1981-333RESOLUTION N0. 81R-333
L.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF ANAHEIM FINALLY ACCEPTING THE CQMPLETION
AND THE FURNISHING OF ALL PLANT, LABOR, SER-
VICES, MATERIALS AND EQUIPMENT AND ALL UTIL-
ITIES AND TRANSPORTATION INCLUDING POWER,
FUEL AND WATER, A21D THE PERFORMANCE OF ALL
WORK NECESSARY TO CONSTRUCT AND COMPLETE THE
FOLLOWING PUBLIC IMPROVEMENT, TO WIT:
GEORGE WASHINGTON COMMUNITY CENTER, I!V THE
CITY OF ANAHEIM, ACCOUNT NO. 25-848-7105-84808•
WHEREAS, the City Council of the City of Anaheim did
cause to be published in a newspaper of general circulation
printed, published and circulated in the City of Anaheim, to wit:
The Anaheim Bulletin, on the 7th and 14th days of Auaust
19 80, a notice inviting sealed
proposals for furnishing the following:
All plant, labor, services, materials and equipment,
and all utilities and transportation, including power,
fuel and water, and performing all work necessary to
construct and complete in a good and workmanlike man-
ner, in strict accordance with the specifications,
plans and drawings therefor on file in the Office of
the City Engineer or City Clerk of the City of Anaheim,
the following public improvement, to wit:
George Washington Community Center, in the City of
Anaheim, consisting of remo~~eling including but not
limited to site work and landscaping, concrete, carpen-
try, glazing, electrical, HUAC and finishes and shall
be completed as shown on the plans and delineated in
the specifications; contractor shall provide, install,
perform and pay for all work, labor, material, equipment,
transpori.atiooi =~~~arges, taxes and all ayaour'r_enani: ice~ns
necessary to complete the project as shown on the plans
and delineated in specifications on file in the office
of the City Engineer, Account No. 25-848-7105-84808:-
in accordance with the designs, plans, profiles and specifica-
tions prepared by the Public Works Department ,
and the notice inviting sealed proposals, which said notice
Arr-ao -1-
specified that ..waled proposal's as specified in said notice would
be received up until 200 o'clock P.M. of the 28th - day of
Au ust ~, 19 $Q, and which said notice id state and
ed Clare twat, pursuant to the provisions of Section 1770 of the
Labor Code, the City Council of the City of Anaheim had ascertained
the prevailing rate of wages for each type of labor needed to exe-
cute said contract, and did state that the prevailing hourly wage
scale so ascertained was on file in the Office of the City Clerk;
.~. ~ and
~JHEREAS, on the 28th day of Auaust , 19 80, at
the hour of 2:00 o'clock P.M., the City Clerk and the City Engineer
of the City of Anaheim did open said sealed proposals received up
to that time for. the furnishing of all plant, labor, services,
materials and equipment, and all utilities and transportation, in-
cluding power, .fuel and water, and performing all work necessary to
construct and complete, in a good and workmanlike manner, in strict
accordanc with the specifications, plans and drawings therefor on
file in t~e Office of the City Clerk of the City of Anaheim, the
public improvement hereinabove more particularly described and set
forth, in public, in the City Council Chamber in the City Hall;
Anaheim, California, and the City En~zineer did tabulate the result
of said sealed proposals and did make a report to the City Council
at its fourth subsequent regular or adjourned regular meeting;
and __: •
WHEREAS, the City Council •of the City of Anaheim did, at
its fourth subsequent regular or adjourned regular meeting, held
on the 23rd day of September , 1980 , at the hour of 1:30
o'clock-~.M., consider the sealed proposals submitted for furnish-
ing the materials and performing the work hereinabove more particu-
larly described and set forth, and did thereupon find and determine
that the sealed proposal submitted by BUILDERS WEST, 1608-B North'
Main Street, Santa Ana,. California 92701
for the construction, installation and completion of said
George Washington Community Center, in the City of Anaheim. Account
No. 25-848-7105-84808
hereinabove mentioned and
described, was the lowest responsible proposal submitted therefor,
and thereupon accepted said bid and did award a contract to said'
contractor for furnishing all plant, labor, services, materials and
equipment and all utilities and transportation, including power,
.fuel and water, and performing all work necessary to construct and
complete, in a good and workmanlike manner, in strict.accordanee
