1177 W LOCUST AVE (4)Permit Types
BLD ELE MEC PLM
X X
Permit Number: BLD2025-01039
Issued: 04/14/2025
CITY OF ANAHEIM
BUILDING DIVISION
200 S. ANAHEIM BLVD.
(714) 765-5153
F ANAHEIM CALIF
50
www.anaheim.net/building
(714)765-4626
Quarter Section: 64
Site Address: 1177 W LOCUST AVE ANAHEIM, CA 92802
Legal Description: N TR 1394 BLK LOT 26
APN: 03629112
Project Description: Residential Remodel: To install washer/ dryer & drywall throughout garage with electrical.
Living Area:
Garage Area:
Carport Area:
Balcony/ Deck Area:
Cool Roof
People Associated with Project:
Number of Stories:2 Valuation:
Construction Types:
Occupancy Groups:
Fire Sprinklered:
Total Fees paid for Permit:
OUNDEDD 1851
5,000.00
VB
992.65
Owner KUNG, HOWARD
Type Electrical Fixtures
Receptacle, switches, lights
Qty
1177 W LOCUST AVE
Plumbing Fixtures QtyType
Gas System (outlets)
Laundry Tray 1
Mechanical Fixtures Qty
Heating Appliances, including vent
The permit shall expire by limitation and become null and void if the building or work has not passed final inspection 365 days from the
date of permit issuance. A new permit is required to commence or continue work.
City of Anaheim
Building Division
OF ANAHEIM CALIFOВ
FOUNDED 181851
Do not occupy this building until the final inspections have been made.
INSPECTION DATE INSPECTOR
Do not pour concrete until the following applicable items have been signed:
Plumbing (Ground/Underfloor Drain Waste)
Electrical Ground Electrode/Ufer
Setback/Forms/Trenches (Footings)
6/9/25
FINAL INSPECTIONS DATE INGPECTOR
All applicable items below must be signed before utilities are released
Final Gas Test
Electrical Final 6/1025 JAM
Plumbing Final 6/10/20 JA
Mechanical Final 이어 JAM
Cross Connection Control (714) 765-4280
Engineering Final (714) 765-5126
Fire Sprinkler (ONLY) (714) 765-5041
Fire Dept. Final (714) 765-5041
JAM Water Engineering (714) 765-4591
Do not install subfloor or pour floor slab until the follwing applicable items have been
signed:
Plumbing (Ground/Underfloor Water)
Underfloor Rough Gas
Mechanical (Groundwork)
Electrical (Underground Conduit)
Sub List/Bus. Lic. (714) 765-5194 (Allow 10 business days)
COA/Migation Measures
Building Final (714 765-5153)
Last Inspection-Final Only After Above Completed 25 JAM.
PARTIAL INSPECTIONS
Building Inspections
Pre-slab (Compaction/Membrane Reinf.)
Floor (Joist/Girders)
Underfloor Insulation (Raised Foundation Only)
Floor Nailing (Raised Foundation Only)
2nd Floor (Floor Nailing)
Do not cover or conceal the work below until the following applicable items have
been sianed:
1st Floor Shear
Firesprinkler (Rough) (Fire Dept.)
2nd Floor Shear
Roof (Sheathing/Diaphragm/Frame)
Mechanical Inspections
Masonry (Reinf./Bond Beam/Pre-Grout)
Rough Plumbing (Top Out)6/9/25 JAM
Rough Duct (Mechanical)
Rough Mechanical 6/9/25 JAM
Rough Electrical bja/25 JAM
Rough COA/Mitagation Measures Plumbing Inspections
Framing (Only after Plbg., Ele., Mec. & Fire)
Insulation (Sound/Energy)
Do not tape or plaster until the following applicable items have been signed:
Drywall
Drywall Penetrations (Ele, Mec & Plbg)
Interior Lath
Exterior Lath Electrical Inspections
Electrical Service Meter-(Meter will be set within 2-3
business days after approval) Excludes New
Construction
Exterior Plaster (Brown Coat)
T-Bar (Struct., Ele., or Mec.)
Grease Interceptor
(Do not backfill unless sianed off)
Sewer
Water Engineering Backflow (Testable Only)
Water Service