ARA1985-025RESOLUTION NO. ARAB-5-25
A RESOLUTION OF THE ANAHEIM REDEVELOPMENT AGENCY
ACCEPTING THE COMPLETION AND FURNISHING OF ALL
PLANT, LABOR, SERVICES, MATERIALS AND EQUIPMENT
AND ALL UTILITIES AND TRANSPORTATION INCLUDING
POWER, FUEL AND WATER, AND THE PERFORMANCE OF
ALL WORK NECESSARY TO COMPLETE A WORK OF
IMPROVEMENT - CONTRACT NO. D85 -1.
(Three D Service Company)
WHEREAS, the Anaheim Redevelopment Agency did award a
contract for furnishing all plant, labor, services, materials and
equipment and all utilities and transportation, including power,
fuel and water, and performing all work necessary to construct and
complete in a good and workmanlike manner in strict accordance
with the specifications, plans and drawings for the following
described work of improvement, to wit:
Demolition and removal of all structures, foundations
and other improvements, and complete site clearance
and grading operations on parcels of land located at
the following addresses:
AGENCY
ITEM STREET ADDRESS BLOCK /PARCEL
1. 304 E. Cypress St. 8/2
2. 911 - 913 E. Lincoln Ave. 12/15
3. 612 -1/2 E. Cypress St. 11/23
4. 903 E. Lincoln Ave. 12/17
5. 130 So. Philadelphia St. 21/20
6. 65 So. Olive St. 8/17
7. 21 So. Olive St. 8/15
8. 211 So. Olive St. 21/13
designated as Contract No. D85 -1.
AND WHEREAS, the contractor has furnished all plant,
labor, services, materials and equipment and all utilities and
transportation, and performed all work necessary for the
construction and completion, in a good and workmanlike manner, in
strict accordance with the specifications, plans and drawings of
said public improvement as specified in the detailed designs,
plans, drawings and specifications prepared by the Community
Development Department, and the contract made and entered into
with said contractor by the Anaheim Redevelopment Agency; and
WHEREAS, the Executive Director has duly certified to the
construction and completion of said public improvement hereinabove
mentioned and described, in accordance with the plans and specifi-
cations and the contract documents duly made and entered into with
said contractor; and
WHEREAS, the Anaheim Redevelopment Agency finds that said
contractor has completed said public improvement hereinabove more
particularly described in accordance with the provisions of the
contract and the contract documents, and that notice of completion
should be filed and payment of the balance due said contractor
authorized in accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the Anaheim
Redevelopment Agency that all plant, labor, services, materials and
equipment and all utilities and transportation, and the per-
formance of all work necessary to construct, install and complete
in a good and workmanlike manner, in strict accordance with the
specifications, plans and drawings therefor on file in the Office
of the Anaheim Redevelopment Agency, together with the appurten-
ances thereto, said public improvement hereinabove more particu-
larly described and set forth, in the City of Anaheim, by said
contractor, be, and the same are hereby, accepted subject, never-
theless, to all the terms, conditions and provisions of the con-
tract documents and that the balance due said contractor for said
work be paid to said contractor thirty -five (35) days from and
after final acceptance of said work as evidenced by the adoption of
this resolution, but not sooner than thirty (30) days after the
date of the filing of notice of completion, excepting only such sum
or sums as may lawfully be withheld in accordance with the
provisions of said contract and contract documents. That
acceptance by the contractor of said payments made in accordance
with said final estimate shall operate and shall be a release to
the Anaheim Redevelopment Agency, its officers, agents and employ-
ees from all claims and liabilities due the contractor for any-
thing done or furnished or withheld or for anything relating to the
work or any act or neglect of the Anaheim Redevelopment Agency, the
City of Anaheim, its officers, agents and employees, excepting only
claims against the Anaheim Redevelopment Agency for amounts
withheld by the Anaheim Redevelopment Agency at the time of such
payment.
BE IT FURTHER RESOLVED that the Chairman be, and he is
hereby, authorized to execute and file notice of completion for
said work as provided by law.
THE FOREGOING RESOLUTION is approved and adopted by the
Anaheim Redevelopment Agency this 22nd day of October, 198
4 . "/, CHAIRMAN
ANAHEIM REDEVELOPMENT AGENCY
ATTEST•
SECRETARY
ANAHEIM REDEVELOPMENT AGENCY
/fm/4279M/100885 -2-
STATE OF CALIFORNIA )
COUNTY OF ORANGE )
CITY OF ANAHEIM )
I, LEONORA N. SOHL, Secretary of the Anaheim Redevelopment Agency, do hereby
certify that the foregoing Resolution No. ARA85 -25 was passed and adopted at a , 000111
regular meeting of the Anaheim Redevelopment Agency held on the 22nd day of
October, 1985, by the following vote of the members thereof:
AYES: AGENCY MEMBERS: Kaywood, Bay, Overholt, Pickler and Roth
NOES: AGENCY MEMBERS: None
ABSENT: AGENCY MEMBERS: None
AND I FURTHER CERTIFY that the Chairman of the Anaheim Redevelopment Agency
signed said Resolution on the 22nd day of October, 1985.
IN WITNESS WHEREOF, I have hereunto set my hand and seal this 22nd day of
October, 1985.
SECRETARY OF THE ANAHEIM REDEVELOPMENT AGENCY