ARA1978-066RESOLUTION NO. ARA78 -66
A RESOLUTION OF THE ANAHEIM REDEVELOPMENT
AGENCY ACCEPTING SEALED PROPOSALS AND
AWARDING CONTRACTS TO THE LOWEST RESPONSIBLE
BIDDERS FOR DEMOLITION AND CLEARANCE OF
CERTAIN AGENCY PROPERTIES.
WHEREAS, the Anaheim Redevelopment Agency did cause
to be published in a newspaper of general circulation, printed,
published and circulated in the City of Anaheim, to wit: The
Anaheim Bulletin, on the 11th and 18th days of May, 1978, a
notice inviting sealed proposals for demolition and site
clearance of the following Agency properties, to wit:
Demolition, grading and site clearance of all structures,
including existing utility connections; and all appurtenant
work as outlined in the specifications on file in the
Agency offices, Contract No. D78 -4 of the following
Agency properties:
Item Street Address
Block /Parcel
1 411
West Chestnut
15/7
2 201
North Emily
6/7
3 101
East Lincoln
5/13
in accordance with the specifications on file in the Office of
the Secretary of the Agency; and
WHEREAS, said notice inviting sealed proposals for said
demolition and clearance did provide that sealed proposals would
be received by the Anaheim Redevelopment Agency at the Office of
the Secretary of the Anaheim Redevelopment Agency up to the hour
of 2:00 o'clock P.M. on the 25th day of May, 1978, for the
furnishing of all plant, labor, services, materials and equipment,
all utilities and transportation, including power, fuel and water,
and performing all work necessary to complete in a good and
workmanlike manner, the demolition and clearance hereinabove more
particularly mentioned and described, and which notice did state
and declare that pursuant to the provisions of Section 1770 of
the Labor Code, the Anaheim Redevelopment Agency had ascertained
the prevailing rate of wages in the locality in which this type
of labor is to be performed for each craft or type of workman or
mechanic needed to execute the contract, and which wage scale is
on file in the Offices of the Secretary of the Agency; and
-1-
WHEREAS, the Secretary of the Agency did receive the
following sealed proposals prior to 2:00 o'clock P.M. on the
25th day of May, 1978, in response to the notice aforesaid
inviting sealed proposals, to wit:
CONTRACTOR NAME
ITEM 1 ITEM 2 ITEM 3 ITEM 4*
ECCO CONTRACTORS $ 7,600.00
$6,900.00
$14,900.00
$28,800.00
HINTZ WRECKING CO. 6
4,500.00
4,000.00
14,900.00
CCC LAND CLEARING 19,400.00
5,200.00
5,200.00
29,400.00
ECONOMY LAND CLEAR. 26,500.00
4,500.00
1,000.00
32,000.00
* total bid for all buildings listed in Items 1, 2 & 3
WHEREAS, the Agency Representative did thereupon examine
and tabulate said sealed proposals and did report to the Anaheim
Redevelopment Agency the result of his examination and tabulation;
and
WHEREAS, the Anaheim Redevelopment Agency finds that
the sealed proposals submitted by Hintz Wrecking Co., Inc. for
Items 1 and 2, and by Economy Land Clearing and Wrecking for Item 3
are the lowest responsible proposals submitted for the furnishing
of all plant, labor, services, materials and equipment, all
utilities and transportation, including power, fuel and water
-2-
and performing all work necessary to complete in a good and work -
manlike manner, in strict accordance with the specifications
therefor on file in the Office of the Secretary of the Agency,
the demolition and clearance hereinabove mentioned and described,
together with the appurtenances thereto, and as specified in the
notice inviting sealed proposals, and that said proposal of said
above -named bidder should be accepted and a contract awarded to
said bidder in accordance therewith; and
WHEREAS, the Anaheim Redevelopment Agency finds that
the above - mentioned sealed proposal.is the lowest responsible
proposal received and that the person, firm or corporation sub-
mitting said proposal is a responsible person, firm or corpora-
tion and that the proposal submitted is the best suited and fitted
for the demolition and clearance to be undertaken.
