ARA1976-045RESOLUTION NO. ARA76- 45
A RESOLUTION OF THE ANAHEIM REDEVELOPMENT AGENCY
DETERMINING CERTAIN PUBLIC IMPROVEMENTS TO BE
OF BENEFIT TO REDEVELOPMENT PROJECT ALPHA PROJECT
AREA; AND APPROVING AND AUTHORIZING THE EXECUTION
OF A COOPERATION AND REIMBURSEMENT AGREEMENT
THEREFOR BETWEEN THE CITY AND THE AGENCY.
WHEREAS, the City of Anaheim (the "City ") is under-
taking certain public improvements in the Redevelopment
Project Alpha Project area; and
WHEREAS, the installation of such public improve-
ments is necessary for the execution of Redevelopment Project
Alpha under the provisions of the California Community
Redevelopment Law (Health and Safety Code, Sections 33000 et
seq.) and pursuant to the Redevelopment Plan for Redevelopment
Project Alpha; and
WHEREAS, the Anaheim Redevelopment Agency desires to
reimburse and pay the City for the costs of such public improve-
ments, the terms and conditions of such reimbursement being
contained in that certain "Cooperation and Reimbursement
Agreement" (hereinafter "Agreement ") between the City and the
Agency; and
WHEREAS, a list of said public improvements is
attached hereto as Attachment 1 (said attachment consisting of
four pages);
WHEREAS, the terms and conditions of said Agreement
are acceptable to the Anaheim Redevelopment Agency; and
WHEREAS, Section 33445 of the California Health and
Safety Code requires the Anaheim Redevelopment Agency to
determine the issue of benefit to the Redevelopment Project
Alpha Project area prior to such payments being made by the
Agency to the City.
WHEREAS, a Final Environmental Impact Report has
been approved and adopted for Redevelopment Project Alpha and
the Anaheim Redevelopment Agency, the Community Redevelopment
Commission, and the City Council of the City of Anaheim have
certified to the completion of the Final Subsequent Environ-
mental Impact Report for the Second Amendment to the
Redevelopment Plan for Redevelopment Project Alpha.
NOW, THEREFORE, BE IT RESOLVED by the Anaheim
Redevelopment Agency as follows:
1. The Anaheim Redevelopment Agency hereby finds
and determines that the environmental impacts
related to the construction and installation
of the public improvements set forth in
Attachment 1 were considered under the circum-
stances presented in the Final Environmental
Impact Report and Final Subsequent Environmental
Impact Report, and that therefore, a Subsequent
Environmental Impact Report need not be prepared.
-1-
2. The Anaheim Redevelopment Agency hereby certifies
that it has reviewed and considered the informa-
tion contained in the Final Environmental Impact
Report and Final Subsequent Environmental Impact
Report.
3. The Anaheim Redevelopment Agency hereby finds and
determines that the installation and construction
of the public improvements pursuant to the Agreement
will not have a significant effect or substantial
adverse impact on the environment.
4.' It is hereby determined that the installation of
the public improvements as set forth in Attach-
ment 1 is of benefit to the Redevelopment Project
Alpha Project area.
5. The Anaheim Redevelopment Agency hereby approves the
terms and conditions of said "Cooperation and
Reimbursement Agreement."
6. The Chairman and Secretary are hereby authorized
and directed to execute said Agreement on behalf
of the Anaheim Redevelopment Agency.
THE FOREGOING RESOLUTION is approved and signed lby
me this 28th day of December, 1976 �^
k 1 /Z
ANAHEITY REDEVELOPMENT AGENCY
ATTEST:
SECRETARY
ANAHEIM REDEVELOPMENT AGENCY
MES:jh
-2-
STATE OF CALIFORNIA )
COUNTY OF ORANGE )
CITY OF ANAHEIM )
I, LINDA D. ROBERTS, Secretary of the Anaheim Redevelopment Agency,
do hereby certify that the foregoing Resolution No. ARA76 -45 was
passed and adopted at a regular meeting;of the Anaheim Redevelop-
ment Agency held on the 28th day of December, 1976, by the following
vote of the members thereof:
AYES: AGENCY MEMBERS: Kaywood, Seymour, Kott, Roth and Thom
NOES: AGENCY MEMBERS: None
ABSENT: AGENCY MEMBERS: None
AND I FURTHER CERTIFY that the Chairman of the Anaheim Redevelopment
Agency approged and signed said Resolution on the 28th day of December,
1976.
