777 W KATELLA AVE (142)Permit Types
BLD ELE MEC
X PL M
Permit Number: BLD2025-00659
Issued: 03/25/2025
CITY OF ANAHEIM
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(714)765 -5153
www. a naheim.net(buildmg
(714)765-4626
Quarter Section: 76
Site Address: 777 W KATELLAAVE ANAHEIM, CA 92802
Legal Description: S TWP 4 RGE 10 SEC 22 T4 R10 SEC 22 POR OF W 112
APN: 08219027
Project Description: DCA- Golden Vine Winery/Little Mermaid/San Fransokyo - Food and Wine'25 - Miscellaneous: Install (7) food kiosks
and (1) refrigerator. (Install 02/19/25 - 04/23125)
Living Area: Number of Stories:
0 Valuation: 50,000.00
Garage Area
Construction Types: N/A
Carport Area:
Occupancy Groups:
Balcony / Deck Area
Fire Sphnklered:
Coal Roof:
Total Fees paid for Permit: 997.00
People Associated with Project:
Permit Applicant PAYTON BEABER
1200 N. Miller St Anaheim, CA 92806
Owner WALT DISNEY PARKS AND RESORTS US INC
PO BOX 313
Engineer KENNETH E AGEE
3452 E FOOTHILL 626-432-5850200101171447134090 PASADENA, CA 91107
Type Electrical Fixtures Oty Type Plumbing Fixtures Qty Mechanical Fixtures Qty
The permit shall expire by limitation and become null and void H the building or work has not passed final inspection 365 days from the
date of permit issuance. A new permit is required to commence or continue work.
P�pHEIM �q<
City of Anaheim p4 iO
Building Division i
>
0V/yD ED 1
Do not occupy this building until the final inspections have been made.
FINAL INSPECTIONS
DATE
INSPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
Electrical Final
Plumbing Final
Mechanical Final
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-6126
INSPECTION I DATE
I INSPECTOR
Fire Sprinkler (ONLY) (714) 765-5041
Do not pour concrete until the following applicable items have been signed:
Fire Dept. Final (714) 765-5041
Plumbing (Ground/Underfloor Drain Waste)
Water Engineering (714) 765-4591
Electrical Ground Electrode/Ufer
Sub LisVBus. Lic. (714) 765-5194 (Allow 10 business days)
Setback/Forms/Trenches (Footings)
COA/Migation Measures
Do not install subfloor or pour floor slab until the follwing applicable items have been
sioned
Building Final (714 765-5153)
Last Inspection -Final Only After Above Completed
1�
-r1r
N
Plumbing (Ground/Underfloor Water)
Underfloor Rough Gas
PARTIAL INSPECTIONS
Building Inspections
Mechanical (Groundwork)
Electrical (Underground Conduit)
Pre -slab (Compaction/Membrane Reinf.)
Floor (JoistlGirders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been sioned*
1st Floor Shear
Firesprinkler (Rough) (Fire Dept.)
Mechanical Inspections
2nd Floor Shear
Roof (Sheathing/Diaphragm/Frame)
Masonry (Reinf./Bond Beam/Pre-Grout)
Rough Plumbing (Top Out)
Rough Duct (Mechanical)
Rough Mechanical
Rough Electrical
Rough COA/Mitagation Measures
Plumbing Inspections
Framing (Only after Plbg_ Ele.. Mec. 8 Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed.
Drywall
Drywall Penetrations (Ele, Mec & Plbg)
Interior Lath
Exterior Lath
Electrical Inspections
Electrical Service Meter -(Meter will be set within 2-3
business days after approval) Excludes New
Qnngriirfinn
Exterior Plaster (Brown Coat)
T-Bar (Struct., Ele., or Mec.)
Grease Interceptor
(Do not backfill unipgs sinned off I
Sewer
Water Engineering Backflow (Testable Only)
Water Service
laq
W H E E L E R & G R A Y, I N C
CONSULTING ENGINEERS
Field Observation Report
BLD2025-00659
DATE: February 27, 2025
SUBJECT: Food and Wine Festival - 2025
Disney's California Adventure - Disneyland Resort
777 W. Katella Ave, Anaheim, CA 92802
FROM: Ken Agee Phone #: (626) 893-4672
REMARKS:
A structural observation was performed on February 27, 2025, at the project site in order to
review the installation of the temporary booths, pergolas and refrigerators at the Disneyland
Resort installed for the Food and Wine Festival. Here are the comments in regards to the
construction:
1. The installation is constructed and installed in accordance with the approved design
drawings and subsequent approved revisions.
300 S. HARBOR BLVD., SUITE 1010 • ANAHEIM • CALIFORNIA • 92805 • (714) 937-9100