NOW, THEREFORE, BE IT RESOLVED by the Anaheim Redevelop-
ment Agency that the sealed proposal submitted by said contractor
for the furnishing of all plant, labor, services, materials and
equipment, all utilities and transportation, including power, fuel
and water, and performing all work necessary to complete, in a
good and workmanlike manner, in strict accordance with the speci-
fications therefor on file in the Office of the Secretary of the
Anaheim Redevelopment Agency and the notice inviting sealed pro-
posals, the demolition and clearance hereinabove more particularly
mentioned and described, together with the appurtenances thereto,
be, and the same is hereby, accepted, and that a contract for the
completion of said demolition and clearance be, and the same is
hereby, awarded to the said above -named bidder.
AND BE IT FURTHER RESOLVED that the successful bidder
or bidders upon each contract awarded as hereinabove set forth,
shall be, and they are hereby required to execute a contract in
the required form with the Anaheim Redevelopment Agency upon the
terms and conditions specified-in the notice inviting sealed
proposals and the proposal submitted by said successful bidder
or bidders and in accordance with the specifications for said
demolition and clearance hereinabove described, and in accordance
with the terms, conditions and provisions of this resolution, and
that said successful bidder or bidders to whom each contract is
awarded shall be required to furnish a surety bond in an amount
equal to one hundred percent (100 %) of the contract price for all
labor, materials and equipment to be furnished and performed, as
set forth in the sealed proposal submitted by said bidder for the
demolition and clearance, together with the appurtenances thereto
or such portion thereof as is covered by said contract, as secur-
ity for the faithful performance of said contract, and a separ-
ate surety bond in an amount equal to one hundred percent (100 %)
of the cost of said demolition and clearance covered by said
contract, as security for the payment of all persons performing
labor and furnishing material for said demolition and clearance.
AND BE IT FURTHER RESOLVED that said successful bidder
or bidders be, and they are hereby,required to furnish to the
- 3 -
Anaheim Redevelopment Agency in companies satisfactory to the
Anaheim Redevelopment Agency, public liability, property damage,
compensation, and other insurance in the amounts and for the
purposes set forth and specified in the notice inviting sealed
proposals, and subject to the approval of the General Counsel
of the Agency as to form and sufficiency.
AND BE IT FURTHER RESOLVED that the Chairman and
Secretary of the Anaheim Redevelopment Agency be, and they are
hereby, authorized and directed to make, execute and enter into,
for and on behalf of the Anaheim Redevelopment Agency, a written
contract with said successful bidder or bidders for the furnish-
ing of all plant, labor, materials, and equipment and performing
all work, as hereinabove more particularly described for the
completion of said demolition and clearance hereinabove described
upon the terms and conditions as specified in the notice inviting
sealed proposals, the specifications, and all addenda thereto,
and all modifications incorporated therein prior to the date of
the opening of bids, on file in the Office of the Secretary of
the Anaheim Redevelopment Agency and in strict accordance with
the terms, conditions and provisions of this resolution, and in
accordance with all of the contract documents herein specified.
THE FOREGOING RESOLUTION is approved and signed by me
this 6th day of June , 19 /-)
ATTEST:
SECRETARY
ANAHEIM REDEVELOPMENT AGENCY
- 4 -
STATE OF CALIFORNIA )
COUNTY OF ORANGE )
CITY OF ANAHEIM )
I, LINDA D. ROBERTS, Secretary of the Anaheim Redevelopment Agency, do
hereby certify that the foregoing Resolution No. ARA78 -66 was passed and
adopted at a regular meeting of the Anaheim Redevelopment Agency held on
the 6th day of June, 1978, by the following vote of the members thereof:
AYES: AGENCY MEMBERS: Overholt, Kaywood, Kott, Roth and Seymour
NOES: AGENCY MEMBERS: None
ABSENT: AGENCY MEMBERS: None
AND I FURTHER CERTIFY that the Chairman of the Anaheim Redevelopment
Agency signed said Resolution on the 6th day of June, 1978.
IN WITNESS WHEREOF, I have hereunto set my hand and seal this 6th day of
June, 1978.
SECRETARt OF THE ANAHEI REDEVELOPMENT AGENCY