ARA1979-013RESOLUTION NO. ARA79 - 13_
A RESOLUTION OF THE ANAHEIM REDEVELOPMENT
AGENCY ACCEPTING THE COMPLETION AND FURNISH-
ING OF ALL PLANT, LABOR, SERVICES, MATERIALS
AND EQUIPMENT AND ALL UTILITIES AND TRANS-
PORTATION INCLUDING POWER, FUEL AND WATER,
AND THE PERFORMANCE OF ALL WORK NECESSARY
TO COMPLETE A WORK OF IMPROVEMENT.
WHEREAS, the Anaheim Redevelopment Agency did award a contract for
furnishing all plant, labor, services, materials and equipment and all util-
ities and transportation, including power, fuel and water, and performing all
work necessary to complete in a good and workmanlike manner in strict accord-
ance with the specifications, plans and drawings for the following described
work of improvement, to wit:
Demolition and site clearance of Agency -owned
properties as listed:
STREET ADDRESS
AGENCY
BLOCK /PARCEL
140
W.
Lincoln
Ave.
18/9
138
W.
Lincoln
Ave.
18/9
134
W.
Lincoln
Ave.
18/10
132
W.
Lincoln
Ave.
18/10
124
W.
Lincoln
Ave.
18/10
212
W.
Lincoln
Ave.
17/5
232
W.
Lincoln
Ave.
17/3
114
N.
Clementine
3/12
WHEREAS, the contractor has furnished all plant, labor, services,
materials and equipment and all utilities and transportation, and performed
all work necessary for the completion, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings of said public
improvement as specified in the detailed designs, plans, drawings and speci-
fications prepared by the Anaheim Redevelopment Agency, and the contract made
and entered into with said contractor by the Anaheim Redevelopment Agency; and
WHEREAS, the Anaheim Redevelopment Agency has duly certified to the
completion of said public improvement hereinabove mentioned and described, in
accordance with the plans and specifications and the contract documents duly
made and entered into with said contractor; and
WHEREAS, the Anaheim Redevelopment Agency finds that said contractor
has completed said public improvement hereinabove more particularly described
in accordance with the provisions of the contract and the contract documents,
and that Notice Of Completion should be filed and payment of the balance due
said contractor authorized in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the Anaheim Redevelopment Agency
that all plant, labor, services, materials and equipment and all utilities and
transportation, and the performance of all work necessary to construct, install
and complete in a good and workmanlike manner, in strict accordance with the
specifications, plans and drawings therefor on file in the Office of the Anaheim
Redevelopment Agency, together with the appurtenances thereto, said public
improvement hereinabove more particularly described and set forth, in the City
of Anaheim, by said contractor, be, and the same are hereby, accepted subject,
nevertheless, to all terms, conditions and provisions of the contract documents
and that the balance due said contractor for said work be paid to said contractor
thirty -five (35) days from and after final acceptance of said work as evidenced
by the adoption of this resolution, but not sooner than thirty (30) days after
the date of the filing of Notice Of Completion, excepting only such sum or sums
as may lawfully be withheld in accordance with the provisions of said contract
and contract documents. That acceptance by the contractor of said payments made
in accordance with said final estimate shall operate and shall be a release to
the Anaheim Redevelopment Agency, its officers, agents and employees from all
claims and liabilities due the contractor for anything done or furnished or
withheld or for anything relating to the work or any act or neglect of the
Anaheim Redevelopment Agency, the City of Anaheim, its officers, agents and
employees, excepting only claims against the Anaheim Redevelopment Agency for
amounts withheld by the Anaheim Redevelopment Agency at the time of such payment.
AND BE IT FURTHER RESOLVED that the Chairman be, and he is hereby,
authorized to execute and file Notice Of Completion for said work as provided by
law.
THE FOREGOING RESOLUTION is approved and adopted by the Anaheim
Redevelopment Agency this 20th day of Fe bruary , 1979•
ATTEST:
C4- a'4-2 Z. 244r-e-le
Secretary
ANAHEIM REDEVELOPMENT AGENCY
MES: jw
i unai n
ANAHEIM RED LOPMENT AGENCY
- 2 -
STATE OF CALIFORNIA )
COUNTY OF ORANGE )
CITY OF ANAHEIM )
I, LINDA D. ROBERTS, Secretary of the Anaheim Redevelopment Agency, do
hereby certify that the foregoing Resolution No. ARA79 -13 was passed and
adopted at a regular meeting of the Anaheim Redevelopment Agency held on
the 20th day of February, 1979, by the following vote of the members thereof:
AYES: AGENCY MEMBERS: Kaywood, Kott, Roth and Seymour
NOES: AGENCY MEMBERS: None
ABSENT: AGENCY MEMBERS: Overholt
AND I FURTHER CERTIFY that the Chairman of the Anaheim Redevelopment
Agency signed said Resolution on the 20th day of February, 1979.
IN WITNESS WHEREOF, I have hereunto set my hand and seal this 20th day of
February, 1979.
SECRETA' OF THE ANAHE REDEVELOPMENT AGENCY
(SEAL)