IN WITNESS WHEREOF, I have hereunto set my hand and seal this 28th day
of December, 1976.
SECK OF THE ANAHEIM REDEVELOPMENT AGENCY
(SEAL)
2uiqun000V
aouauzg
• iooV quauidojaA@a •uuu00
a043aaTa aAT noaxS
f R
• REDEVELOPMENT PROJECT ALPHA
PUBLIC IMPROVEMENTS
PROJECTS
ATTACHMENT NO. 1
PROJECT NO. 1 OFF SITE STORM DRAIN
Description:
Mainline storm drain extending
from the Carbon Creek Channel
to the westerly limit of the
Downtown portion of the Rede-
veiopement Project area at
Harbor Boulevard.
Cost Estimate:
$3,200,000
PROJECT NO. 2 OFF SITE SEWER
Description:
Trunk sewer extending from ex-
isting 24 trunk sewer at.West
Street and Vermont Avenue to
the Downtown portion of the
Redevelopment Project area at
Lincoln Avenue and Lemon Street.
Cost Estimate: $ 600,000
PROJECT NO. 3 OFF SITE WATER MAINS
Description:
Twelve inch (12 ") water main in
Lemon Street extending from the
existing trunk line in Vermont
Avenue to the Downtown portion
of the Redevelopment Project
area at Lincoln Avenue.
Cost Estimate: $ 1- 60,000
ROJECT NO. 4 . .. ... ' ..RAMOR BOULEVARD WtDENtNG
Description:
Construction of ultimate road-
way improvements along the
easterly side of Harbor
Boulevard extending through
the Downtown portion of the
Redevelopment Project area
from Broadway to Cypress
Street, including storm drain
extension from Chartres Street
to Lincoln.Avenue.
Cost Estimate:
Roadway improvements
Storm drain improvements
Right of way acquisition
Sub Total
$ 785,000
PROJECT NO. 5 ULTIMATE ROADWAY IMPROVE-
MENTS FOR ANAHEIM BOULE-
VARD FROM CYPRESS STREET
TO BROADWAY
Description:
Construction of ultimate
roadway improvements for
Anaheim Boulevard extend-
ing to Cypress Street to
Broadway, including
sewer, storm drain, and
water lines.
Cost Estimate:
Road improvements $ 330,000
Sewer improvements 17,000
Water improvements 54,000
Storm drain improvements 113,000
Right of way acquisition 2,375,000
Sub Total $2,889,000
$ 160,000
75,000
550,000
M-M
PROJECT NO. 6 BROADWAY WIDENING FROM
HARBOR BOULEVARD TO
CLEMENTINE STREET
Description:
Construction of ultimate
roadway improvements
along the northerly side
of Broadway extending
from Harbor Boulevard to
Clementine Street, in-
cluding water lines.
Cost Estimate:
Roadway improvements
Water improvements
Sub Total
$ 98,000
20,000
$ 118,000
PROJECT NO. 7 BROADWAY WIDENING FROM
CLEMENTINE.STREET TO
ANAHEIM BOULEVARD
Description:
Construction of ultimate
roadway improvements
along northerly side of
Broadway extending from
Clementine Street to
Anaheim Boulevard, in-
cluding sewer and water
lines.
Cost Estimate:
Roadway improvements $ 115,000
Sewer improvements 25,000
Water improvements 26___ ,000
Sub Total
- 3 -
$ 166,000
f
PROJECT NO. 8 RELOCATION OF UTILITIES
WITHIN SENIOR CITIZENS
HOUSING SITE
Description:
Relocation of existing
sewer and water lines
from within proposed
Senior Citizens housing
development site to an
off -site location.
Cost Estimate:
Sewer relocation $ 11,000
Water relocation 4,500
Sub Total $ 15,500
PROJECT NO. 9 CONSTRUCTION OF EAST
RICHFIELD CHANEL
Description:
Construction of East
Richfield storm drain
channel south of Orange -
thorpe to the Santa Ana
River Channel in cooper-
ation with Orange County.
Agency to fund 50% of
total lost.
Cost Estimate:
Total project $ 500,000
Agency share (50 %) 250,000
Sub Total $ 250,000
GRAND TOTAL
$8,183,500