with the specifications, plans and drawings, the said public im-
provement as specified in said notice inviting sealed proposals,
and did authorize the Mayor and the City Clerk of the City of
Anaheim to execute a contract for and on behalf of the City of
Anaheim with said contractor, which said contract was duly made and
entered into on the 30th day of september , 1980 ; and
WHEREAS, the said contractor has furnished all plant,
labor, services, materials and equipment and all utilities and
transportation, and performed all work necessary for the construc-
tion and completion, in a good and workmanlike manner, in strict
-2-
accordance with the specifications, plans and drawings of said
public improvement as specified in the notice inviting sealed
proposals and in the detailed designs, plans, drawings and speci-
fications prepared by the Public Works Department, and the con-
tract made and entered into with said contractor by the City of
Anaheim; and
WHEREAS, the Public Works Executive Director has duly
certified to the construction and completion of said public im-
provement hereinabove mentioned and described, in accordance with
the plans and specifications and the contract documents duly made
and entered into with said contractor; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinabove more particularly
described in accordance with the provisions of the contract and
the contract documents, and that notice of completion should be
filed and payment of the balance due said contractor authorized
in accordance with the contract documents.
NO!~1, THEREFORE, BE IT RESOLVED by the City Council of
the City of Anaheim that all plant, labor, services, materials
and equipment and all utilities and transportation, and the per-
formance of all work necessary to construct, install and complete
in a good and workmanlike manner, in strict accordance with the
specifications, plans and drawings therefor on file in the Office
of the City Clerk of the City of Anaheim, together with the appur-
tenances thereto, said public improvement hereinabove more parti-
cularly described and set forth, in the City of Anaheim, by said
contractor, be, and the same are hereby, accepted subject, never-
theless, to all the terms, conditions and provisions of the contract
documents, and that the balance due said contractor for said work
be paid to said contractor thirty-five (35> days from and after
final acceptance of said work as evidenced by the adoption of this
resolution, but not sooner than thirty (30) days after the date of
the filing of notice of completion, excepting only .such sum or sums
as may lawfully be withheld in accordance with the provisions of
said contract and contract documents. That acceptance by the con-
tractor of said payments made in accordance with said final estimate
shall operate and shall be a release to the City of Anaheim, its
officers, agents and employees from all claims and liabilities due
the contractor for anything done or furnished or withheld or for
anything relating to the work or any act or neglect of the City,
its officers, agents and employees, excepting only claims against
the City for amounts withheld by the City at the time of such
payment.
AND BE IT FURTHER RESOLVED that the Mayor be, and he is
hereby, authorized to execute and file a notice of completion of
said work as required by law.
-3-
v_ THE FOREGOING RESOLUTION is approved and adopted
by the City Council of the City of Anaheim this 14th day of
July 1981
~ // ,~
i ~y
PRO TEM
ATTEST:
/fm
-~+
'"'~~„+.
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) ss.
CITY OF ANAHEIM )
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify
that the foregoing Resolution No. 81R-333 was introduced and adopted at a
regular meeting provided by law, of the City Council of-the City of Anaheim
held on the 14th day of-July, 1981, by the following vote of the members
thereof t
AYES: COUNCIL MEMBERS: Overholt, Kaywood, Bay and Roth
NOES: COUNCIL MEMBERS: None
ASSENT: COUNCIL MEMBERS: Seymour
AND I FURTHER CERTIFY that the Mayor Pro Tem of the City of Anaheim signed
said Resolution No. 81R-333 on the 14th day of July, 1981.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of the
City of Anaheim this 14th day of July, 1981. ~
CITY C ERK OF THE C TY OF ANAHEIM
(SEAL)
I, LINDA D. ROBERTS, City Clerk of the City of Anaheim, do hereby certify
that the foregoing is the original of Resolution No. 81R-333 duly passed
and adopted by the Anaheim City Council on-July 14, 1981.