ARA1985-018RESOLUTION NO. ARA85 -18
A RESOLUTION OF THE ANAHEIM REDEVELOPMENT
AGENCY ACCEPTING THE COMPLETION AND FURNISHING
OF ALL PLANT, LABOR, SERVICES, MATERIALS AND
EQUIPMENT AND ALL UTILITIES AND TRANSPORTATION
INCLUDING POWER, FUEL AND WATER AND THE
PERFORMANCE OF ALL WORK NECESSARY TO COMPLETE
A WORK OF IMPROVEMENT. (Contract No. D84 -3)
(CHARLIE L. CLARK DBA THREE D SERVICE COMPANY
WHEREAS, the Anaheim Redevelopment Agency did award a
contract to CHARLIE L. CLARK dba THREE D SERVICE COMPANY, 4300
Alderson, Baldwin Park, California 91706, for furnishing all
plant, labor, services, materials and equipment and all utilities
and transportation, including power, fuel and water, and
performing all work necessary to construct and complete in a good
and workmanlike manner in strict accordance with the
specifications, plans and drawings for the following described
work of improvement, to wit:
Demolition and site clearance of various Agency properties
described in Exhibit A attached hereto and incorporated by
reference herein; and
WHEREAS, the contractor has furnished all plant, labor,
services, materials and equipment and all utilities and transport-
ation, and performed all work necessary for the construction and
completion, in a good and workmanlike manner, in strict accordance
with the specifications, plans and drawings of said public im-
provement as specified in the detailed designs, plans, drawings
and specifications prepared by the Community Development
Department, and the contract made and entered into with said con-
tractor by the Anaheim Redevelopment Agency; and
WHEREAS, the Executive Director has duly certified to
the construction and completion of said public improvement herein -
above mentioned and described, in accordance with the plans and
specifications and the contract documents duly made and entered
into with said contractor; and
WHEREAS, the Anaheim Redevelopment Agency finds that
said contractor has completed said public improvements hereinabove
more particularly described in accordance with the provisions of
the contract and the contract documents, and that notice of com-
pletion should be filed and payment of the balance due said con-
tractor authorized in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the Anaheim
Redevelopment Agency that all plant, labor, services, materials
and equipment and all utilities and transportation, and the per-
formance of all work necessary to construct, install and complete
in a good and workmanlike manner, in strict accordance with the
specifications, plans and drawings therefor on file in the Office
of the Anaheim Redevelopment Agency, together with the appurten-
ances thereto, said public improvement hereinabove more particu-
larly described and set forth, in the City of Anaheim, by said
contractor, be, and the same are hereby, accepted subject, never-
theless, to all the terms, conditions and provisions of the con-
tract documents and that the balance due said contractor for said
work be paid to said contractors thirty -five (35) days from and
after final acceptance of said work as evidenced by the adoption
of this resolution, but not sooner than thirty (30) days after the
date of the filing of notice of completion, excepting only such
sum or sums as may lawfully be withheld in accordance with the
provisions of said contract and contract documents. That accept-
ance by the contractor of said payments made in accordance with
said final estimate shall operate and shall be a release to the
Anaheim Redevelopment Agency, its officers, agents and employees
from all claims and liabilities due the contractor for anything
done or furnished or withheld or for anything relating to the work
or any act or neglect of the Anaheim Redevelopment Agency, the
City of Anaheim, its officers, agents and employees, excepting
only claimns against the Anaheim Redevelopment Agency for amounts
withheld by the Anaheim Redevelopment Agency at the time of such
payments.
BE IT FURTHER RESOLVED that the Chairman be, and he is
hereby, authorized to execute and file notice of completion for
said work as provided by law.
THE FOREGOING RESOLUTION is approved and adopted by the
Anaheim Redevelopment Agency this 10th day of September, 1985.
Z 4. 4 04
CHAIRMAN
ANAHEIM REDEVELOPMENT AGENCY
ATTEST:
SECRETARY
ANAHEIM REDEVELOPMENT AGENCY
/fm
4114M
082385
-2-
STATE OF CALIFORNIA )
COUNTY OF ORANGE )
CITY OF ANAHEIM )
I, LEONORA N. SOHL, Secretary of the Anaheim Redevelopment Agency, do hereby
certify that the foregoing Resolution No. ARA85 -18 was passed and adopted at a
regular meeting of the Anaheim Redevelopment Agency held on the 10th day of
September, 1985, by the following vote of the members thereof:
AYES: AGENCY MEMBERS: Kaywood, Bay, Pickler, Overholt and Roth
NOES: AGENCY MEMBERS: None
ABSENT: AGENCY MEMBERS: None
AND I FURTHER CERTIFY that the Chairman of the Anaheim Redevelopment Agency
signed said Resolution on the 10th day of September, 1985.
IN WITNESS WHEREOF, I have hereunto set my hand and seal this 10th day of
September, 1985.
L A-"-V -1f.11
SECRETARY OF THE ANAHEIM REDEVELOPM GENCY
(SEAL)
ka
E XHIBIT A
PROJECT: (DESCRIPTION AND ACCOUNT NUMBER)
Demolition and site clearance of the following Agency properties.
to wit:
designated as Contract No. D84 -3
AGENCY
ITEM
STREET ADDRESS
BLOCK /PARCEL
1.
202 N. Olive Street
9/20
2.
512 E. Chartres Street
10/14
3.
516 E. Chartres Street
10/15
4.
South Side of Chestnut Street
15/9
between Harbor Boulevard and
Helena Street extending south
approximately 125 feet
5.
423 W. Broadway
15/10
6.
310 and 311 W. Oak Street; and
16/8
7.
adjoining Parking Lot south side
16/10
of building to Chestnut Street
8.
307 W. Chestnut, 125 S. Clementine,
16/9
117 S. Clementine
9.
310 W. Chestnut. 204 S. Helena
16/12
10.
309 W. Third Street
16/13
11.
203 S. Clementine Street
16/14
12.
207 S. Clementine Street
16/15
13.
209 S. Clementine Street
16/16
14.
217 S. Clementine Street
16/17
15.
221 S. Clementine Street
16/18
16.
303 W. Broadway
16/19
17.
307 W. Broadway
16/20
18.
313 W. Broadway
16/21
19.
314 and 316 W. Third. 315 W.
16/22
Broadway
20.
118 S. Clementine Street
17/8
21.
210 W. Oak Street
17/7
22.
135 S. Lemon Street
17/6
23.
200 S. Clementine Street
17/9
24.
217 -221 W. Third Street
17/14
25.
218 S. Clementine Street
17/16
26.
221 W. Broadway
17/21
27.
130 S. Lemon Street; and
18/18
28.
adjoining parking lot south
18/19
side of building to Chestnut Street
29.
126 S. Philadelphia Street
21/21
30.
512 E. Lincoln Avenue
23/3
31.
924 E. Lincoln Avenue
26/7
32.
211 S. Bush Street
26/15
designated as Contract No. D84 -3