
provement hereinabove mentioned and described, in accordance with
the plans and specifications and the contract documents duly made
and entered into with said contractor; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinabove more particularly
described in accordance with the provisions of the contract and
the contract documents, and that notice of completion should be
filed and payment of the balance due said contractor authorized
in accordance with the contract documents.
NO?~J, THEREFORE, BE IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the per-
formance of all work necessary to construct, install and complete
in a good and workmanlike manner, in strict accordance with the
specifications, plans and drawings therefor on file in the Office
of .the City Clerk of the City of Anaheim, together with the appur-
tenances thereto, said public improvement hereinabove more parti-
cularly described and set forth, in the City of Anaheim, by said
contractor, be, and the same are hereby, accepted subject, never-
theless, to all the terms, conditions and provisions of the contract
documents, and that the balance due said contractor for said work
be paid to said contractor thirty-five (35) days from and after
final acceptance of said work as evidenced by the adoption of this
resolution, but not sooner than thirty (30) days after the date of
the filing of notice of completion, excepting only such sum or sums
as may lawfully be withheld in accordance with the provisions of
said contract and contract documents. That acceptance by the con-
tractor of said payments made in accordance with said final estimate
shall operate and shall be a release to the City of Anaheim, its
officers, agents and employees from all claims and liabilities due
the contractor for anything done or furnished or withheld or for
anything relating to the work or any act or neglect of the City,
its officers, agents and employees, excepting only claims against
the City for amounts withheld by the City at the time of such
payment.
AND BE IT FURTHER RESOLVED that the Mayor be, and he is
hereby, authorized to execute and file a notice of completion of
said work as required by law.
-3-
THE FOREGOING
by the City Council of
June 1981 ,
ATTEST:
RESOLUTION is approved and adopted
the City of Anaheim this 9th day of
/fm
STATE OF CALIFORNIA )
COUNTY OF ORANGE ~ ss.
CITY OF ANAHEIM
I, LINP.A D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify that
the foregoing Resolution No. 81R-275 was introduced and adopted at a regular
meeting provided by law, of the City Council of the City of Anaheim held on
the 9th day of June, 19$1, by the following vote of the members thereof:
AYES: COUNCIL MEMBERS: Overholt, Kaywood, Bay, Roth and Seymour
NQES: COUNCIL MEMBERS: None
ABSENT: COUNCIL MEMBERS: None
AND I FUF'THER CERTIFY that the Mayor of the City of Anaheim signed said
Resolution No. 81R-275 on the gbh. day of ,Tune, 1981.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of the
City of Anaheim this 9th day of June, 1981.
CITY' C'ERK: OF THE CITY OF ANAHEIM
(-SEAL)
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify that
thE~ foregoing is the original of Resolution No. 81R-275 duly passed and adopted
by the Anaheim City Council on June 9, 1981.
t/~~F.-..c~aJ
CITY CLERk: